The Code requires that the provision for renewable is clearly shown in the design and construction documents in terms of space, structure as well as supporting services like electrical and plumbing.
The following shall be indicated in design and construction documents:
(a) Location for inverters and metering equipment,
(b) Pathway for routing of conduit from the REGZ to the point of interconnection with the electrical service,
(c) Routing of plumbing from the REGZ to the water-heating system and,
(d) Structural design loads for roof dead and live load.
DEFINITIONS, ABBREVIATIONS, & ACRONYMS
8.DEFINITIONS, Abbreviations, and Acronyms