(a) Services exceeding 1000 kVA shall have permanently installed electrical metering to record demand (kVA), energy (kWh), and total power factor. The metering shall also display current (in each phase and the neutral), voltage (between phases and between each phase and neutral), and total harmonic distortion (THD) as a percentage of total current.
(b) Services not exceeding 1000 kVA but over 65 kVA shall have permanently installed electric metering to record demand (kW), energy (kWh), and total power factor (or kVARh).
(c) Services not exceeding 65 kVA shall have permanently installed electrical metering to record energy (kWh).
(d) In case of tenant based building, metering should be provided at a location from where each tenant could attach the services.
| 120 kVA to 250 kVA | Greater than 250 kVA | |
| Minimum requirement for metering of electrical load | ||
| Energy kWh | Required | Required |
| Demand kVA | Required | Required |
| Total power factor | Required | Required |
| Minimum requirement for separation of electrical load | ||
| HVAC system and components | Required | Required |
| Interior and Exterior Lighting * | Not required | Required |
| Domestic hot water | Not required | Required |
| Plug loads | Not required | Required |
| Renewable power source | Required | Required |
| Mandatory requirement for building type over the requirement stated above | ||
| Shopping Complex | Façade lighting | Elevator, escalators, moving walks |
| Business | Data centers | |
| Hospitality | Commercial kitchens | |
* Hotel guestrooms and hospital in patient areas are exempted from the lighting sub-metering requirements.