52.1 General
The intent of these regulations is to promote transit supportive development around proposed metro rail stations and proposed BRT stations. Such development is intended to include high intensity 18+ hour uses that will make places in the core area of the station vibrant and active throughout the day and well into the evening hours. These would include a mixed use development consisting of commercial and residential development with a mix of housing types from high-end apartments, to middle-income housing, and affordable housing, all at a relatively high density.
To manage the potential oversupply and speculative development, these TOD zone regulations shall be applicable in the future at only such time as when the State Government or the relevant authority responsible for the Metro rail project, awards the contract for construction of the metro rail. If phased construction is envisaged, the TOD zone shall apply to only those stations that are taken up for development along the transit line. (Definition of TOD Zone shall be as given in 2.128 of these Regulations)
52.2 FSI
The maximum permissible total FSI/FAR in the TOD zone shall be 4.0, including base permissible FSI and may be admissible to the plots having area 1,000 sqm and above subject to availability of minimum road width and other applicable regulations within this area.
Above FSI shall be calculated on the net plot area.
52.2.3 In case of plot/plots partly falling within the TOD zone, the FSI permissible shall be on prorata basis, provided that the total area of the plot (plot falling within NMRC plus plot falling outside NMRC) shall be 1,000 sqm..
52.2.4 Notwithstanding anything contained in any another provision of these Regulations TDR shall not be allowed to be received on the plots within TOD zone, irrespective of its location in congested area/non-congested area as per the Development Plan of NMA.
52.2.5 Additional FSI over and above permissible base FSI of respective land use zones as per these DCRs may be permitted on the payment of premium equivalent to 0.5 times of the Annual Schedule of Rates of land (Ready Reckoner) per square meter of additional FSI.
Notwithstanding anything contained in the provisions of this DCR, no component of the building in NMRC shall be free of FSI.
52.3 Minimum layout open space to the extent of 10% of the plot area shall be provided for the plot having area of 4,000 sq.m and above, of sole/amalgamated area of the plot/land.
52.4 For any development or redevelopment within NMRC size of the dwelling unit shall be of minimum 25 sqm and maximum 120 sqm of built up area and out of total proposed tenements, atleast 70% tenements shall be less than 60 sqm.
52.5 Density: Minimum density in the defined TOD zone for any development or redevelopment shall be 600 dwelling units per hectare.
52.6 Permissible land uses: Mixed use in the form of residential and commercial may be permissible on the plot in NMRC fronting on road width of 12 m. and above subject to be maximum 30 % of the total built up area as commercial and also subject to separate horizontal and vertical access for residential and commercial units.
52.7 Other provisions regarding marginal open spaces shall be governed by the proposed height of the development, as given in provisions 1.8 below and should confirm to the Maharashtra Fire Prevention and Life Safety Measures Act 2006(Maharashtra Act no III of 2007).No building permission shall be issued without NOC of the fire officer. Other regulations regarding room sizes, apertures for light and ventilation shall be given in these DCRs for the NMA
52.8 Marginal spaces to be left around building in the TOD zone shall be H/4, where ‘H’ is height of the proposed building provided that the marginal space shall be minimum 6m for the building up to 24m height and minimum 9m for the building above to 24m height.
Note 1: No projections shall be allowed in marginal spaces so that minimum 6 mt. marginal spaces remain free from all encumbrances for the movement of fire tenders. In case if ramp is necessary for accessibility such ramp may be allowed after living 6 m. clear margin. Note 2: If entire floor is used for parking, the height of parking floor shall be counted towards the height of the building
52.9 Parking provisions shall be made as per the table given below
| S. No | Occupancy | For every | Car | Scooter / Motorcycle | Cycle |
|---|---|---|---|---|---|
| 1 | Residentiali. Multifamily | Tenements having carpet areai. from 25 to 40 sqmii. 41 to 60 sqmiii. 81 sqm & aboveremaining (b) to (f) will have same provision | 0001 | 1121 | 22221 |
| 2 | Govt. & Semi govtPrivate business buildings | 100 sqmt carpet area or fraction thereof | 1 | 2 | 2 |
Note: Parking spaces for differently-abled as per Indian Road Congress Code no. IRC 103:2012 shall be provided in each new construction/development/re-development in the TOD influence zone.