Section 7 Prefabrication, Systems Building and Mixed/Composite Construction: 7B Systems Building and Mixed/Composite Construction
2.1 For the purpose of this sub-section, the following definitions shall apply.
2.1.1 Authority Having Jurisdiction — The Authority which has been created by a statute and which, for the purpose of administering the Code/Part, may authorize a committee or an official or an agency to act on its behalf; hereinafter called the ‘Authority’.
2.1.2 Basic Module — The fundamental module used in modular co-ordination, the size of which is selected for general application to building and its components.
NOTE — The value of the basic module has been chosen as 100 mm for the maximum flexibility and convenience. The symbol for the basic module is M.
2.1.3 Cellular Concrete — The material consisting of an inorganic binder (such as, lime or cement or both) in combination with a finely ground material containing siliceous acid (such as sand), gas generating material (for example, aluminium powder), water and harmless additives (optional); and steam cured under pressure in autoclaves.
2.1.4 Components — A building product formed as a distinct unit having specified sizes in three dimensions.
2.1.5 Composite/Mixed Construction — Construction involving two or more components, such as, prefabricated structural units of steel, prestressed concrete or reinforced concrete and cast in-situ concrete, timber, masonry in brickwork and blockwork, glass and glazing connected together in such a manner that they act integrally.
2.1.6 Increments — Difference between two homologous dimensions of components of successive sizes.
2.1.7 Module — A unit of size used in dimensional co-ordination.
2.1.8 Modular Co-ordination — Dimensional co-ordination employing the basic module or a multi-module.
NOTE — The purposes of modular co-ordination are:
a) to reduce the variety of component sizes produced, and
b) to allow the building designer greater flexibility in the arrangement of components.
2.1.9 Modular Grid — A rectangular coordinate reference system in which the distance between consecutive lines is the basic module or a multi-module. This multi-module may differ for each of the three orthogonal dimensions of the grid, two in plan and one in vertical direction.
2.1.10 Multi-module — A module whose size is a selected multiple of the basic module.
2.1.11 Prefabricate — To fabricate components or assembled units prior to erection or installation in a building.
2.1.12 Prefabricated Building — The partly/fully assembled and erected building, of which the structural parts consist of prefabricated individual units or assemblies using ordinary or controlled materials, including service facilities; and in which the service equipment may be either prefabricated or constructed in-situ.
2.1.13 Sandwich Panels — Panels made by sandwiching a layer of insulation material between two outer layers of hard durable materials like steel, dense concrete, plastic, cement based sheet, ceramic, etc. The hard coverings on two outer faces may be of same or different materials; the three layers being bonded with each other to behave as a composite panel.
2.1.14 Self-Compacting Concrete — Concrete that is able to flow under its own weight and completely fill the voids within the formwork, even in the presence of dense reinforcement without any vibration, whilst maintaining homogeneity without segregation.
2.1.15 Shear Connectors — Structural elements, such as anchors, studs, channels and spirals, intended to transmit the shear between the prefabricated member and the cast in-situ concrete and also to prevent separation at the interface.
5
2.1.16 System — The method of construction of buildings with certain order and discipline and repetitive operations using the prefabricated components, tunnel form or engineered shuttering, where the work is organized and follows a defined procedure.
2.1.17 Unit — Building material formed as a simple article with all three dimensions specified, complete in itself but intended to be part of a compound unit or complete building. Examples are brick, block, tile, etc.
3.1.1 See Part 6 ‘Structural Design, Sub-section 7A Prefabricated Concrete’, regarding materials and the characteristics to be considered in their selection.
3.1.2 The materials used in prefabricated components may be many and the modern trend is to use concrete, steel, treated wood, aluminium, cellular concrete, light weight concrete, ceramic products, etc. However, this section pertains to mixed/composite construction.
See Part 6 ‘Structural Design, Sub-section 7A Prefabricated Concrete’.
