(a) Basement exits shall be sufficient to provide for the capacity of the basement as determined in accordance with 15.9.3. In no case there shall be less than two independent basement exits.
(b) Basements having incidental occupancies to main occupancy shall be planned with exit requirements of the basements for the actual occupancy within the basement.
(c) Where basement is used for car parking and also there is direct approach from any occupancy above to the basement, door openings leading to the basement shall need to be protected with fire doors with 120 min fire rating, except for exit discharge doors from the basement.
(d) The basement shall be partitioned and in no case compartment shall be more than 500 sq. m. and less than 50 sq. m. area except parking. Each compartment shall have ventilation standards as laid down in Regulations separately and independently. The partition shall be made in consultation with the Director, Directorate of Fire and Emergency Services.
(e) The first basement (immediately below ground level) can be used for services/parking/other permissible services. Lower basement, if provided, shall exclusively be used for car parking only.
(f) Each basement shall be separately ventilated. Vents with cross-sectional area (aggregate) not less than 2.5 percent of the floor area spread evenly round the perimeter of the basement shall be provided in the form of grills or breakable starboard lights or pavement lights or by way of shafts. Alternatively a system of air inlets shall be provided at basement floor level and smoke
275 Substituted vide Amendment Regulations, 2019.
276 Substituted vide notification No. 21/1/TCP/2011/Part file/3252 dated 1-8-2011.
277 Substituted vide Amendment Regulations, 2023.
182–
outlets at basement ceiling level. Inlets and extracts may be terminated at ground level with starboard or pavement lights as before. But ducts to convey fresh air to the basement floor level have to be laid. Starboard and pavement lights should be in positions easily accessible to the firemen and clearly marked ―SMOKE OUTLET‖ or ―AIR INLET‖ with an indication of area served at or near the opening.
(g) The staircase of basement shall be of enclosed type having fire resistance of not less than two hours and shall be situated at the periphery of the basement to be entered at ground level only from the open air and in such positions that smoke from any fire in the basement shall not obstruct any exit serving the ground and upper storeys of the building and shall communicate with basement through a lobby provided with fire resisting self closing door of one hour rating. In case of basement being used as car parking only, the travel distance shall be 45 meters.
(h) In multi-storeyed basements, intake duct may serve all basements levels, but each basement and basement compartment shall have separate smoke outlet duct or ducts. Mechanical extractors for smoke venting system from lower basement levels shall also be provided. The system shall be of such design as to operate on actuation of smoke, heat sensitive detectors/sprinklers, if installed, and shall have a considerably superior performance compared to the standard units. It shall also have an arrangement to start it manually.
(i) Mechanical extractors shall have an internal locking arrangement so that extractors shall continue to operate and supply fans shall stop automatically with the actuation of fire detectors. Mechanical extractors shall be designed to permit 12 air changes per hour in case of fire or distress call. However, for normal operation, only 12 air changes or any other convenient factor can be maintained. (i) Mechanical extractors shall have an alternate source of power supply.
(j) Ventilating ducts shall be integrated with the structure and made out of brick masonry or RCC as far as possible and when this duct crosses the transformer area of electrical switchboard, fire dampers shall be provided.
(k) Kitchens working on gas fuel shall not be permitted in basement/sub-basement.
(l) If cutouts are provided from basement to the upper floors or to the atmosphere, all side cutout openings in the basements shall be protected by sprinkler heads at closed spacing so as to form a water curtain in the event of a fire.
(m) Dewatering pump shall be provided in all basements.
(n) Additional provisions shall apply to parking structures of the closed or open type, within buildings above or below grade as per Annex H of Part 4 of the National Building Code of India, 2016.
- All high-rise buildings having height above 200 meters shall have provision for a Helipad on the terrace for specific requirements like landing of fire equipment and support facilities or other emergencies. The same shall be subject to approval of the Airport Authority and Structural Safety from Indian Institute of Technology/National Institute of Technology.
