a) Schedule of stanchions giving sizes, lengths and typical details of brackets, joints, etc;
b) Plan of grillages showing sizes, lengths and levels of grillage beams and particulars of any stiffeners required;
c) Plans of floor beams showing sizes, lengths
PART 6 STRUCTURAL DESIGN — SECTION 6 STEEL
and levels eccentricities and end moments. The beam reactions and details of the type of connection required should be shown on the plans;
d) Plan of roof steelwork. For a flat roof, the plan should give particulars similar to those of a floor plan. Where the roof is pitched, details should be given of trusses, portals, purlins, bracing, etc;
e) The steelwork drawings should preferably be to a scale of 1 to 100 and should give identification marks against all members; and
f) Particulars of holes required for services, pipes, machinery fixings, etc. Such holes should preferably be drilled at works.
a) Supply of materials;
b) Weight of steelwork for payment;
c) Wastage of steel;
d) Insurance, freight and transport from shop to site;
e) Site facilities for erection;
f) Tools and plants;
g) Mode and terms of payment;
h) Schedules;
j) Force Majeure (sections and provisions for liquidation and damages for delay in completion); and
k) Escalation sections.
F-5 Detailing
In addition to the number of copies of the approved drawings or details required under the contract, dimensioned shop drawings or details should be submitted in duplicate to the engineer who should retain one copy and return the other to the steel supplier or fabricators with his comments, if any.
F-6 Time Schedule
As the dates on which subsequent trades can commence, depend on the progress of erection of the steel framing, the time schedule for the latter should be carefully drawn up and agreed to by the parties concerned at a joint meeting.
F-7 Procedure on Site
The steelwork contractor should be responsible for
the positioning and levelling of all steelwork. Any checking or approval of the setting out by the general contractor or the engineer should not relieve the steelwork contractor of his responsibilities in this respect.
F-8 Inspection
References may be made to the accepted standard [6-6(41)] for general guidance.
F-8.1 Access to Contractor's Works
The contractor should offer facilities for the inspection of the work at all stages.
F-8.2 Inspection of Fabrication
Unless otherwise, agreed, the inspection should be carried out at the place of fabrication. The contractor should be responsible for the accuracy of the work and for any error, which may be subsequently discovered.
F-8.3 Inspection on Site
To facilitate inspection, the contractor should during all working hours, have a foreman or properly accredited charge hand available on the site, together with a complete set of contract drawings and any further drawings and instructions which may have been issued from time to time.
F-9 Maintenance
F-9.1 General
Where steelwork is to be encased in solid concrete, brickwork or masonry, the question of maintenance should not arise, but where steelwork is to be housed in hollow fire protection or is to be unprotected, particularly where the steelwork is exposed to a corroding agent, the question of painting or protective treatment of the steelwork should be given careful consideration at the construction stage, having regard to the special circumstances of the case.