The formwork systems which are utilized in buildings shall be as given in 6.1 to 6.5.
This is a system which casts walls and slab together like a portal in a single pour. Façade walls are precast or of block masonry to enable removal of tunnel form. All components are made up of steel. This produces
very rapid construction. Accelerated curing if required is possible enabling early stripping of formwork.
Slipform is a continuously moving form at such a speed that the concrete when exposed has already achieved enough strength to support the vertical pressure from concrete still in the form as well as to withstand nominal lateral forces. Slipform may be classified as straight slipform, tapering slipform and slipform for special applications. Construction of lift cores and stairwell using slipform technique comes under special applications because of their complex sizes, shapes and loads to be lifted alongwith the slipform like walkway truss, etc, which is essential for construction. This system uses hydraulic jacks avoiding crane for lifting of assembly during construction operation. This system facilitates rapid construction and continual casting, creating a monolithic structure thereby avoiding construction joints.
This system of formwork uses aluminium, which is light and rust free material, in both sheathing and framework. It may be used for a broad range of applications from wall to slab construction panels to more complicated structures involving bay windows, stairs and hoods. Every component is light enough to be handled easily thereby minimizing the need for heavy lifting equipment.
This is a system, which gives an advantage of combining speed and quality of construction. The vertical load carrying members are made of steel whereas the horizontal members are of plywood inserted into two wooden beams thereby forming a web flange. All the formwork and support systems shall be designed for the loads coming during the actual execution stage.
Any other/new system may be used for systems building after due examination and approval by the Authority.
5.1 The preferred dimensions of precast elements used and their casting tolerances shall be in accordance with Part 6 ‘Structural Design, Sub-section 7A Prefabricated Concrete’.
5.2 The permissible tolerances of timber used shall be in accordance with Part 6 ‘Structural Design, Subsection 3A Timber’.
5.3 For permissible tolerances of steel and masonry, reference may be made to relevant Indian Standards.
7.1 Several schemes are possible, with certain constraints, using the same set of components. The degree of flexibility varies from system to system. However, in all the systems there is a certain order and discipline.
7.2 The following aspects, among others, are to be considered in devising a system:
a) Effective utilization of spaces;
b) Straight and simple walling scheme;
c) Limited sizes and numbers of components;
d) Limited opening in bearing walls;
e) Regulated locations of partitions;
f) Standardized service and stair units;
g) Limited sizes of doors and windows with regulated positions;
h) Structural clarity and efficiency;
j) Suitability for adoption in low and high rise building;
k) Ease of manufacturing, storing and transporting;
m) Speed and ease of erection; and
n) Simple jointing system.
The system of mixed/composite construction depends on the extent of the use of prefabricated components, their materials, sizes and the technique adopted for their manufacture and use in building.
The following combinations may be used in mixed/ composite construction:
a) Structural steel work and timber roofs on precast frames.
b) Precast floors onto steel and concrete beams, and masonry walls.
c) Profiled metal decking on precast beams.
d) Precast frames onto cast in-situ foundations, retaining walls, etc.
e) Precast frames stabilized by masonry walls, steel bracing, etc.
f) Precast cladding in steel or cast in-situ frames and vice versa.
g) Glass curtain walling, stone cladding or metal sheeting onto precast concrete frames, etc.
h) Reinforced concrete and structural steel as composite columns and beams.
7.3.1.1 Precast concrete may be combined with cast in-situ concrete, often termed hybrid construction. Cast in-situ is mostly used to form homogenous connections between precast elements and provide a structural topping for horizontal diaphragm action. In other cases it is used to form the foundations and sub-structure to the building.
7.3.1.2 Structural steelwork is largely used in long span prestressed concrete floors supported on rolled and prefabricated steel beams and also as steel roof trusses supported on concrete columns.
7.3.1.3 Timber may be used as long span gluelaminated beams and rafters, with precast concrete. Precast floors may be used in timber frame construction. Similarly, timber frames with precast elements shall be used as a building system.
