4.2.1 Cooling and heating load estimate shall be carried out prior to design and installation of HVAC equipment. Calculation of cooling and heating load shall take into account the following factors:
a) Recommended indoor temperature, relative humidity, air velocity, mean radiant temperature, clothing and activity;
b) Outside design conditions as specified in 5;
c) Details of building construction and orientation of exposures of building components;
d) Fenestration area, thermal properties and shading factors;
e) Occupancy — Number of people and their schedule of activities;
f) Ventilation — Requirement for fresh air;
g) Infiltration, air leakage;
h) Internal load — Equipment, computer/server and lighting;
j) Effective volume; and
k) Occupancy, lighting and equipment schedule.
4.2.2 The design of air conditioning, heating and mechanical ventilation system and its associated controls shall also take into account the following:
a) Nature of application,
b) Permissible control limits,
c) Fire safety,
d) Opportunities for heat recovery,
e) Energy efficiency,
f) Filtration standard,
g) Hours of use,
h) Suitable diversity factor based on usage,
j) Outdoor and indoor air quality, and
k) Availability of make-up water for cooling towers.
4.2.3 Due consideration shall also be given to air conditioning load encountered during off-peak hours
including night time and weekend/holidays.
4.2.4 Consideration shall be given to the anticipated future changes, permanent or temporary, in building load and the system shall be so designed that maximum operational efficiency is maintained throughout.
4.2.5 Special applications like hospitals/operating theatres, computer rooms, data centers and telecommunication rooms, clean rooms, laboratories, libraries, museums/art galleries, sound recording studios, etc, shall be handled differently.
4.2.6 Computer based hourly load calculation and energy simulation tools may be used for HVAC equipment sizing and to identify effect of various energy conservation measures on energy consumption.