This Code (Part 0) covers guidelines to be followed for judicious implementation of the provisions of various Parts/Sections of the National Building Code of India following an integrated approach.
3.1 Buildings shall be classified as Residential, Educational, Institutional, Assembly, Business, Mercantile, Industrial, Storage and Hazardous in groups and sub-divisions as classified in Part 4 ‘Fire and Life Safety’ of the Code.
For various related provisions of buildings with respect to administration; development control rules and
general building requirements; building materials; fire and life safety; structural design; construction management, practices and safety; building and plumbing services; landscape development, signs and outdoor display structures; sustainability; asset and facility management, and other Parts/Sections of the Code may be referred to. For provisions on sustainability of buildings and built environment, reference to the concerned Part may be made, which while also referring to the other Parts/Sections as may be required, gives a comprehensive approach to sustainability.
3.2 The brief coverage in various Parts/Sections of the Code which cover detailed provisions on different aspects of development of land/building construction activity, are given in Annex A, with a view to providing an overview for the users of the Code.
For the purpose of this Part, the following definitions shall apply.
2.1 Authority Having Jurisdiction — The authority which has been created by a statute and which, for the purpose of administering the Code/Part, may authorize a committee or an official or an agency to act on its behalf; hereinafter called the ‘Authority’.
2.2 Building — Any structure for whatsoever purpose and of whatsoever materials constructed and every part thereof whether used as human habitation or not and includes foundation, plinth, walls, floors, roofs, chimneys, plumbing and building services, fixed platforms, verandah, balcony, cornice or projection, part of a building or anything affixed thereto or any wall enclosing or intended to enclose any land or space and signs and outdoor display structures. Tents/Shamianahs/Pandals, tarpaulin shelters, etc, erected for temporary and ceremonial occasions shall not be considered as building.
2.3 Owner — A person, a group of persons or a body having a legal interest in land and/or building thereon. This includes freeholders, leaseholders or those holding a sublease, who will have legal right to occupation and have liabilities in respect of safety or building condition.
In the case of lease or sublease holders, as far as ownership with respect to the structure is concerned, the structure of a flat or structure on a plot belongs to the allottee/lessee till the allotment/lease subsists.
NOTE — For the purpose of the Code, the word ‘owner’ will also cover the generally understood terms like ‘client’, ‘user’, etc.
5.1 The main functions of design team (see 4.1.1) constituted for the planning, designing and development, are as under:
a) Formalization of design brief in consultation with the owner.
b) Site survey and soil investigation.
c) Preparation of alternative concept designs, highlighting both their positive and negative aspects.
d) Selection of a concept in consultation with and with the consent of the owner.
e) Sizing the system.
f) Development of design, involving:
Integration of architecture, structure and services,
Synthesis of requirements of each discipline, and
Interaction with each other within the design team and with the owner.
g) Preparation of preliminary designs and drawings and obtaining the owners' approval.
h) Preparation of preliminary cost estimates for approval of owner.
j) Preparation of work-breakdown structure and programme for pre-construction activities.
k) Assisting client to obtain approvals of the Authority/authorities.
m) Preparation of detailed specifications and construction working drawings with integration of engineering inputs of all concerned disciplines.
n) Preparation of detailed design of each discipline for various services.
p) Peer review/proof checking of the drawings/designs in case of major/important projects, depending upon their complexity and sensitivity.
q) Preparation of detailed cost estimate.
r) Obtaining final approval of the client.
s) Preparation of bill of quantities, specifications and tender documents.
5.2 The following considerations, as may be applicable to the project, may be considered during planning, notwithstanding the other relevant aspects specifically prescribed in concerned Parts/Sections of this Code; these considerations in general are with the objective of addressing important issues like environmental protection, energy conservation, cultural issues, creating barrier free built-environment, safety aspects, etc, all of these leading towards sustainable development, and have to be applied with due regard to the specific requirements of size and type of project:
Geoclimatic, geological and topographical features.
Geotechnical considerations with respect to soil/rock, water table, etc.
Varied sociological pattern of living in the country.
Effective land use to cater to the needs of the society in a most convenient manner.
Modular planning and standardization to take care of future planning giving due consideration to the specified planning controls.
Emphasis on daylight utilization, natural ventilation, shielding, and window area and disposition; daylighting to be supplemented with an integrated design of artificial lighting.
Optimum utilization of renewable energy sources duly integrated in the overall energy system design; with consideration of active and passive aspects in building design including thermal performance of building envelope.
Rain water harvesting, integrated water management including recycle and reuse, etc.
Use of appropriate building materials considering aspects like energy consumption in production, transportation and utilization, recyclability, etc, and for deconstruction, for promoting sustainable development.
Requisite mandatory provisions for persons with disabilities.
Acoustical controls for buildings and the surroundings.
Promotion of artwork in buildings, especially, major/important buildings.
Due cognizance of recommendations of the Archaeological Survey of India with regard to national monuments and construction in archaeologically important sites.
Due cognizance of relevant provisions applicable to coastal regulation zone.
Conservation of heritage structures and areas, with due consideration to the concerns of the archaeological departments.
Environmental and social impact analysis.
Design of services with emphasis on aspects of energy efficiency, environment friendliness and maintainability.
Integrated waste management.
Voice and data communication, automation of building services, and intelligent building; use of security and surveillance system in important and sensitive buildings, such as access control for the people as well as for vehicle.
Interlinking of fire alarm system, fire protection system, security system, ventilation, electrical systems, etc.
PART 0 INTEGRATED APPROACH — PREREQUISITE FOR APPLYING PROVISIONS OF THE CODE
Analysis of emergency power, standby power requirement and captive power systems.
Cost optimization through techniques like value engineering.