7.3.1.4 Brick and block masonry may be combined with precast concrete structures and floors. The most common combinations is to use prestressed floors on load bearing walls.
The mixed/composite structures shall be analyzed appropriately and the joints in them designed to take the forces of an equivalent discrete system. Resistance to horizontal loading shall be provided by placing beams, walls and bracings in two directions at right angles or otherwise. The individual components shall be designed, taking into consideration appropriate end conditions and loads at various stages of construction. The components of the structure shall be designed for loads in accordance with Part 6 ‘Structural Design, Section 1 Loads, Forces and Effects’. In addition, members shall be designed for handling, erection and impact loads that may be expected during handling and erection.
7.4.1 For mixed and composite construction the following points shall be considered:
a) Positions of stability cores, walls, bracing, etc. — In high rise buildings the most popular method is a cast in-situ core constructed several storeys ahead of the framework. In medium height buildings this may be precast concrete or brick infill, steel cross bracing or precast concrete diagonal bracing.
b) Maturity of connections — This may be decisive for or alter planned site progress unless it is properly managed. Cast in-situ grouted joints need a few days of temporary propping unless combined mechanical connections are also used.
c) As a consequence of the above, the need to design some of the key components to achieve temporary stability.
d) The availability and/or positioning of equipments to transport and erect components — The size and weight of the various components shall be organized to make optimum use of crane capacity, for example, the lightest units farthest from the operating zone.
e) Erection safety and speed of construction, with attention to cast in-situ concreting sequences — This is particularly important
where fixing gangs are unaccustomed to working with different materials.
f) Tolerances for economical construction — This is particularly important where different manufacturers are producing components in different materials.
7.4.2 Other design considerations and safety requirements against progressive collapse shall be in accordance with Part 6 'Structural Design, Sub-section 7A Prefabricated Concrete'.
The requirements relating to manufacture, storage, transport and erection of precast concrete elements shall be in accordance with Part 6 Structural Design, Sub-section 7A Prefabricated Concrete'.
Constructional practices relating to decking shall be as given in Annex A.
Concreting on decking shall be carried out in accordance with Annex B.
Construction Practice for Decking
A-1 Receiving, Storing and Lifting Decking
Decking is packed by the manufacturer into bundles of up to 24 sheets, and the sheets are normally secured with metal banding. Each bundle may be up to 1 m wide (the width of a single sheet) by 750 mm deep. and may weigh up to 2.5 t, depending on sheet length (average mass of sheet being about 1.5 t). Loads are normally delivered by articulated vehicles approximately 16 m long with a maximum gross mass of up to 40 t, and a turning circle of approximately 19 m. It shall be ensured that there is suitable access and appropriate standing and off-loading areas.
Each bundle will be given an identification tag by the
manufacturer. The information on each tag shall be checked immediately upon arrival, to prevent incorrect sheets being used, or unnecessary delays if changes are necessary. In particular, the stated sheet thickness shall be checked against the requirement specified on the drawings, and a visual inspection shall be made to ensure that there is no damage.
The bundles shall be lifted from the vehicle. Bundles shall never be off-loaded by tipping, dragging, dropping or other improvized means.
The decking shall not be delivered more than one month before its anticipated use, as it may be vulnerable to abuse and damage if stored for longer periods on site. If it is not for immediate use, the decking shall be
stored on the steel frame. If this is not possible, it shall be located in an area where it will not be contaminated by site traffic, and placed on bearers, which provide a gentle slope to the bundle. This will allow any condensation or rain to drain and a free flow of air around the bundle. Bundles shall not be stacked more than 4 m high, and no other materials shall be stored on top of them. Bearers shall be placed between bundles, and positioned to prevent bending of the sheets.
The support steelwork shall be prepared to receive the decking before lifting the bundles onto it. The top surface of the underlying beams shall be reasonably clean. When through-deck welding of shear studs is specified, the tops of the flanges shall be free of primer, paint and galvanising.
