a. Fee for approval: Fee for approval of Layout Plan/ Site Plan or Sub-division Plan@ Rs. 10,000/- per acre
b. Betterment levy/additional FAR charges and penalty/compounding charges/special compounding charges:
The gazette notification of 23.07.98 regarding enhanced FAR, number of Dwelling Units shall be charged @ Rs. 450/- sq.m over and above the FAR of group housing given in Master Plan for Delhi- 2001 -
| Notification | Max. FAR | Net Housing Density | Max. height |
|---|---|---|---|
| Dated 1.8.90 | 133 | 140 | 26m |
| Dated 23.7.98 | 167 | 175 | 33m |
| Difference | 35 |
c. Surcharge: In cases where the additional construction has already been carried out without getting sanction as per notification 23.07.1998 norms but which are within the norms as revised vide notification dated 23.7.1998, the construction will be regularized on payment of the levy plus a surcharge of 10%. This will be addition to the existing compounding fee, etc.
2.1.1 Fees for Inspection and completion
a. Notice for inspection of completion work up to plinth level shall be accompanied with fee of Rs.500/-Please refer Form C-1
b. Application for completion certificate shall be accompanied with fee of Rs. 10/- per sq.m of covered area.
c. Pre-occupancy charges: - Pre-occupancy charge @ Rs. 25,000/- per dwelling unit in case of group housing.
For Commercial building @ Rs. 2000/- per sq.m
For Institutional/Govt./Others@ Rs. 500/- per sq.m
a. Fees & Charges are to be determined by the Authority/ concerned local body from time to time and shall be payable by applicant/Owner.
b. Charges for compoundable deviations shall be as per Annexure IV.
c. Charges applicable for compoundable construction shall be as per Development Code clause 3(12) of MASTER PLAN for DELHI 2021 (Chapter-17) [Building Bye laws- Annexure IV, Clause 3(12)].
2.1.1 Peripheral charges:- Peripheral charges are to be paid by plot owner of Co-operative House Building Society Group IV for laying of such services by the DDA @ Rs. 70/-(in view of Hon’ble Court orders and consequent office order No. 80 dated. 12.06.03) per sq.m of net plot area at the time of sanction of building plans. Also, individual plot owner will submit an undertaking in the prescribed format for deposition of peripheral charges, at the time of submission of Building Plans.
3 Betterment charges for additional construction at Terrace:- As per Notification No.K-12016/10/82-DD IIA dt.10.08.83, the permission of construction at terrace as a dwelling unit was permitted, provided the intending builders deposit betterment charges@150/-per sq.m of built up area either at the time of sanction of building plans or regularization of structure at the time of issue of completion/occupancy certificate. The betterment charges are levied for coverage beyond 25% and in case of provision of regular dwelling unit proposed even with 25% and in case of provision of regular dwelling unit proposed even with 25% coverage, full betterment charges are levied.
4 Additional FAR charges:- Means levy payable on the additional FAR allowed @ Rs. 450/- per sq.m to be calculated for additional FAR, applicable on individual residential plot vide Notification No. K-12016/5/79-DD IIA/VA/IB dated. 23.07.98 over and above the FAR applicable vide Notification No. K-12016/5/79-DD IIA/IB dated. 15.05.95 which is shown in Table 1 below:
| S. No. | Area of the Plot (Sq. m) | FAR as per Notification dated23.07.98 | FAR as per Notification dated15.05.95 | Difference (FAR to be charged) |
|---|---|---|---|---|
| 1 | Below 32 | 225 | 150 | 75 |
| 2. | Above 32 to 50 | 225 | 150 | 75 |
| 3. | Above 50 to 100 | 225 | 180 | 45 |
| 4. | Above 100 to 250 | 200 | 160 | 40 |
| 5.(a) | Above 250 to 500 | 150 | 140 | 10 |
| (b) | Above 500 to 750 | 120 | 100 | 20 |
| 6. | Above 750 to 1000 | 100 | 83 | 17 |
| 7. | Above 1000 to 1500 | 100 | 83 | 17 |
| 8. | Above 1500 to 2250 | 100 | 83 | 17 |
| 9. | Above 2250 to 3000 | 100 | 83 | 17 |
| 10. | Above 3000 to 3750 | 100 | 83 | 17 |
| 11. | Above 3750 | 100 | 83 | 17 |
5 Surcharge: In cases where the additional construction has already been carried out without getting sanction as per notification 23.07.1998 norms but which are within the norms as revised vide notification dated 23.7.1998, the construction will be regularized on payment of the levy plus a surcharge of 10%. This will be addition to the existing compounding fee, etc.
Note: The building plans shall be sanctioned subject to certification by the Chief Town Planner, Local Body that up gradation of infrastructure and services has been done or are inexistence and layout/services plans revised in consonance with July 23,1998 Notification.
