BUREAU OF INDIAN STANDARDS
- FOREWORD .... 3
Book Supply Bureau Under the License from BIS for LARSEN AND TOUBRO CONSTRUCTION - MANAPAKKAM, CHENNAI ON 17-03-2017 09:00:59 (123.63.24.35) valid up
- SCOPE .... 7
- TERMINOLOGY .... 7
- GENERAL .... 7
Construction Management
4 CONSTRUCTION PROJECT MANAGEMENT ... 8
Construction Planning and Site Management
- 5 PLANNING ASPECTS ... 17
Construction Practices
- 6 CONSTRUCTION CONTROL AND PRACTICES ... 19
- 7 TEMPORARY WORKS ... 21
- 8 STORAGE, STACKING AND HANDLING PRACTICES ... 23
Safety in Construction
- 9 SAFETY IN CONSTRUCTION OF ELEMENTS OF A BUILDING ... 34
- 10 SAFETY IN DEMOLITION OF BUILDINGS ... 52
Repairs, Retrofitting and Strengthening of Buildings
- 11 MAINTENANCE MANAGEMENT ... 57
- 12 PREVENTION OF CRACKS ... 57
- 13 REPAIRS AND SEISMIC STRENGTHENING OF BUILDINGS ... 58
Habitat and Welfare Requirements for Workers
- 14 HABITAT AND OTHER WELFARE REQUIREMENTS FOR CONSTRUCTION WORKERS ... 59
- ANNEX A CHECK LIST FOR STACKING AND STORAGE OF MATERIALS ... 63
- LIST OF STANDARDS ... 64
This Code (Part 7) covers construction project management; construction planning, site management and building construction practices; storage, stacking and handling of materials; and safety of personnel during construction operations for all elements of a building and demolition of buildings; and habitat and welfare requirements for workers. It also covers guidelines relating to repairs, retrofitting and strengthening of buildings.
The principles enunciated in the various sections of this Part are to be ultimately utilized and implemented in the physical construction of the buildings with the required infrastructure. This would require sound construction practices and efficient management thereof in order to ensure that the implementation of the project is carried out within the estimated cost and planned period to the required quality standards and in a safe and sustainable manner. Workers in large number, both skilled and unskilled, are engaged in the innumerable construction works. Due to increased tempo of such a building activity and large scale mechanization, hazards of accidents could increase considerably. It is, therefore, imperative that adequate safety rules are laid down for every phase of construction work. It is also important to give due cognizance to habitat and welfare requirements of workers at construction site. This Part also deals with these aspects.
Planning the various construction operations before hand and making adequate arrangements for procurement and storage of materials, and the machinery to get work done is as important as carrying out these construction operations in accordance with good practice. Lack of planning or defective planning may result in avoidable delay in the completion of work and consequently increased hazards from the point of view of fire, health and structural soundness. This Part covers provisions in this regard.
A construction project is an endeavour undertaken by a project team on behalf of owner/client to create a built facility suited to the defined functional objectives. From inception to commissioning, the project goes through various distinct stages leading to progressive achievement of project objectives. Each stage involves specific inputs, processes (both technical and managerial) and deliverables. Typically, the life cycle of a project from commencement to completion involves the following stages:
a) Project formulation and appraisal — Inception, feasibility and strategic planning;
b) Project development — Project brief development, planning and design, finalization of proposals, procurement strategy, construction documentation including tender drawings, working drawings, specifications, cost estimates, bills of quantities, procurement documents;
c) Planning for construction — Sequencing of project components, planning tools, resource planning and time cost trade off;
d) Tender action — Open competitive bidding/pre-qualification of agencies, issue of tender documents, evaluation of bids, negotiation if required and award of work;
e) Construction — Execution, monitoring, control, work acceptance; and
f) Commissioning and handing over — Contractual closeout, financial closeout, defect liability commencement, facility handing over.
The distinct features of a construction project include the temporary nature of the organizations involved, the evolutionary process of project deliverables during project development stages and the unique output of the built facility. As a result of these features, unless there is efficient and effective project management, a construction project is faced with challenges of uncertainties leading to time over-runs, cost over-runs, changes in project parameters, loss of quality and inability to meet the functional objectives. While technical soundness of a proposal is an important aspect of a construction project, the management aspects, which involve techno-legal, financial and other issues, have also a significant role in the success of a project. Therefore, management functions and technical processes in a construction project need to be integrated towards achieving project objectives. Top management commitment plays an important role in harmoniously achieving these project objectives. In some of the public sector projects, it may be necessary to share relevant information with public at large through appropriate
means. The overall management of a building construction project is very important to ensure that the objectives of such a project are achieved through scope management, procurement management, time management, cost management, quality management, risk management, communication management, human resources management, safety, health and environment management and integration management. This Part, therefore, gives guidelines on these areas.
The first version of this Part was formulated in 1970, which was subsequently revised in 1983 and 2005. In the first revision, information regarding handling operations that is unloading, stacking, lifting, loading and conveying of building materials, was also given along with the storage practices. Additional information regarding the use of ladders; safety requirements for floor and wall openings, railings and toe boards; piling and other deep foundations; constructions involving use of hot bituminous materials; and erection of structural steel work and concrete framed structures, etc, were included.