Adoption of innovative technologies giving due consideration to constructability and quality aspects.
Instrumentation of building, monitoring and use of information so generated to effect improvements in planning and design of future building projects, and use of such instrumentation to monitor any adverse effect on the building as well as neighbouring buildings.
4.1 A land development/building project and the built facility during its service life comprises the following major stages:
a) Location/siting,
b) Conceptualization and planning,
c) Designing and detailing,
d) Construction/execution,
e) Operation and maintenance, and
f) Decommissioning and deconstruction.
Each stage necessarily requires professionals of many disciplines who should work together as a well coordinated team to achieve the desired product delivery with quality and safety and other objectives, in an effective manner.
Appropriate multi-disciplinary teams (see 4.1.1 to 4.1.3) need to be constituted to successfully meet the requirements of different stages. Each team may comprise need based professionals out of the following depending upon the nature, magnitude and complexity of the project:
Architect;
Civil engineer;
Structural engineer;
Geotechnical engineer;
Electrical engineer;
Plumbing engineer;
PART 0 INTEGRATED APPROACH — PREREQUISITE FOR APPLYING PROVISIONS OF THE CODE
Fire protection engineer;
Heating, ventilation and air conditioning engineer;
Lift, escalator and moving walk specialist;
Acoustics specialist;
Information/communication technology engineer;
Health, safety and environment specialist;
Environment/sustainability specialist;
Town planner;
Urban designer;
Landscape architect;
Security system specialist;
Interior designer;
Quantity surveyor;
Project/construction manager;
Accessibility and universal design specialist;
Asset/facility manager; and
Other subject specialist(s).
It is important that leaders and members of design team, project management/construction management team, and operation and maintenance team, depending on the size and complexity of the project, are carefully selected considering their qualification, experience and expertise in these fields.
In building projects, various aspects like form; space planning; aesthetics; fire and life safety; structural adequacy; plumbing services; lighting and natural ventilation; electrical and allied installations; air conditioning, heating and mechanical ventilation; acoustics, sound insulation and noise control; installation of lifts and escalators; building automation; data and voice communication; other utility services installations; landscape planning, design and development; urban planning; etc need to be kept in view right at the concept stage. The project requiring such multi-disciplinary inputs need a coordinated approach among the professionals for proper integration of various design inputs. For this, and to take care of the complexities of multi-disciplinary requirements, a design team of professionals from the required disciplines shall be constituted at the appropriate stage. Here, it is desirable that the multi-disciplinary integration is initiated right from the concept stage. The team shall finalize the plan. The composition of the team shall depend on the nature, magnitude and complexities of the project. Design is an evolutionary and participatory process, where participation of the owner constitutes a very important input at all stages, and the same shall be ensured by the design team.
To ensure proper implementation of the design, the design team, may be associated during the construction/execution stage.
The objective of project management or construction management is primarily to achieve accomplishment of a project in accordance with the designs and specifications in a stipulated time and cost framework, etc, with a degree of assurance prior to commencement and satisfaction on completion and commissioning.
For large projects, separate teams of experienced professionals from the required disciplines may be constituted for project management (including planning and scheduling) and for construction management depending upon the complexities of the project. However, for smaller projects these teams may be combined. The teams shall be responsible for day-to-day execution, supervision, quality control, etc, and shall ensure interdisciplinary coordination during the construction stage. The team shall be responsible to achieve satisfactory completion of the project in respect of all relevant project management functions like cost, time, quality, safety, etc. Some members of the design team may also be included in the project management team and/or associated actively during the project execution stage.
Operation, maintenance and repairs also require a multidisciplinary approach to ensure that all the requirements of the users are satisfactorily met. During maintenance and repairs, the jobs requiring inter-disciplinary coordination have to be executed in such a manner as not only to cause least inconvenience to the user but also to ensure that there is no mismatch or damage to the structure, finishing, fittings and fixtures, and to preserve the integrity of other services. For carrying out routine maintenance/repair jobs, utilization of the services of trained technicians preferably having multidisciplinary skills should be encouraged.
Special repairs, rehabilitation and retrofitting are specialized jobs which demand knowledge of the existing structure/installations. Association of concerned specialists may be helpful for these works.
The operation and maintenance team may also be known as asset and facility management or estate management team.
6.1 The main functions of the teams (see 4.1.2) constituted for Project Management/Construction Management may be to,
a) specify criteria for selection of constructors;
b) specify quality control, quality audit system and safety system;
c) short-list constructors;
d) have pre-bid meetings with the intending constructors;
e) receive and evaluate tenders;
f) select constructors;
g) execution and supervision;
h) monitor for quality, time and cost control and for other project management functions;
j) prepare/certify the completion (as-built) drawings;
k) assist in getting statutory approvals at various stages; and
m) ensure availability of operation manuals for field use.
6.2 Apart from the specific provisions laid down in the concerned Parts/Sections of the Code, the following considerations, as may be applicable to the project concerned, shall be given due attention:
a) Adopting scientific principles of construction project management, including quality, cost, time, and safety management.
b) Engagement of executing and supervising agencies, which meet the specified norms of skills, specialization, experience, resourcefulness, etc, for the work.
c) Ensuring inter-disciplinary coordination during construction.
d) Contract management and techno-legal aspects.
e) Completion, commissioning and trial run of installations/equipment and their operation and maintenance through the suppliers/other teams, where necessary.
f) Make available shop drawings as well as as-built drawings for the building and services.
g) Arrange all maintenance and operation manual from the concerned suppliers/manufacturers.
6.3 The team of professionals (see 4.1.2) shall work and monitor the project activities for successful construction/execution of the project with regard to various construction project management functions, particularly, time, cost, quality and safety.