7.1 Owner’s Liability
Neither the grant of permission nor approval of the drawing and specifications nor inspections by the Chairman, NIT during erection of the building, shall in any way relieve the owner of such building from full responsibility for carrying out the work in accordance with these Regulations and safety norms as prescribed by the Bureau of Indian Standards.
7.2 Documents at site
The following documents shall be maintained on the construction site during the entire duration of construction:
a) Results of tests: Where tests of any material are made to ensure conformity with the requirements of these Regulations, records of the test data shall be kept available for inspection during the construction of the building and for such period thereafter as required by the Chairman, NIT.
b) Development Permission: The person to whom development permission is issued shall during the period of construction, keep:
i) A copy of a development permission placed in a conspicuous place on the site for which permission has been issued, and
ii) A copy of the approved drawings and specifications referred to in Regulation 6 on the site for which the permit was issued.
c) Display board: Display board mentioning name of the owner, name of architects, name of structural engineer, except for small individual plot holders
7.3 Checking of Plinth, Columns upto Plinth Level
The owner through his licensed surveyor, engineer, structural engineer or supervisor or his architect shall give notice in the form of Appendix F to the Chairman, NIT on completion of work upto plinth level enabling the Chairman to ensure that the work conforms to the sanctioned plans. The Chairman may inspect the work jointly with the licensed technical personnel or architect within 15 (fifteen) days from the receipt of such notice and either give or refuse permission for further construction as per the sanctioned plans in the form in Appendix G. If within this period, the permission is not refused it shall be deemed to have been given provided the work is carried out according to the sanctioned plans.
7.4 Deviation During Constructions
If during construction of a building any departure of a substantial nature from the sanctioned plans is intended by way of internal or external additions, sanction of the Chairman, NIT shall be necessary. A revised plan showing the deviation shall be submitted and the procedure laid down for the original plans shall apply to all such amended plans. Any work done in contravention of the sanctioned plans, without prior approval of the Chairman shall be deemed as unauthorized.
7.5 Completion Certificate
The owner through his licensed surveyor / engineer / structural engineer / supervisor or his architect who has supervised the construction, shall furnish a Building Completion Certificate to the Chairman in the form in Appendix H. This certificate shall be accompanied by three sets of plans of the completed development, one of which shall be cloth mounted for office record.
These ‘as built’ plans shall also be made available in an electronic format, as specified by NIT/ SPA from time to time. In addition to the Completion Certificate and drawings of the completed development, the owner shall submit the following plans/documents to NIT/SPA:
a) Sewer connection plan;
b) Final NOC/Clearance from the Chief Fire Officer, NIT/ NMC/ Director of Fire Services Government of Maharashtra, wherever necessary;
c) Environment clearance as per the Environment Protection Act 1986, wherever necessary; and
d) Structural Stability Certificate from a competent structural engineer;
e) Release letter from NIT for dwelling units/ tenements in case of group housing.
7.6 Occupancy Certificate
The Chairman, NIT after inspection of the work, scrutiny of the submitted documents and after satisfying himself that there is no deviation from the sanctioned plans and after requisite fees are paid, issue the Occupancy Certificate in the form given in Appendix I or refuse to sanction the Occupancy Certificate in the form given in Appendix J within 21 days from the date of receipt of the said completion certificate, failing which the work shall be deemed to have been approved for occupation provided the construction conforms to the sanctioned plans. One set of plans, certified by the Chairman NIT, shall be returned to the owner along with the Occupancy Certificate. Where the Occupancy Certificate is refused or rejected, the reasons for refusal or rejection shall be given in intimation of the rejection or the refusal.
7.7 Part Occupancy Certificate
When requested by the holder of the development permission, the Chairman NIT may issue a part occupancy certificate for a building or part thereof, before completion of the entire work, as per development permission, provided sufficient precautionary measures are taken by the holder to ensure public safety and health. The occupancy certificate shall be subject to the owners indemnifying the Chairman in the form of Appendix K.
8 INSPECTION
The Chairman, NIT shall have the power to carry out inspection of the work under the provisions of the Act, at various stages to ascertain whether the work is proceeding as per the provisions of regulations and sanctioned plan.
9 UNSAFE BUILDINGS
All unsafe buildings shall be considered to constitute danger to public safety, hygiene and sanitation and shall be restored by repairs or demolished or dealt with as otherwise directed by the NIT/ SPA. The relevant provisions of the Regulation No. 24.12 shall apply for procedure of actions to be taken by the Chairman, NIT for unsafe buildings.