General Recommendations for Steelwork Tenders and Contracts
F-1 General
F-1.1 The recommendations given in this annex are in line with those generally adopted for steelwork construction and are meant for general information.
F-1.2 These recommendations do not form part of the requirements of the Section and compliance with these is not necessary for the purpose of complying with this Section.
F-1.3 The recommendations are unsuitable for inclusion as a block requirement in a contract, but in drawing up a contract the points mentioned should be given consideration.
F-2 Exchange of Information
Before the steelwork design is commenced, the building designer should be satisfied that the planning of the building, its dimensions and other principal factors meet the requirements of the building owner and comply with regulations of all authorities concerned. Collaboration of building designer and steelwork designer should begin at the outset of the project by joint consideration of the planning and of such questions as the stanchion spacing, materials to be used for the construction, and depth of basement.
F-3 Information Required by the Steelwork Designer