The identification tags shall be used to ensure that bundles are positioned on the frame at the correct floor level, and in the nominated bay shown on the deck layout drawing. The bundles shall be positioned such that the interlocking side laps are on the same side. This will enable the decking to be laid progressively without the need to turn the sheets. The bundles shall also be positioned in the correct span orientation, and not at 90° to it. Care shall be taken to ensure that the bundles are not upside down, particularly with trapezoidal profiles. For most trapezoidal decking profiles, the embossments shall be oriented so that they project upwards.
Care is needed when lifting the decking bundles; protected chain slings are recommended for the same. Unprotected chain slings can damage the bundle during lifting. When synthetic slings are used there is a risk of the severing them on the edges of the decking sheets.
If timber packers are used, they shall be secured to the bundle before lifting so that when the slings are released they do not fall to the ground (with potentially disastrous results). Bundles shall never be lifted using metal banding.
A-2 Deck Installation
Breaking open the bundles and installing the decking shall be done only when all the sheets can be positioned and secured. The decking layout drawing shall also be checked to ensure that any temporary support that need to be in position prior to deck laying, is in place.
Access for installation may normally be achieved using ladders connected to the steel frame. Once the laying out the sheets is started by erectors, they shall create
working platform by securely fixing the decking as they progress.
The laying of sheets shall begin at the locations indicated on the decking layout drawings. These would normally be at the corner of the building at each level, to reduce the number of ‘leading edges’, that is unprotected edges where the decking is being laid. When the bundles have been properly positioned, as provided above, there shall be no need to turn the sheets manually, and there shall be no doubt which way up the sheet shall be fixed.
Individual sheets shall be slid into place and, where possible, fixed to the steelwork before moving onto the next sheet. This will minimize the risk of an accident occurring as a result of movement of a sheet when it is being used as a platform. However, for setting-out purposes, it may be necessary to lay out an entire bay using a minimum number of temporary fixings before fully securing the sheets later.
Sheets shall be positioned to provide a minimum bearing of 50 mm on the steel support beams. The ends of adjacent sheets shall be butted together. A gap of up to 5 mm is generally considered not to allow excessive seepage, but, if necessary, the ends of the sheets may be taped together. When end gaps are greater than 5 mm, it is normally sufficient to seal them with an expanding foam filler. The longitudinal edges shall be overlapped, to minimize concrete seepage along the seams. Although not normally required, seam fixings may be necessary in some circumstances. Sheets projecting freely more than 600 mm shall be avoided.
If necessary, sheets shall be cut using a grinder or a nibbler. However, field cutting shall be kept to a minimum and shall only be necessary where a column or other obstruction interrupts the decking. Gaps adjacent to the webs of columns shall be filled in with off-cuts or thin strips of steel. Decking sheets shown as continuous on the decking layout drawing shall never be cut into more than one length. Also, sheets shall never be severed at the location of a temporary support, and the decking shall never be fastened to a temporary support.
As the work progresses, scraps and off-cuts shall be disposed of in a skip placed alongside the appropriate level of working. The skip shall be positioned carefully over a support beam to avoid overloading the decking. If a skip is not available, scraps shall be gathered for collection as soon as is possible. Partially used bundles shall be secured, to avoid individual sheets moving in strong winds.
Decking sheets shall be fixed to the top of the
supporting structure. All fixings shall be made through the troughs in the decking. Fixings shall be at approximately 300 mm centres (or in every trough) along the end supports, and at 600 mm centres (or in alternate troughs) along the internal supports. As an absolute minimum, each sheet shall be connected at least twice to each permanent support. The number
and placement of fasteners will normally be given on the decking layout drawing. Fixings shall not be made to temporary supports.
The fixings, together with ‘through-deck’ welded studs (if present) normally provide lateral restraint to the beams during the construction stages.