12.1 Construction Inspection
Prior to Performance Testing, verify and document the following:
(a) System controls are wired correctly to ensure economizer is fully integrated (i.e. economizer will operate when mechanical cooling is enabled).
(b) Economizer lockout control sensor location is adequate (open to air but not exposed to direct sunlight nor in an enclosure; away from sources of building exhaust; at least 8 meters away from cooling towers).
(c) System is provided with barometric relief, relief fan or return fan to control building pressure.