5. Service Ducts/Refuse Chute:
Service Ducts/Refuse Chute shall be as per Clauses 3.4.5.4 and 3.4.5.5 of Part 4 of the National Building Code of India, 2016.
6. Electrical Services:
Electrical Services shall be as per Clause 3.4.6 to Clause 3.4.6.2 of Part 4 of the National Building Code of India.
183–
7. Staircase and Corridor Lights:
The staircase and corridor lighting shall be as per Clause 3.4.7 to 3.4.7.2 of Part 4 of the National Building Code of India, 2016.
8. Air-Conditioning:
Air-conditioning shall be as per Clause 3.4.8 to 3.4.9 of Part 4 of the National Building Code of India, 2016.
9. Fire Dampers:
Fire Dampers shall be as per Clause 3.4.8.4of Part 4 of the National Building Code of India, 2016.
10. Boiler Rooms:
Boiler Rooms shall be as per Clause 3.4.9.2 of Part 4 of the National Building Code of India, 2016.
11. Alternate Source of Electric Supply:
Alternate Source of Electric Supply shall be as per Clause 3.4.6.4 of Part 4 of the National Building Code of India, 2016.
12. Safety Measures in Electric Sub-Station:
Safety Measures in Electric Sub-Station shall be as per Clause 3.4.6.3 to 3.4.6.3.2 of Part 4 of the National Building Code of India, 2016.
13. Control room:
Control room/Fire Command Centre shall be as per Clause 3.4.12of Part 4 of the National Building Code of India, 2016.].
278[Omitted]
279 [ANNEXURE - V
27.V.— ADDITIONAL REGULATIONS TO PROVIDE FOR RAIN WATER HARVESTING IN BUILDING FROM ROOF TOP FOR STORAGE/RE-USE OR LAND BASED CATCHMENT AREA FOR RECHARGING OF GROUND WATER/STORAGE/RE-USE:
- Definitions:— (a) ―Harvesting Structure‖ means a system of structures built in the building site to collect, filter and channel the rain water from roof tops/terrace or any paved or unpaved surface within the building site and to store collected rain water for percolation or recharge or storage in underground or over ground tank and re-use in non-monsoon seasons. Harvesting Structure has broad meaning and shall include ground water recharge system for percolation of water into the ground to augment the ground water stock or/to recharge the aquifers and to avoid flooding.
(b) ―Harvesting Tank‖ means a water tight underground tank to collect and store rain water collected from roof tops/terraces or any paved or unpaved surface within the building site after screening through filter beds/mediums for re-use in non-monsoon seasons.
278 Annexure IV omitted vide Amendment Regulations, 2023.
279 Substituted vide notification No. 21/1/TCP/2011/Part file/3252 dated 1-8-2011.
184–
(c) ―Harvesting Reservoir‖ means a water tight open to sky reservoir to collect and store rain water collected from roof tops/terraces or any paved or unpaved surface within the building site after screening through filter beds/mediums for re-use in non-monsoon seasons.
(d) ―Permeable Trench‖ means a trench dug along the compound wall/contours filled with gravel/sand mixture for recharging the ground water with rain water collected from roof tops/terraces or any paved or unpaved surface within the building site after screening through filter beds/mediums. Permeable Trench/Pit may also include trench dug on any other appropriate spot within the building sites or recharging of the ground water.
(e) ―Recharge Well‖ means a well with filter bed structure built around existing well/ /abandoned bore well to recharge the ground water with rain water collected from roof tops/terraces or any paved or unpaved surface within the building site after screening through filter beds/mediums for re-use in non-monsoon seasons. In the case of hard rock strata, boreholes are to be made with filter arrangement to percolate water into the ground.
- Structures for Rain Water Harvesting.— (a) Rain water harvesting shall be either in form of collection of rain water from roof tops/terraces or any paved or unpaved surface within the building site through pipes/gutters into a filter bed, built around a bore well or a well for ground water recharge or through a filter bed into a underground harvesting tank or open to sky reservoir for storage and use in non-monsoon periods.
