47.1 Utility easements
Easements established as per the width and locations required by the engineering or the utility department, in no case less than 3m wide, should be provided for open or piped storm drainage, sanitary sewers, water lines and other utilities. This requirement applies to such lines installed at the time of the development and to easements for such lines which may reasonably be expected to be installed in the future.
47.2 Stream Buffer Easements
The stream buffer easement is applicable for plots which have one or more boundaries adjoining a natural stream. Stream buffer as per the Regulation 11.1 (b) shall be reserved as a stream buffer. The plot owner shall provide access for maintenance of the stream at all times.
The stream buffer area can be landscaped or retained in its natural condition. Construction of permanent buildings shall not be permitted. Not more than 10 percent area within the stream buffer shall be paved.