Provisions for Green Building (Please refer Chapter 10 of this document)
1. Water Conservation and Management- Bye laws: 10.2 (1)
Considering an ever increasing demand for water, efforts are needed to substantially reduce water consumption in buildings. Integrated and sustainable water management focusing on least anthropogenic water discharge from human activities should be pursued. The use of water conserving fixtures, landscaping, rain water harvesting, aquifer recharging and waste-water recycling need to be given due consideration.
a. Rain Water Harvesting from roof and non-roof areas (by Recharge)
Design rainwater harvesting system to capture at least ‘peak-month rainfall’ runoff volume from roof and non-roof areas.
ii. WC faucets, wash basin taps, and kitchen taps:
Faucets and taps can have flow rates upto 25 litre/min. The flow rate can be reduced without compromising on the water pressure by having restrictors, pressure inhibitors and aerators. Auto control valves can further help in reducing wastage.
Pressure reducing device: Use of aerators can result in flow rates as low as 2 litre/min, which is adequate for hand washing purpose.
Auto control valves: Installation of magic eye solenoid valve (self-operating valve) can result in water savings. The sensor taps has automatic on and off flow control. It functions with parameters such as distance and timing.
iii. Urinals:
The conventional urinals use water at a rate of 7.5-11 litres per flush.
Low flush urinals use only 2 litre/flush
Use of electronic flushing system or magic eye sensor can further reduce the flow of water to 0.4 litres per flush
Waterless urinals use no water
iv. Shower heads:
Conventional showerheads can deliver water at flow rates above 25litres/min.
A perfectly pleasant shower can however, be obtained with flow rates well below 10 litres / min.
Shower heads fitted with aerators and pressure regulators can reduce flow rates as low as 4.5litrs/min and their use will show a significant saving.
c. Waste Water Recycle and Reuse
i. Waste Water Treatment: Design an on-site treatment system to handle 100% of waste water generated in the building, to the quality standards suitable for reuse, as prescribed by Central (or) State Pollution Control Board, as applicable.
ii. Waste Water Reuse: Use treated waste water for at least 25% of the total water required for landscaping, flushing, and cooling tower make-up water (if the project uses water-cooled chillers).The treated waste water could be used for landscaping, flushing and air-conditioning.
Waste water here refers to both grey and black water
Waste water can be treated in-situ and reused in-situ
In case the local authorities insist the project to divert waste water to a centralized/ common waste water treatment plant, then the project can show compliance, by reusing treated wastewater from the centralized/ common/ any other waste water treatment plant
Treated waste water from other sites/ local authorities through permanent piped connections or other means can also be considered to show compliance
Captured rain water can also be considered to show compliance
The water requirement and average number of watering days for landscaping shall be considered as 6 liters per sq.m. per day (i.e. 6 liters/ sq.m./ day) for a minimum of 300 days (or) Justify if the water requirement and the average number of watering days for landscaping is less than the above requirement.
b. Low Water Consumption Plumbing Fixtures
Use water efficient plumbing fixtures (as applicable) whose flow rates meet the baseline criteria in aggregate. The total annual water consumption of the building should not exceed the total base case water consumption computed. The baseline criteria are as below:
Table 8Baseline Flow Rates / Consumption for Plumbing Fixtures
S. No.
Fixture Type
Maximum Flow Rate / Consumption
Duration Estimated Daily Uses per FTE**
1
Water Closet (Full Flush)
6 LPF
1 for male 1 for female
2
Water Closet (Half Flush)
3 LPF
2 for female
3
Urinals
4 LPF
2 for male
4
Faucets / Taps*
6 LPF
4
5
Health Faucet*
6 LPF
1
6
Shower Head / Handheld Spray*
10 LPF
0.1
Source: Uniform Plumbing Code – India
LPF: Litre per flush
*Reporting pressure for these fixtures shall be at 3 bar.
**Full Time Equivalent (FTE) represents a regular building occupant who spends 8 hours per day in the building. Part-time or overtime occupants have FTE values based on their hours per day divided by 8.
Plumbing fixtures certified by IGBC under Green Product Certification Programme can be used by the project to show compliance, as and when certified fixtures are available
As per MoEF&CC guidelines, water reduction can be achieved up to 36% using water conserving fittings with sensors, auto valves, pressure reducing device wherever possible which can result in significant reduction in water consumption.
i. Water closets (WCs):
Conventional toilets use 9 litres of water per flush. Low flush toilets are available with flow rate of 6.0 litres and 3.0 litres of water per flush.
