A. All the applications for setting up or installation of any Telecommunication Cell Site/ Base Station (TCS/BS) or erection of a part thereof, shall be made to the Competent Authority by the concerned Telecom Service Provider (TSP) or the concerned Infrastructure Provider (IP), in such form and containing such particulars as may be prescribed by the Competent Authority or the Government.
B. The application to the Competent Authority for obtaining the aforesaid development permission shall be accompanied by the following documents,-
a) All the documents as otherwise required to be attached for any development permission under the sanctioned Development Control Regulations for the area in which the site under application is located.
b) Plans showing Location Map, Key Plan, Site Plan, Block Plan and Plans of the proposed work. In case of roof-top tower, the copy of Occupation Certificate or copy of sanctioned building plans or copy of Commencement Certificate issued by the Competent Authority or any other valid proof, in respect of the building on which the erection of roof-top tower is proposed, showing that such building is authorised.
c) Notarised consent of the Owner of premises, 'Which shall mean and include consent of the owner of property or no-objection certificate of the concerned registered Co-op Housing Society or notarised consent of 70% of the total number legal occupants in case of Apartments or Condominium or no-objection certificate of the lessor in case of a lease-hold property.
d) Copy of agreement between the TSP/IP and the Owner of premises.
e) Copy of Access Service License/Infrastructure Provider (IP) Registration Certificate, granted to the TSP/IP by the Department of Telecommunications (DoT), Government of India (GoI).
f) "Copy of clearance from the Standing Advisory Committee for Frequency Allocations (SACFA) or copy of application made to SACFA for the said location submitted to Wireless Planning Commission (WPC) wing of the Department of Telecommunications (DoT), with registration
number as WPC Acknowledgement, along with an undertaking that in case of any objection/rejection, TSPs/IPs will take corrective actions or remove the TCS/BS."
g) "Acknowledgement receipt issued by Telecom Enforcement Resource and Monitoring (TERM) Cell in respect of the. self-certificate submitted by TSP/IP regarding mobile towers/ Base Transceiver Station (BTS) [Ground-based or Roof-Top or Pole/wall-mounted] in the format as prescribed by Telecom Engineering Centre (TEC), DoT, establishing/certifying that all General Public areas around the TCS/BS will be within safe Electro-Magnetic Radiation (EMR) exposure limit as per peak traffic measurement after the antennae starts radiating."
h) "Copy of Structural Stability Certificate for any ground-based Base Transceiver Station (BTS).
OR
In case of any roof-top BTS tower, Structural Stability Certificate for the building, based on written approval of any authorized Structural Engineer of the State/Local Body/Central Building Research Institute (CBRT), Roorkee/IIT/NIT or any other Agency authorized by the Competent Authority.
Provided that such NOC shall not be required for the single pole antennae or cellular signal boosters.
i) Copy of the type test certificate issued by Automotive Research Association of India (ARAI) to the manufacturers of the Diesel Generator (DG) Sets.
j) Notarised undertaking from the Applicant/ owner of premises:-
i. That the cabin will not be utilized for any purpose other than the Telecommunication Cell Site/Base Station.
ii. That if the said activity is discontinued by the Applicant, the said cabin will be demolished forthwith by the Applicant /Owner of premises.
k) No-objection certificate from the Authority concerned under the Civil Aviation Ministry (hereinafter referred to as the said Authority) in case of any building falling in any area where such no-objection certificate of the said Authority is required under the relevant rules or law.
l) No objection certificate of the Maharashtra Pollution Control Board regarding compliance with the norms prescribed for noise levels and smoke levels for the power generating sets having capacity above 100 kW, to be provided for Base Transceiver Stations.
m) No objection certificate of the Chief Fire Officer of the concerned Urban Local Body, and elsewhere, of the Director of Fire Services, only in case of High Rise buildings having height of 15 mt or more measured from ground level.
n) Copy of clearance from the State Environment Department as well as the Forest Department, in case of forest, protected areas, if applicable.
o) Data Sheet containing the information regarding:-
i. Name of Telecom Service Provider/ Infrastructure Provider
ii. Location-
iii. Tower Reference-
a. Height & Weight of Tower
b. Ground Based Tower/ Roof Top Tower
c. Number of Antennae planned on Tower
d. Permissible maximum EMF Radiation Level
e. Proposed maximum EMF Radiation Level.
p) Requisite fees, charges, as applicable.
C. In case of area under Coastal Regulation Zone and/or in case of a listed Heritage building/Heritage precinct and/or in case of ceased buildings and/or in case of area under Environmentally Sensitive Zone (ESZ), notified by the Ministry of Environment and Forest
(MoEF) Government of India (GoI), all the applications for installation of any TCS/BS or erection of part thereof, shall be made to the concerned Competent Authority, which will forward it to the Maharashtra Coastal Zone Management Authority (MCMA) or National Coastal Zone Management Authority (NCZMA), as the case may be, and/or Heritage Conservation Committee concerned and/or MHADA and/or High Level Monitoring Committee (HLMC) appointed/ constituted by MoEF, respectively.