Pre-commissioning check points and safety precautions are given under Part1/Sec 17. It is important to follow the guidelines before putting the installation in regular use.
11.1 Before commissioning or charging any electrical installation, it shall be ensured that all pre-commissioning tests are conducted as per Part1/Section 17 on site and the obtained results are documented.
11.2 Certificates of satisfactory routine tests from manufacturer and under certain cases type and acceptance test from accredited laboratory, wherever necessary, shall be available. Documentation of such test report/certificates, duly signed by competent person, shall be preserved as records.
11.3 In case of charging the installation on completion of work and after returning the permit, removal of the earthing and short-circuiting devices shall be carried out in the reverse order to that adopted while de-energizing. The conductor shall not be touched after the earthing device is removed.
11.4 Settings of all relays, protection devices shall be done properly with respect to designed load, fault current, correlated short circuit withstand capacity, tripping time with desired coordination. Simulations shall be performed for testing and certificate from the appropriate person, agency; mentioning all details and schedule of settings, and the documents shall be preserved as record.
11.5 In case of cables above 650V, ‘high pot’ testing shall be carried out before charging. After testing, care shall be taken to discharge cable properly owing to the dielectric absorption, particularly prominent in DC voltage testing.
11.6 Inspection shall be carried out, and there shall no objectionable points/remarks in the Inspection Reports (refer schedule IV, Forms I/II/III from CEA Safety Regulations 2010). Any statutory permission/approval if required under CEA safety regulations 2010 (see 5.5) shall be complied with before testing/energising the installation.
11.7 Electricity supplier shall observe obligations as per CEA Reg. 16 (Earth terminal at consumer’s premises), Reg. 31 (testing of consumer’s installation) and Reg. 33 (Precautions against leakage before connection) before release of supply.
11.8 No person shall apply test voltage to any mains unless he is authorized, has fulfilled conditions of permit-to-work and has notified all persons working on the mains of the proposed application of test voltage. If any part which becomes alive, the person-in-charge of the test shall take due precautions to ensure that the exposed live portion does not constitute danger to any person and limited approach boundary is protected. It should also be ensured before the application of test voltage, that no other permit-to-work has been issued for working on these mains/lines.
11.9 Post commissioning check sheets and as-built/record drawings of completed work shall be prepared showing all details like layout, distribution diagrams, capacities of switchgears, their protections, cables etc. This shall form part of documentation to be preserved and handed over to the care taker. This record shall be readily available for persons maintaining electrical installation and for presenting to concerned authorities, whenever, called for.