PENAL ACTION FOR VIOLATION OF PROVISIONS OF MASTER PLAN/ZONAL PLAN REGULATIONS/ BYE-LAWS (Please refer clause 2.2, 2.7.7(b) & 2.8 of this document).
All fees and charges to be decided by Sanctioning Authority as notified from time to time
(A) Non Compoundable Items: Any deviations from the maximum, minimum prescribed limits regarding:-
-
No. of floors
-
No. of DUs &density
-
Parking norms
-
Light and ventilation provisions
-
Use premises
-
All other provision of these bye-laws except items given in para ‘B’ below shall not be compounded/ regularized and shall have to be rectified by altering/demolition at the risk and cost of owner. Besides this any other action as per terms &conditions of lease and provisions of Delhi Development Act, 1957 shall proceed.
-
Staircase.
(B) Compoundable Items
Sanctioning Authority shall be empowered after levying penalty to compound deviations from limits of coverage/FAR to the extent of 5% of the permissible coverage and FAR, a subject to maximum of 13.5 sq.m in building(s)/ premises at the time of considering the completion/occupancy certificate. In group Housing schemes and Public & semi-public facilities, 5% FAR beyond permissible FAR can be compounded by the Sanctioning Authority at the time of considering the completion/ occupancy certificate. The charges for compounding the deviation shall be as follows:
-
Up to 0.5% - same charges* as for permissible additional FAR.
-
Above 0.5 to 2.5% - 5 times the charges* as for permissible additional FAR.
-
Above 2.5% to 5% - 10 times the charges* as for permissible additional FAR.
* Charges as notified from time to time by the authority/ concerned local body
i. Deviations in terms of covered area- If a building or part thereof has been constructed unauthorized i.e. without obtaining the requisite building permit from the Sanctioning Authority as re¬quired under clause 2.0 of the building bye-laws, the same shall be compounded at the following rates provided the building or part thereof so constructed otherwise conforms to the provisions contained in the Building Bye-Laws and Master/Zonal Plan regulations. For this the owner shall have to submit the request for building permit in the prescribed procedure.
RATES (Prior to Sanction Charges)
a) Rs. 50 per sq.m of the covered area constructed unauthorized in residential building upto 500 sq.m plot size.
b) Rs. 200 per sq.m of the covered area constructed unauthorized in building categorized below:
(i) All Government Public and Semi-public and Utility buildings
(ii) Religious, Institutional &Educational Buildings
c) Rs. 500 per sq. m of the covered area constructed unauthorized
(i) Residential buildings above 500 sq. m plot size, Group Housing & Guest Houses
(ii) Industrial Buildings:
(iii) Storage buildings (underground or above ground)
d) Rs. 2000 per sq. m of the covered area constructed unauthorized:
(i) Commercial & Business Buildings
(ii) Cinema & Theatre Buildings
(iii) Petrol Pumps (filling/Service Stations)
(iv) Hazardous Building.
e) RATES (Pre- Occupancy Charges): Shall be charged on the covered area/built up area occupied without obtaining Completion cum Occupancy certificate:
a) Pre-occupancy charge @ Rs. 25,000/- per dwelling unit in case of Residential-Plotted or Group Housing.
b) For Mercantile/Commercial/ Industrial / Cinema / Petrol Pump/Hazardous building @ Rs. 2000/- per sq.m
c) For Institutional/Govt. /Religious/Public-Semi-Public/ Utility/Storage/ Others/ @ Rs. 500/- per sq.m
Note: a. The building not covered specifically under the above categories shall be compounded as decided by the Sanctioning Authority, considering the merit of each individual case.
b. Item which are exempted from the calculations of the coverage and FAR e.g. cup-boards, canopy, basement &mezzanine, loft, watchman cabins etc. but constructed unauthorized without obtaining prior permission from the Sanctioning Authority, but within the permis¬sible limits shall also be compounded/ regularized at the rate prescribed above.
c. Compounding at setback infringements
The infringement of the setback maximum to the extent of 0.3 m may be compounded by the way of levying compounding fees at the following rates:
| Infringements | Residential Buildings | Non-Residential Buildings |
|---|---|---|
| Up to 0.15 m | Rs. 1000 per sq. m of the area infringing the set back | Rs. 2500 per sq. m of the area infringing the set back |
| above 0.15 m | Rs. 2500 per sq. m of the area infringing the set back | Rs. 5000 per sq. m of the area infringing the set back |
ii. Deviations of the building bye-laws other than as specified in (A) (Non- Compoundable).
Deviations up to the maximum extent of 10% from the maximum/minimum prescribed limit (as prescribed by the building bye-laws) shall be compounded at the following rates:-
a. In case of deviations of areas of various components of the buildings, the rate of penalty will be @ Rs.100/- per 1 % of deviation.
b. For deviations in terms of height the penalty shall be @ Rs. 100/ -per 1 % of deviation’ for every 10 sq.m or part there of the affected area.
c. Deviations from the prescribed limit of width: length penalty shall be @ Rs. 100/- per 1 % of the deviation for every 10 sq. m or part there of the affected area.
-
Notwithstanding the provisions above, no penalty shall be levied for the first 3% of deviation but in case deviation limit exceed 3% penalty shall be levied at the above rates for the total deviation up to 10%.
-
The penalties at the above rates as given in ii (a), (b) &(c) shall be charged for each deviation and for every component of the building separately.
d. In case of increase in size of canopy in front open space from the prescribed limits of bye-laws, the same shall be charged @ Rs. 200/- per sq. m.
e. End walls up to 0.9 m in terrace type construction constructed purely as an architectural feature- Rs. 100/ -each.
f. Enclosing of front balcony by Jali wall which is being used as a part of stair-case¬ Rs. 2500/-Sq. m.
g. Toilet constructed without sanction on terrace (refer 7.2.2. f) – Rs.500/-per sqm.
h. All roof projections beyond permissible limit of bye-laws as specified shall be counted towards FAR calculations if otherwise the same do not infringe upon other bye-laws except the canopy as said in para (d) above.
j. Extra slab in mumty constructed without sanction shall be compounded at the rate given in (B) (compoundable item) provided it does not infringe upon the provision of any other bye-laws.
k. Partition walls provided without sanction at any floor if the same are not infringing upon the provision of any other bye-laws Rs. 150/- per sq. m of the surface area of the wall i.e. (length x height).
l. Projection on public land: -Not permitted.