5.1 No person shall carry out any development, in contravention of the Development Plan proposals.
5.2 No person shall carry out any development work including development of land by laying out into suitable plots or amalgamation of plots or development of any land as group housing scheme or erect, re-erect or make alterations or demolish any building or cause the same to be done without first obtaining a separate building permit/ commencement certificate for each such development work/ building from NIT/ SPA.
5.3 No temporary construction shall be carried out without obtaining prior approval of NIT/ SPA, which may be granted subject to such conditions as may be deemed necessary by NIT/ SPA.
5.4 Development undertaken on behalf of Government
As per the provisions of Section 58 of the Maharashtra Regional and Town Planning Act, 1966 the office incharge of the Government Department shall inform in writing to the NIT/ SPA of its intention to carry out its purpose along with details of such development or construction as specified below:-
i) An official letter by the authorized officer of Government Department addressed to the Authority, giving full particulars of the development work on any operational construction.
ii) Ownership document and measurement plan issued by the Competent Authority of Land Records Department.
iii) Development / building plans confirming to the provisions of Development Plan and these Regulations for the proposed development work to the scale specified in these Regulations.
iv) The proposals of the Development Plan or Town Planning Scheme/ Improvement Scheme affecting the land.
v) A Site Plan (as per Regulation 6.2.4) showing the plan, sections and elevations of the proposed development work to the scale.
vi) Detailed plan (with required number of copies) showing the plan, sections and elevations of the proposed development work to the scale, including existing building specified either to be retained or to be demolished.
5.4.1 The operational construction of the Government, whether temporary or permanent which is necessary for the operation, maintenance, development or execution of any of following services may be exempt from the provisions of these regulations:
i) railways;
ii) national highways;
iii) national waterways;
iv) airways and aerodromes;
v) major ports;
vi) posts and telegraphs, telephones, wireless, broadcasting and other like forms of communication;
22
vii) regional grid for electricity;
viii) Defence authorities, and
ix) any other service, which the State Government/ Central Government may by notification, declare to be a service for the purpose of this clause, if it is of opinion that the operation maintenance development of execution of such services is essential for the community.
All such construction shall however, conform to the prescribed requirement for the provision of essential services, water supply connection, drains etc., to the satisfaction of the Chairman/ NIT.
5.4.2 However, the following constructions of government departments do not come under the purview of operational construction for the purpose of exemption under Regulation 5.4.1:
i) new residential building, roads and drains in railway colonies, hospitals, clubs, institute and school, in the case of railways;
ii) a new building, new construction or new installation or any extension thereof, in the case of any other services.
However, no permission shall be necessary for the following works:
i) the carrying out of works in compliance with any order or direction made by any authority under any law for the time being in force.
ii) the carrying out of work by any Authority in exercise of its powers under any law for time being in force.
iii) the carrying out of any works by the Central or State Government or any local authority:
a) required for the maintenance or improvement of highway, road or public street, being works carried out on land within the boundaries of such highway, road or public street;
b) Required for the purpose of inspecting, repairing or renewing any drains, sewers mains, pipes, cable, telephone or cables, or other apparatus including the breaking open of any street, or other land for the purpose.
Provided that the concerned authority shall inform the NIT/ SPA, in writing, one month before carrying out such development.
i) the excavation (including excavation of wells) made in the ordinary course of agricultural operations.
ii) the construction of a road intended to give access to land solely for agricultural purpose.
iii) Normal use of land which has been used temporarily for other purposes like marriage pandals or for festive occasions; and
iv) in case of land, normally used for one purpose and occasionally used for any other purpose, for the use of land for that other purpose on occasions.