Schedules are used to describe the percentage of a maximum design value of an internal load that is applicable during a particular time period, usually one hour, i.e., lighting power density, miscellaneous equipment (plug load) power density, occupant load or any other significant load thermostat set point (s) applicable in this time period, or the availability (on/off), and control operation of a system or system component, e.g., cooling systems, fans, chillers, or pumps. Schedules have a large impact on the overall energy consumption. Designers are required to specify Weekday, Saturday, Sunday, and Holiday operation in each schedule. An example for Weekday schedules in an office building is shown below.
The ECBC allows designers to select reasonable or typical schedules for the building. In all cases, the schedules for the Proposed Design and the Standard Design shall be identical. This means that the Proposed Design may not take advantage of scheduling changes. It further means that any equipment in the Proposed Design that saves energy by altering operating patterns or profiles must be modeled explicitly; it is not sufficient simply to assume a schedule
change and use that to account for the electricity savings.
An example is daylighting controls, which reduce lighting power when daylight is available in a space. The Proposed Design must simulate the actual performance of the daylighting control in response to daylight availability, rather than the simulator simply assuming some schedule change that arbitrarily reduces lighting power during daylight hours. Another example of equipment that must not be modeled by reducing operating hours in the Proposed Design are occupancy-sensing controls that turn off equipment when not needed. While this type of equipment might well be installed because of the owner’s conviction that it is a good investment, there is no credit for it under the WBP method.
In selecting the schedules, it is prudent to consider the likely long-term operation of the building. For example, if a new school will initially operate on a traditional schedule, but the school district has a policy of shifting its schools over to year-round operation, then it would be prudent to apply a year-round schedule in the WBP method modeling. The selected schedules should likewise not intentionally misrepresent the operation of the building. If a grocery store chain keeps its stores open 24 hours a day, it would be inappropriate to use a 12-hour-a-day operating schedule in the modeling.