Dual flush adapters can be used for standard flushing for solid waste and a modified small flush for liquid waste
Flush valves with 20-25 mm inlets can be used for restricting the water flow
d. Reduction of hardscape
At least 50% of the total paved area on site should either be soft-paved and/or shaded under trees/ pergolas/ solar photovoltaics, etc.
Limit use of turf on the site to conserve water and/ or ensure that landscaped area is planted with drought tolerant / native / adaptive species.
Avoid disturbance to the site by retaining natural topography (and/ or) design vegetated spaces on the ground, for at least 15% of the site area.
Restore disturbed site area by designing vegetated spaces over built structures and on the ground, for at least 30% of the site area (including development footprint).
Preserve or transplant at least 75% of existing fully grown trees within the project site / campus.
Plant tree saplings that can mature into fully grown up trees within the next 5 years on the project site, as per the below criteria (including existing and transplanted trees in the project site).
The landscape here refers to soft landscaping which includes only pervious vegetation.
Areas planted with turf should not exceed a slope of 25 percent (i.e., a 4:1 slope).
Landscape areas over built structures such as basements, podium, roofs, etc., can be considered for the calculation.
Retaining ‘Natural Topography’ in its broad sense means preserving the natural features of the terrain such as exposed natural rocks, water body, etc.,
Grass medians, grass pavers, jogging track, open-air theatre, parking areas, driveways, walkways, playground, swimming pool, etc., are considered as site disturbances.
Native / adaptive vegetation shall be retained as much as possible.
Potted plants shall not be considered as vegetation.
2. Solar Energy Utilization Bye laws: 10.2 (2)
All efforts need to be made towards optimum and efficient use of energy sources for life sustenance. The increasing thrust on using non-fossil fuel energy for all needs have to be given priority consideration. The tapping of renewable sources of energy for lighting, heating, cooling and ventilation needs, deserve special attention.
Note: For captive solar power generation, a minimum of 15 % of sanctioned load is the requirement.
a. Installation of Solar Photovoltaic Panels
Solar photovoltaic (PV) systems are direct energy conversion systems that convert solar radiation into electric energy. Roof of buildings as well as other exposed areas such as of parking shade, vertical/inclined walls, windows can be installed with solar PV system. can be installed with solar PV system.
b. Installation of Solar Assisted Water Heating Systems
i. Solar water heating systems should be made in the building for hospitals, hotels, hostels, guest houses, police men/ army barracks, canteens, laboratories and research institutions, schools and colleges and other institutes.
ii. The solar water heating system should be mandatory in the hospitals and hotels, where the hot water requirements are of continuous nature. These buildings must be provided with auxiliary back-up system.
iii. The use of solar water heating system is recommended in the following type of buildings in Government/ Semi-Government and Institutional buildings where the hot water requirements may not be continuous/ permanent.
Guest Houses
Police men/Army barracks
Canteens
Laboratory & Research Institutions where hot water is needed.
Hostels, Schools, Colleges and Other Institutes.
iv. The Installation of the electrical back up in all such water heating system shall be optional depending on the nature of requirements of the hot water.
v. It is suggested that solar heating systems of the capacity of about 100 liters per day based on thermos phonic with necessary electrical back-up be installed at residential buildings like hostels.
vi. In order to facilitate the installation of the solar water heating systems, the new buildings shall have the following provisions:
vii. All such buildings where solar water heating systems are to be installed will have open sunny roof area available for installation of solar water heating system.
The roof loading adopted in the design of such building should be at least 50 kg per sq. m. for the installation of solar water heating system.
A solar water heating system can also be integrated with the building design. These either can be put on the parapet or could be integrated with the south facing vertical wall of the building. The best inclination of the collector for regular use throughout the year is equal to the local latitude of the place. The Collectors should be facing south. However, for only winter use the optimum inclination of the Collector would be (Latitude + 15 degrees of the south.). Even if the Collectors are built in south facing vertical wall of building the output from such Collectors during winter month is expected to be within 32% output from the optimum inclined Collector.
All the new buildings to be constructed shall have an installed hot water line from the rooftop and insulated distribution pipelines to each of the points where hot water is required in the building.
The capacity of the solar water heating system to be installed on the building shall be described on the basis of the average occupancy of the building. The norms for hospitals, hotels and other functional buildings are given below:
Table 9Recommended capacity in various types of Buildings
Sr. No.
