Construction Practice for Concreting on Decking
B-1 Placing Concrete
B-1.1 Preparation
Prior to beginning work on the decking, guardrails shall be in position at all perimeters, internal edges and voids. The positions of any props (and back props) shall be checked against the details shown on the decking layout drawings to ensure that adequate support has been provided.
B-1.2 Cleaning the Decking
The surface of the decking shall be reasonably free of dirt, oil, etc, prior to concreting.
B-1.3 Construction Joints
Although there is no technical limitation to the area
that may be concreted, the usual pour area is up to . Where the limits of the pour do not coincide with permanent slab edges, construction joints are used to define the extent of the pour.
The locations and details of the construction joints may have an effect on the cracking. The layout and details of the joints shall be determined by the structural designer. For example, when brittle bonded finishes are used, the relationship between the joints in the concrete and the joints in the finishes shall be considered at the outset, to reduce the risk of cracking in undesirable locations.
Where possible, the construction joints shall be located close to butt joints in the decking. Where shear connectors are used, it is preferable to create the joint to one side of the line of the shear connectors, to ensure
sound concrete around the studs. If the construction joint cannot be made near a butt joint, it is suggested that no more than one-third of the decking span from a butt joint shall be left unpoured. Concreting shall not be stopped within a sheet length, because excessive deflections may occur when the loads on a continuous decking sheet are not balanced on either side of the intermediate support beam.
Stop ends, usually in the form of timber or plastic inserts, are used to create the construction joints. As with all the joints and ends of the decking, they shall be checked for potential grout loss.
B-1.4 Reinforcement
All reinforcement shall be properly supported so that it does not get displaced during concreting. Plastic stools, loops or preformed mesh may be used as 'chairs', but not plastic channels, which can induce cracking. Chairs shall be robust. In particular, the handling and movement of concrete carrying pipes during pumping can cause significant local impacts on the reinforcement.
The reinforcement that has been fixed shall be checked. Particular attention shall be given to checking any additional bar reinforcement, such as may be needed around openings.
B-1.5 Grout Loss
The decking joints shall be closely butted and exposed ends shall be ‘stopped’ with proprietary filler pieces to avoid grout loss. Gaps greater than 5 mm shall be sealed.
B-2 Placement
B-2.1 Concrete shall be placed in a way that minimizes the permanent deformation of the decking. This is particularly important for spans greater than 3 m. When concreting is progressed in the same direction as the span of the decking (that is parallel to the decking ribs), it shall be placed first over supports where the decking is continuous, followed by the mid-span region and finally the areas above the end supports. When concreting is progressed in a direction perpendicular to the decking span (that is transverse to the decking ribs), it shall be placed first at the edge where a decking sheet is supported by the underlap of an adjacent sheet. This helps to ensure that longitudinal seams between panels remain closed.
The concrete shall be well compacted, particularly near and around any shear connectors. This may be done using a vibrating beam, which may require adequate supports at either ends, or an immersion needle vibrator. Hand tamping is not recommended as a way of
compacting the concrete. For slim floors with deep decking, or for other partially encased beams, a needle vibrator is needed to ensure proper concrete flow around the beams, beyond the ends of the decking.
B-2.2 Concrete Pumping
Pumping may be adopted for both normal and lightweight concrete mixes. Flow rates in the order of to of concrete per minute may be achieved, although, clearly, the longer the pump lines and the higher the concrete is to be pumped, the slower the operation. A pump may normally lift the concrete up to . Secondary pumps, placed at intermediate levels, may be necessary for higher lifts.
Pumplines are normally 150 mm in diameter and are assembled in segments. As the force exerted at bends may be significant, straight line pumping is preferred. The lines shall be supported on timber blocks at intervals of 2 m to 3 m. Resetting of pumplines is required at frequent intervals as the pour progresses. This means that the outlet pipe shall be moved frequently and carefully so that concrete heaping is minimized. A minimum of two operatives are necessary for this operation, one to hold and manoeuvre the outlet pipe, the other to shovel away excess concrete. No more than 4 workmen shall be present around the pipe outlet during pumping, because of the potential for overloading the decking. The concrete shall not be dropped from the outlet pipe onto the decking from a height of more than about 1 m.
B-2.3 Skip and Barrow
Placing concrete from a skip hung from a crane may be difficult because of obstructions from beams and decking at higher floor levels. However, despite being time consuming, it is sometimes efficient to use the skip and barrow technique for small infill bays.
Skips shall have a means of controlling the rate of discharge, and shall not be discharged from more than 0.5 m above the decking or barrow. When discharging into a barrow, the barrow shall be supported by thick (about 30 mm) boards covering a 2 m x 2 m area, or by a finished part of the slab. Either provision limits impact loads. Barrows shall be run over thick boards placed on the mesh, which shall be supported locally.
B-3 Finishing, Curing and Drying
If power floating is to be carried out, this shall be done within 2 h to 3 h of casting. This allows time for the concrete to harden sufficiently.
As the concrete is only exposed on one surface of a composite floor, it can take longer than a traditional reinforced concrete slab to dry out.
PART 6 STRUCTURAL DESIGN — SECTION 7 PREFABRICATION, SYSTEMS BUILDING AND MIXED/COMPOSITE CONSTRUCTION: 7B SYSTEMS BUILDING AND MIXED/COMPOSITE CONSTRUCTION
LIST OF STANDARDS
The following list records those standards which are acceptable as ‘good practice’ and ‘accepted standards’ in the fulfilment of the requirements of the Code. The latest version of a standard shall be adopted at the time of enforcement of the Code. The standards listed may be used by the Authority for conformance with the requirements of the referred clauses in the Code.
In the following list, the number appearing in the first column within parentheses indicates the number of the reference in this Subsection.
IS No. Title
(1) 3935 : 1966 Code of practice for composite construction
(2) 3201:1988 Criteria for the design and construction of precast—Trusses and purlins (first revision)
(3) 6332 : 1984 Code of practice for construction of floor and roofs using precast doubly-curved shell units (first revision)
10297: 1982 Code of practice for design and construction of floors and roofs using precast reinforced/ prestressed concrete ribbed or cored units
| IS No. | Title |
|---|---|
| 10505 : 1983 | Code of practice for construction of floors and roofs using precast reinforced concrete waffle units |
| 13994 : 1994 | Code of practice for design and construction of floor and roof with precast reinforced concrete planks and RC joists |
| 14142 : 1994 | Code of practice for design and construction of floors and roofs with prefabricated brick panel |
| 14215 : 1994 | Code of practice for construction of floor and roof with RC channel units |
| 14242 : 1994 | Code of practice for design and construction of roof with L-Panel units |
| (4) 11447 : 1985 | Code of practice for construction with large panel prefabricates |
| (5) 6061 | Code of practice for construction of floor and roof with joists and filler blocks: |
| (Part 1) : 1971 | With hollow concrete filler blocks |
| (Part 2) : 1981 | With hollow clay filler blocks (first revision) |
PART 6 STRUCTURAL DESIGN
Section 8 Glass and Glazing