a) Notwithstanding the land use provisions under the relevant Development Control Regulations (DCR) pertaining to any Development Plan (DP) or Regional Plan (RP), subject to the compliance of other provisions of these Regulations, it shall be permissible to install TCS/BS, on,-
i. All land uses as earmarked in any DP or RP.
ii. All lands which are designated for non-buildable reservations in any DP or RP, subject to the condition that the maximum permissible area for installation of such TCS/BS shall not be more
than 5% of the area of the reserved site or 100 sq.m. whichever is less, and .shall be located in one corner of the reserved site.
iii. All lands which are designated as open spaces/ recreational open spaces/ recreational grounds in a sanctioned layout, where such installation shall be permissible only with the no- objection certificate of the concerned registered co-operative housing society or consent of 70% of the total number of 1egal occupants/ plot holders of such layout, subject to the condition that the maximum, permissible area for installation of such TCS/BS shall not be more than 5% of such area or 100 sq.m. whichever is less, and the same shall be located in one corner of such area.
iv. All buildable reservations in any DP or RP, except for buildings of uses mentioned in Regulation No. 42.6 (f), where such installation shall be permissible on the roof top, but only after development of the said reservation.
v. All open lands in slum areas belonging to the Government I Public Authority I Planning Authority, where only ground-based TCS I BS shall be permissible and no Roof-Top Tower shall be permissible, save as provided in Regulation 42.6 (a)(vi) herein below.
vi. public buildings in slum areas, like public toilets, community centres etc., constructed by any Public Authority or to be constructed by the TSP/ IP, where construction of Roof Top Towers shall be permissible, subject to maintenance and compliance of other terms and conditions specified by the concerned Authority.
b) No permission for installation of TCS/BS shall be granted in wildlife areas and/ or ecologically important areas, without ecological impact assessment and review of installation site. The Forest Department should be consulted before installation of TCS/BS in and around Protected Areas (PAs) and Zoos.
c) The TCS/BS must have clear access by means of an existing road having minimum width of 6 m. For locations falling in congested area as earmarked on any DP or RP and 9 m, for locations falling outside such congested area. However, in exceptional circumstances, the Competent Authority may relax such road width suitably, but in no case, shall it be less than 5 m.
d) In case of both ground-based towers and roof-top towers, there shall be no nearby buildings right in front of the antenna(e) of equivalent height, taking into account the tilt of the lowest antenna on tower, as per the details in the Table below :-
| Sr. No. | Number of Antenna(e) Pointed in the Same Direction | Building /Structure Safe Distance from the Antenna(e) at the same Height (in mtrs) |
|---|---|---|
| 1 | 1 | 20 |
| 2 | 2 | 35 |
| 3 | 4 | 45 |
| 4 | 6 | 55 |
Provided that, the antennae at the same height only are to be counted, as the beam width of the mobile antennae, in the vertical direction, is very narrow:
(Explanation- The distance figures in the above Table are based on empirical estimation considering that all the antennae are emitting at their maximum RF power of 20 Watts and exactly in the same direction with the same height.)
Provided further that, above norms shall automatically stand revised as per the latest guidelines issued by the DoT from time to time.
e) In case of Wall Mounted /Pole Mounted Antenna (e):-
I. Wherever the antennae are mounted on the Wall of a building or pole or along the road, their height should be at least 5 m. above ground level/ road level:
Provided that, such installations shall have to comply with the prescribed radiation limits.
II. As far as safe distance of buildings from antenna(e) is concerned, guidelines as in Regulation 42.6(d) above shall apply.
f) Installation of Base Station antenna(e) shall not be permissible 'within the premises of schools, colleges and hospitals as well as on the adjoining land /building within 3 m. from the boundary of premises of schools, colleges and hospitals. Also antenna(e) shall not be directed/ positioned towards any school/ college/ hospital building.
g) The existing Base Station antenna(e) approved earlier on any school/ college/ hospital building shall not be renewed further after the expiry of period of approval and the same shall be removed immediately thereafter, subject to the provisions of Regulation 42.8(d).
h) Access to Base Station Antenna site shall be prohibited for the general public, by putting in place suitable measures such as wire-fencing, locking of the door to the roof, etc.
i) The roof-top TCS/BS towers shall be put only on buildings which are declared structurally strong enough to bear the load of such installation. The base connection to the building should be got designed from a qualified structural engineer. Structural safety certificate of the composite structure [Building + Tower(s)] shall have to be obtained from any of the recognized Government Institutes.
j) While according permission for installation of TCS/BS, permissible for erection of a cabin at ground level may be granted. However, the same shall not be allowed in the prescribed marginal open spaces. The area of such cabin shall not be more than 20 sq. mt. for each TSP/ IP, subject to the certificate of structural safety. Built-up area of such cabin(s) shall not be counted towards builtup area or FSI.
k) No permission for installation of TCS/BS shall be granted on buildings which are unauthorized and structurally unsafe. If permission for installation of such structures is granted on a building, which is declared as unauthorized at a later point of time, the Competent Authority shall first take recourse to the provisions of sections 52, 53, 54 and 55 of the Maharashtra Regional and Town' Planning Act, 1966 or other relevant laws, as the case may be, against such unauthorised building and in case the Competent Authority, after completing the duo process of law, decides to undertake any action of demolition against such unauthorized building then such decision shall also be conveyed to the concerned TSP/IP with a direction to relocate the TCS/BS within a period of 90 days, after which the Competent Authority shall not be under any obligation to send any further intimation to the TSP/IP concerned before demolishing such unauthorised building; and it shall not be liable to pay compensation for the loss of the Base Station as a consequence of the demolition of the unauthorized building. The TSP/IP shall indemnify the Competent Authority to this effect, while seeking permission for installation of TCS/BS.
l) Permission for installation of TCS/BS, once granted shall remain valid for next 5 years. The TSP/IP shall apply for renewal of permission to the Competent Authority. The Competent Authority, while considering renewal, shall insist upon submission of fresh structural stability certificate for buildings more than 30 years of age. Administrative fee shall be levied and collected as prescribed in Clause 5 (b) hereinabove, for every such renewal. If TSP/IP fails to apply for renewal along with all necessary documents before the expiry of earlier permission, then such TSP/ IP shall be liable for action under the provisions of the Maharashtra Regional and Town Planning Act, 1966.
m) In case of any existing TCS /BS on a slum structure, every effort shall be made to relocate such TCS/BS on a nearby suitable public building or any other authorised structure or open land in the slum. If such relocation is not possible, then such TCS/BS may be allowed to be continued on such slum structure subject to its structural suitability, till the TCS/BS is shifted to any other authorised structure or till the redevelopment of the slum, whichever is earlier.