For the purpose of this Subsection, the following definitions shall apply, and for other terms those given in the accepted standard [6-5B(1)] shall apply.
2.1 Anchorage Device — In post-tensioning, the hardware used for transferring the post-tensioning force from the tendon to the concrete in anchorage zone.
2.2 Bonded Member — A prestressed concrete member in which tendons are bonded to the concrete either directly or through grouting.
2.3 Bonded Post-Tensioning — Post-tensioned construction in which the annular spaces around the tendons are grouted after stressing, thereby bonding the tendon to the concrete section.
2.4 Cable — A group of wires or bars or strands or rods.
2.5 Characteristic Load — Load which has 95 percent probability of not being exceeded during the life of the structure (see 20.2).
2.6 Characteristic Strength — Strength of material below which not more than 5 percent of the test results are expected to fall (see 20.1).
2.7 Column or Strut — A compression member, the effective length of which exceeds three times the least lateral dimension.
2.8 Creep — Time dependent deformation due to sustained load.
2.9 Creep Coefficient — The ratio of creep strain to elastic strain in concrete.
2.10 Final Prestress — The stress which exists after substantially all losses have occurred.
2.11 Final Tension — The tension in the prestressing tendon corresponding to the state of the final prestress.
2.12 Initial Prestress — The prestressing force in the tendon at transfer.
2.13 Initial Tension — The maximum stress induced in the prestressing tendon at the time of the stressing operation.
2.14 Post-Tensioning — A method of prestressing concrete in which prestressing steel is tensioned against the hardened concrete.
2.15 Prestressed Concrete — Concrete in which permanent internal stresses are deliberately introduced, usually by tensioned steel, to counteract to the desired degree the stresses caused in the member during service.
2.16 Pre-Tensioning — A method of prestressing concrete in which the tendons are tensioned before concreting.
2.17 Relaxation — Time dependent decrease in steel stress at constant strain.
2.18 Sheathing — A material encasing a prestressing tendon to prevent bonding the tendon with the surrounding concrete during placement of concrete and to provide protection against corrosion.
2.19 Short Column — A column, the effective length of which does not exceed 12 times the least lateral dimension.
2.20 Slender Column — A column, the effective length of which exceeds 12 times the least lateral dimension.
2.21 Shrinkage Loss — The loss of stress in the prestressing steel resulting from the shrinkage of the concrete.
2.22 Stress at Transfer — The stress in both the prestressing tendon and the concrete when the prestressing tendon is released from the prestressing mechanism.
2.23 Tendon — A steel element, such as a wire, cable, bar, rod or strand, or a bundle of such elements used to impart prestress to concrete when the element is tensioned.
2.24 Transfer — The act of transferring the stress in prestressing tendons from the jacks or pre-tensioning bed to the concrete member.
2.25 Transmission Length — The distance required at the end of a pre-tensioned tendon for developing the maximum tendon stress by bond.