(b) Any structures proposed for installation of Rain Water Harvesting (Built underground tank or Reservoir or filter beds or bore well or permeable trench) for storage for re-use shall be permitted free of FAR, Coverage, and height rules and shall be exempt from the setback rules provided these structures shall not come in way of circulation nor interfere with the parking space as per the statute. All the storage structures created for rain water harvesting has to abide by the provisions of the design and specifications as laid down in Goa Public Health Act, 1985 for prevention of Vector Borne Diseases.
1. Basement floor:
The construction of the basement floor shall be allowed by the Authority in accordance with the land use and other provisions specified under the ODP/Zoning Plan for the following uses:
(a) Basement floors shall not be used for purposes other than parking and for locating machines for services and utilities for the building. When used for parking, convenient entry and exit shall be provided to the basement floors from road with a minimum width of 10 meters. Access to the basement floors when used for other uses other than parking purposes can be from inside the building.
(b) Strong rooms in case of banks shall be allowed.
(c) Installation of Radiology and X-Ray equipments only in case of hospital buildings having capacity of more than 50 beds can be allowed. The area to be used for this purpose shall not be reckoned for FAR purpose.
(d) Installation and running of machines for services and utilities for the building. The area to be used for this purpose shall not be reckoned for FAR purpose.
(e) When used as office space, sufficient number of exit ways and access ways shall be provided with a travel distance not more than 15.0 m. The travel distance in case of dead-end shall be 7.5 m. The basement floor may be partitioned and in no case compartment shall be more than 500 sq. m. and less than 50 sq. m. area except when used for parking. Each compartment shall have ventilation standards as laid down in Regulations separately and independently. The partition shall be made in consultation with Chief Fire Officer. The area to be used for this purpose shall be reckoned for FAR purpose.
2. The basement floors shall have the following requirement:
(a) Every basement floor shall be in every part at least 2.5 m. in height from the floor to underside of the roof slab or ceiling and with maximum height not more than 4.5 m.
(b) In case of high rise building/3 Star/5 Star hotel buildings where extra height is necessary for installation and running of the machinery or for purpose of double storied parking lot where mechanical lifts are used for car parking at least for one level, the basement floor may be lowered so as to increase the height upto 4.5 meters. The increase in height shall be limited to the area actually required for the machinery for
187–
car parking lifts. NOC from fire services shall be furnished by the applicant for permitting such increase in height.
(c) Adequate artificial light and ventilation shall be provided for the each of the basement floor. The standard of artificial light and ventilation shall be the same as required by the particular occupancy according to these Regulations. Any deficiency in ventilation may be met by providing adequate mechanical ventilation in the form of blowers, exhaust fans (one exhaust fan for 50.00 square meters basement area), air-conditioning system, etc.
(d) The minimum height of the ceiling of any basement floor shall be 0.90 meters and maximum of 1.20 meters above the average road level on the front side of the building.
(e) Adequate arrangement shall be made such that surface drainage does not enter the basement floors. De-watering pumps are installed on each basement floor to prevent flooding.
(f) The walls and floors of the basement floors shall be watertight and be so designed that the effect of the surrounding soil and moisture, if any, are taken into account in design and adequate damp proofing treatment is done.
(g) The access to the basement floors shall be either from the main or alternate staircase providing access to the building. No direct entry from the road shall be permitted to the basement except when used for parking purposes, convenient entry and exit ramps shall be provided to the basement floors from road with a minimum width of 10.00 meters.
(h) Basement floor in an individual plot touching the adjacent property shall be allowed subject to following:
(i) In all cases the owners shall have to indemnify the local body against any damage caused by her/him/them to the adjacent property.
(ii) In case the portion of the basement floor projecting out of the building line that shall flush with the ground.
(i) In case partition in the basement floors are allowed by the Authority, no compartment shall be less than 50.00 square meters in area and each compartment shall have ventilation standards as laid down in sub-clause (c) above, separately and independently. The basement floor partition shall however, confirm to the norms laid down by Fire Services.
280[(j) Fire and Safety requirements as applicable to each basement floor shall be as per Annexure-III, regulation 27.III.];