b) Provisions relating to prefab systems have been updated.
c) Detailed provisions on diaphragm action of floor systems have been included.
d) Emulative system has been categorized and detailed with respect to its definition, analysis, design, detailing, etc.
e) Design considerations have been updated where accidental impact due to vehicles has been included.
f) Provisions and testing procedures for water tightness of joints have been included.
g) Some of the typical precast joint details have been illustrated.
h) Provisions relating to fire resistance testing of prototypes under sustained load has been provided for.
j) Connection between adjacent prefabricated members only through frictional resistance has been removed and suggestions for resistance using shear has been included.
k) Provisions on site prefabrication have been updated.
m) Guidelines (restriction on the number of components) on vertical stacking on ground have been included.
n) The time for which a chosen component of a lot to be loaded as per the load test has been modified.
p) Provisions for tolerances in erection and associated design considerations have been included.
q) An annex has been included on common defects, their causes and remedies which cover dimensional deviations, cracks, honeycombing, damages, strand slippage, alignment, etc.
The information contained in this Subsection is largely based on IS 15916 : 2010 ‘Building design and erection using prefabricated concrete — Code of practice’. Annex A provides information relating to common defects and remedies related prefabricated concrete construction.
All standards, whether given herein above or cross-referred to in the main text of this Subsection, are subject to revision. The parties to agreement based on this Subsection are encouraged to investigate the possibility of applying the most recent editions of the standards.
For the purpose of deciding whether a particular requirement of this Subsection is complied with, the final value, observed or calculated, expressing the result of a test or analysis, shall be rounded off in accordance with IS 2 : 1960 ‘Rules for rounding off numerical values (revised)’. The number of significant places retained in the rounded off value should be the same as that of the specified value in this Subsection.
7A Prefabricated Concrete