11.1 A period of two to four weeks is normally sufficient for return of tenders. This should be extended, if large numbers of escalators/moving walks or special requirements are involved. The enquiry documents should be kept to the essential minimum, and should be strictly confined to material relevant to the escalators/moving walk works and to the particular project concerned.
When enquiring for and ordering the escalators/moving walks, the particulars given below should be furnished:
a) Type(s) of escalator/moving walk;
b) Number of escalators/moving walks;
c) Location of escalators/moving walks (indoor or outdoor);
d) Capacity/usage type (persons per day/heavy duty, medium duty, light duty);
e) Angle of inclination, in degree;
f) Rise (travel), in m;
g) Nominal speed, in m/s;
h) Step width, in m;
j) Number of flat steps (2 or 3);
k) Balustrade details;
m) Construction, design, finishes details;
n) Escalator/moving walk lighting details;
p) Electric supply: power volts a.c./d.c.; phase; cycles; wire system;
q) Proposed date for commencement on site;
r) Additional items, if required;
s) Details of maintenance, schedule and circuit diagram where so specified; and
t) Details of voice announcements, visual contrast, tactile indicators and warning signage.
11.2 Additional Items
The enquiry should state any additional items required beyond those specified in good practice [8-5B(2)], such as interface requirements, seismic design, etc.
11.3 Finishes
Finishes should be specified at the enquiry stage or provisional sums should be included for them. Finishes to be considered may include step lighting, handrail colour, handrail lighting, balustrade material, step colour, truss cladding details (weight to be considered).
11.4 Inclusions and Exclusions
A number of peripheral items are associated with escalators/moving walk installation, of which some should always be provided by the builder and some are best included by the manufacturer. The requirements vary to some extent with the type of installation.
It is important that the limits of responsibility are clearly understood, and the enquiry documents should be specific in this respect.
The escalators/moving walk manufacturer should include items, such as,
a) tracks,
b) drive unit,
c) controller,
d) broken chain,
e) stop switches at both ends,
f) balustrade,
g) handrail,
h) steps/step drive assembly,
j) saree/skirt guard,
k) step demarcation lights,
m) missing steps,
n) comb plate,
p) flat steps,
q) comb plate switches/skirt switches,
r) landing steps (anti-slip material),
s) truss,
t) guarantee of equipment, and
u) scaffolding for installation.
The escalators/moving walk manufacturer should exclude the supply and fixing of the items or as per the contract conditions as follows:
-
Hoisting hook/beam fixing,
-
Truss cladding,
-
Temporary guarding,
-
Cutting and making goods,
-
Working lights/permanent electricity supplies, and
-
Site painting of steel work.
For more detailed discussion of the requirements for site preparation and work by other trades, reference should be made to relevant provisions of the Code and other good practices.
Facilities for the use of the main contractor's crane should be provided to assist in installing heavy equipment in addition to other unloading facilities on site in the course of erection. The main contractor should be instructed to include these facilities in his own bill of quantities.
11.5 Site Programme
The enquiry should indicate as accurately as possible the contract programme as it affects the manufacturer, in particular the target date for completion, construction schedule, site preparedness, the availability of crane for hoisting, coordination details (with other contractors like BMS interfacing, CCTV interfacing, etc).