6 Betterment levy/additional FAR charges and penalty/compounding charges: Betterment levy or additional FAR charges in respect of additional construction shall be chargeable as follows:-
i. The plot owners/allottees seeking extra coverage, additional FAR or part thereof, over and above the original FAR, as has been provided in Notification dated 23.07.1998, Notification dated 22.09.2006 and Notification dated 26.11.14 shall be applicable, as per the FAR differences given in Table 3.1 & Table 3.2. and for charges refer Table 2 S. No.1.
ii. Plot owners/allottees seeking regularization of construction over the coverage allowed as per notification dated 23.07.1998 in terms of the additional coverage allowed under the Notification dated 26.11. 14, shall have to pay penalty/levy/betterment levy charges / compounding charges as mentioned in Table 2, S.No. 2 (a) & 2 (b).
iii. Plot owners/allottees seeking regularization of additional height in terms of notification dated 22.09.2006, shall have to pay penalty and special compounding as given in Table 2 S.No. 2(c) below:-
| S. No. | Purpose | A & B Colonies | C & D Colonies | E, F & G Colonies: in plots more than 50 sq.m | E, F & G Colonies: in plots up to 50 sq.m |
|---|---|---|---|---|---|
| 1 | New Construction | 3500 /- | 1400 /- | 700 /- | 490 /- |
| 2 | Regularization of unauthorized construction | ||||
| (a) | Additional Coverage within sanctioned height | 3500 /- | 1400 /- | 700 /- | 490 /- |
| (b) | Additional Coverage above sanctioned but within permissible height (as per23.07.1998) | 4375 /- | 1750 /- | 875 /- | 613 /- |
| (c) | Additional Coverage beyond permissible height as per 23.07.1998 but within 15 m | 4900 /- | 1960 /-* | 980 /- | 686 /- |
Rates in Rs. Per sq.m
Height permissible as per notification dated. 23.07.98 is 12.5m
Note: The orders of Hon’ble Supreme Court, dated 14th March 2008, with regard to permissibility in respect of ground coverage, FAR and height according to building norms as per MASTER PLAN for DELHI – 2021 shall be applicable subject to the terms laid down in the above order (in the matter of M.C Mehta v/s UOI and others in IA nos.212-2212 in W.P (Civil) No. 4777 of 1985).
These charges shall be levied on difference in maximum ground coverage (%), FAR, number of dwelling units and height between notification dated 23.07.1998 and notification dated 26.11.14 are as given below:-
| S. No. | Area of the Plot (Sq. m.) | FAR as per Notification dt 23.07.98 | FAR as per Notification dt. 22.09.06 | Difference (FAR to be charged) |
|---|---|---|---|---|
| 1 | Below 32 | 225 | 350 | 125 |
| 2. | Above 32 to 50 | 225 | 350 | 125 |
| 3. | Above 50 to 100 | 225 | 350 | 125 |
| 4. | Above 100 to 250 | 200 | 300 | 100 |
| 5. | Above 250 to 500 | 150 | 225 | 75 |
| 6. | Above 500 to 1000 | 120 | 150 | 30 |
| 7. | Above 1000 to 1500 | 100 | 120 | 20 |
| 8. | Above 1500 to 2250 | 100 | 120 | 20 |
| 9. | Above 2250 to 3000 | 100 | 120 | 20 |
| 10. | Above 3000 to 3750 | 100 | 120 | 20 |
| 11. | Above 3750 | 100 | 120 | 20 |
| S. No. | Area of the Plot (Sq. m.) | FAR as per Notification dt. 22.09.06 | FAR as per Notification dt. 26.11.14 | Difference (FAR to be charged) |
|---|---|---|---|---|
| 1 | Below 32 | 350 | 350 | NIL |
| 2. | Above 32 to 50 | 350 | 350 | NIL |
| 3. | Above 50 to 100 | 350 | 350 | NIL |
| 4. | Above 100 to 250 | 300 | 300 | NIL |
| 5(a) | Above 250 to 500 | 225 | 225 | NIL |
| 5(b) | Above 500 to 750 | 150 | 225 | 75 |
| 6. | Above 750 to 1000 | 150 | 200 | 50 |
| 7. | Above 1000 to 1500 | 120 | 200 | 80 |
| 8. | Above 1500 to 2250 | 120 | 200 | 80 |
| 9. | Above 2250 to 3000 | 120 | 200 | 80 |
| 10. | Above 3000 to 3750 | 120 | 200 | 80 |
| 11. | Above 3750 | 120 | 200 | 80 |
Note: All fees and charges to be decided by concerned Sanctioning Authority as notified from time to time. Notwithstanding anything contained in this Annexure, in case of any repugnancy between the provisions of this Annexure and provisions of concerned Sanctioning Authority, the provisions of concerned Sanctioning Authority shall prevail over this Annexure.