In the second revision, the Section 1 ‘Construction Practices’ of this Part, had been revamped to include the planning and management aspects. Further, provisions on construction using bamboo were also incorporated. The other important modifications incorporated in the second revision included comprehensive updating of the provisions with regard to stacking and storage of building materials and components, which were comprehensively covered in line with the revised IS 4082 : 1996 ‘Recommendations on stacking and storage of construction materials and components at site (second revision)’; addition of provisions of safety requirements of hoists/lifts for worker during construction; incorporation of aspects like preventive measures such as falling material hazards prevention, fall prevention, disposal of debris, fire protection, etc, with regard to safety at work site; addition of provisions regarding safety management at work sites; addition of a new section on ‘Maintenance management, repairs, retrofitting and strengthening of buildings’, covering aspects like maintenance management, prevention of cracks, and repairs and seismic strengthening of buildings; and updating of safety provisions with respect to demolition of buildings.
As a result of experience gained in implementation of 2005 version of this Part and feedback received as well as in view of formulation of new standards in the field of construction project management and construction practices and revision of some existing standards, including those on safety, a need to revise this Part was felt. This revision has, therefore, been prepared to take care of these aspects. This Part has been divided into six sections as follows, under which all technical provisions relating to their subject areas, have been given:
Section 1 Construction Management
Section 2 Construction Planning and Site Management
Section 3 Construction Practices
Section 4 Safety in Construction
Section 5 Repairs, Retrofitting and Strengthening of Buildings
Section 6 Habitat and Welfare Requirements for Workers
The significant changes incorporated in this revision include:
a) This Part has been divided into six Sections under which the provisions have been rearranged in a logical sequence;
b) Provisions on construction project management have been detailed which also now includes project formulation and appraisal.
c) Safety provisions with respect to scaffolding, piling and other deep foundations, blasting and related drilling operations, and construction involving use of hot bituminous materials have been updated;
d) A new clause on habitat and other welfare requirements for construction workers has been introduced;
e) A new clause on urban/city roads planning and construction, has been added;
f) A new clause on temporary works has been included;
g) Provisions on construction using bamboo has been shifted to Part 6 ‘Structural Design, Section 3B Bamboo, and a reference to the same has been given in this Part;
h) Provisions on maintenance management has been shifted to Part 12 ‘Asset and Facility Management’ of the Code and a reference to the same has been given in this Part; and
j) References to all the concerned Indian Standards have been updated.
Users are encouraged to employ suitable construction management software as an aid to implement provisions of
4
this Code. The guidelines may be applicable in general to all construction projects. However, for smaller projects, the applicability of various provisions may be decided appropriately by the parties concerned.
Provisions on sustainable building construction practices are covered in Part 11 ‘Approach to Sustainability’ of the Code.
The information contained in this Part is largely based on the following Indian Standards and Special Publications:
IS 3696 Safety code for scaffolds and ladders:
(Part 1): 1987 Scaffolds
(Part 2): 1991 Ladders
IS 3764 : 1992 Code of practice for excavation work (first revision)
IS 4082 : 1996 Recommendations on stacking and storage of construction materials and components at site (second revision)
IS 4130 : 1991 Safety code for demolition of buildings (second revision)
IS 4912 : 1978 Safety requirements for floor and wall openings, railing and toe boards (first revision)
IS 5121 : 2013 Code of safety for piling and other deep foundations (first revision)
IS 5916 : 2013 Safety code for construction involving use of hot bituminous materials (first revision)
IS 7205 : 1974 Safety code for erection of structural steel work
IS 7969 : 1975 Safety code for handling and storage of building materials
IS 8989 : 1978 Safety code for erection of concrete framed structures
IS 13415 : 1992 Safety code for protective barrier in and around buildings
IS 13416 Recommendations for preventive measures against hazards at work places:
(Part 1): 1992 Falling material hazards prevention
(Part 2): 1992 Fall prevention
(Part 3): 1994 Disposal of debris
(Part 4): 1994 Timber structures
(Part 5): 1994 Fire protection
IS 13430 : 1992 Code of practice for safety during additional construction and alteration to existing buildings
IS 15883 (Part 1): Guidelines for construction project management: Part 1 General 2009
IS 16601 : 2016 Guidelines for habitat and welfare requirements for construction workers
A reference to SP 62 : 1992 ‘Handbook on building construction practices (excluding electrical works)’ and SP 70 : 2001 ‘Handbook on construction safety practices’, may also be made.
All standards, whether given herein above or cross-referred to in the main text of this Part, are subject to revision. The parties to agreement based on this Part are encouraged to investigate the possibility of applying the most recent editions of the standards.
For the purpose of deciding whether a particular requirement of this Code is complied with, the final value, observed or calculated, expressing the result of a test or analysis, shall be rounded off in accordance with IS 2 : 1960 ‘Rules for rounding off numerical values (revised)’. The number of significant places retained in the rounded off value should be the same as that of the specified value in this Part.