Type of Buildings
Capacity recommended - liters per capita per day
1
Hospitals
100
2
Hotels
150
3
Hostels & other such Building
25
4
Canteen
As required
5
Laboratory & Research Institutions
As required
An Open area of 3 sq.m would be required for installation of a collector which supplies about 100 liters of water per day. At least 60% of the roof area may be utilized for installation of the system.
The specification for the solar water heating system laid down by the Ministry of Non-Conventional Energy Sources can be followed. Flat plate collector confirming to Bureau of Indian Standards - latest standard should be used in all such solar water heating systems.
3. Energy Efficiency Bye laws: 10.2 (3)
a. Low Energy Consumption Lighting Fixtures
Lamps, luminaries, ballasts and the controlling systems should be monitored for achieving energy efficiency through artificial lighting.
i. Interior Lighting
For Residential Buildings
Lamps – Lamps used for general lighting scheme shall conform to the following
Point Light Source – All the point light sources installed in the building for general lighting shall be CFL or LEDs or equivalent.
Linear Light Source – All the linear light sources installed in the building for general lighting shall be T-5 or at least 4 Star BEE rated TFLs or equivalent
The installed interior lighting power shall not exceed the LPD (lighting power density) value as recommended by ECBC 2007 (Chapter 7, section 7.3)
For buildings other than residential
Lamps – Lamps used for general lighting shall conform to the following
Point Light Source – All the point light sources installed in the building for general lighting shall be CFL or LEDs or equivalent.
Linear Light Source – All the linear light sources installed in the building for general lighting shall be T-5 or at least 4 Star BEE rated TFLs or equivalent
The installed interior lighting power shall not exceed the LPD (lighting power density) value as recommended by ECBC 2007 (Chapter 7, section 7.3)
Lighting controls shall be installed as recommended by ECBC 2007 (Chapter 7, section 7.2.1) in buildings with connected load of 100 kW or more.
* Exemption to (a) – Spaces in the building where high bay lighting is required
ii. Exterior Lighting
For Commercial, Multi-storey Residential Complexes, Group Housing Societies, Apartment complexes, etc.
Lamps – External lighting sources shall have minimum luminous efficacies as per the table given below
Table 10Minimum allowable luminous efficacy of various light sources
S No.
Light Source
Minimum allowable luminous efficacy (lm/W)
1
CFLs (compact fluorescent lamps)
50
2
LEDs (light emitting diodes)
50
3
Fluorescent Lamps
75
4
Metal Halide Lamps
75
5
High Pressure Sodium Vapour Lamps
90
The installed exterior lighting power density for the respective applications shall be in accordance with ECBC 2007 (Chapter 7, section 7.4)
Lighting controls shall be installed as recommended by ECBC 2007 for external lighting (Chapter 7, section 7.2.1.4)
b. Energy Efficiency in HVAC systems design (Applicable to all use premises) (mandatory for commercial and desirable for residential):
Energy efficiency in HVAC system design for buildings
The inside design conditions of a conditioned space shall conform to National Building Code 2005 (Part 8, section 3)
The outside design conditions shall conform to National Building Code 2005 (Part 8, section 3)
Efficiency of the equipment installed shall comply with ECBC 2007 requirement (Chapter 5, section 5.2.2)
The distributed cooling systems (Unitary air conditioners/ Split air conditioners) shall be at least BEE 3 Star rated products.
To avoid the conductive heat losses through piping and ductwork insulation shall be provided as recommended by ECBC 2007 (section 5.2.4)
4. Waste Management Bye laws: 10.2 (4)
Facilitate segregation of waste at source to encourage reuse or recycling of materials, thereby avoiding waste being sent to landfills.
a. Segregation of Waste
i. Building-level Facility - Provide separate bins to collect dry waste (paper, plastic, metals, glass, etc.,) and wet waste (organic), at all the floors and common areas of the building, as applicable. Divert the collected waste to a centralized facility, which is easily accessible for hauling.
ii. Centralized Facility - In addition to dry and wet waste bins, provide separate bins for safe disposal of the following hazardous waste, at the centralized facility:
Batteries
‘e’ waste
• Lamps
Medical waste, if any
Note: The project has to follow the Hazardous Waste Management Guidelines as prescribed by the Ministry of Environment & Forest (MoEF), Government of India.