building are as follows:
If there is new construction that comes under the ECBC scope and it is part of the existing building but will be excluded from the Proposed Design, then those parts must comply with the Code’s applicable prescriptive requirements.
The excluded parts of the existing building must be served by HVAC systems that are completely independent of the systems or building components being modeled for the Proposed Building.
There should not be any significant energy flows between the excluded parts of the
building and the modeled parts. Rephrasing, the design space temperature, HVAC system operating set points, and operating and occupancy schedules on both sides of the boundary between the included and excluded parts must be the same. If the excluded portion of the building is a refrigerated warehouse and the included portion is an office, this condition would not be met, because there would be significant energy flows between them.