The following exemption to open space shall be permitted.
7.17.1 Projections into open spaces: Every interior open space shall be kept, free from any erection thereon and shall be open to the sky. Nothing except cornice, chajjas or weather shade (not more than 0.75 m wide) shall overhang or project over the said open spaces so as to reduce the width to less than the minimum required.
Interior open to sky areas shall be allowed to cover with retractable roofing at the terrace level or at minimum double height to prevent climatic/weathering effects and the space below can be used as landscaped area, public space but can not be used for any commercial purpose.
a. Such projections shall be allowed at a height more than 2.20 m from the corresponding finished floor level.
b. Pergola shall be permitted if constructed in the exterior open spaces within plot line or terrace. Such pergola shall not exceed 30% of ground coverage. Such pergolas shall have a minimum clear height of 2.2 m with 40% void. On terrace, the maximum height of the pergola shall not exceed the height of the Mumty.
7.17.2 The following shall not be included in covered area for FAR and Ground Coverage calculations, subject to Fire Safety Clearances and other mandatory clearances:
a. Machine room for lift on top floor as required for the lift machine installation.
b. Rockery, lift/ lift well, escalator/travellator well and well structures, plant nursery, water pool, swimming pool at any level (if uncovered), platform around a tree, tank, fountain, bench, chabutara with open top and / or unenclosed sides by walls, open ramps, compound wall, gate, slide swing door, fire staircase, fire towers, refuse area, fire control room, overhead water tank on top of building/open shafts, UGR, STP, ETP, cooling towers or any other service structures as per fire norms. Fire tender movement shall be unhindered.
c. Mumty over staircase on top floor maximum 3m height.
d. Culvert on Municipal drains.
e. Watch and ward cabins of total area not more than 4.5 sqm. and 6 sqm. with W.C each at entry and exit only, within the property line. Movable Porta cabins (max.size 2 sqm.) for guard room is permitted within the plot line in residential plots of size minimum 200 sqm. and above.
f. Entrance porch, canopies and balconies.
g. All pergolas at any floor level not exceeding 20% of Ground Coverage.
h. Sky bridges/Sky walks(covered or uncovered) or intermittent floors as relief in high rise buildings having landscape areas, service floors in high-rise buildings, jogging tracks, swimming pools and other public spaces shall not be counted in FAR irrespective of height and not to be counted towards ground coverage.
i. Architectural and Landscape features on ground or any other floor including rooftops such as swimming pool, terrace garden or any other features as approved by sanctioning authority, Delhi Urban Art Commission and Delhi Fire Service.
j. Architectural elements such as louvers, end wall projected upto 900mm, pergolas, claddings upto 150mm in each side, other sunshade elements (referred in clause 7.1 of these bye laws) should be free from FAR and Ground Coverage.
k. Any landscape element which has built up area as approved by sanctioning authority/ Delhi Urban Art Commission and Delhi Fire Service wherever applicable.
l. The projections (cantilever) of cupboards and shelves shall be permitted and are exempted from covered area calculations in all type of buildings except Mercantile and Business buildings. Such projection shall not exceed 0.75 m in depth and not hindered the fire tender movement.
m.Plinth steps.
n. Area of all staircase/s, Fire Tower/s in high rise/low rise buildings, excluding residential plotted development, shall not be counted in FAR and Ground coverage.
o. ESS/ Meter Room with HT/LT panel, DG Room, AC Plant room, CC TV room/Control room, Fire Control room UGR/STP/ETP and similar services are permitted in the setback subject to approval of DFS and shall not be counted in ground coverage and FAR.
p. Solar Panels at any height or level (including ground level)/terrace/roof top subject to the max. height permitted by AAI/clearance from DFS.
q. In multistory building service shafts like electrical shafts, communication shafts, fire shafts MEP and HVAC shall not be counted in ground coverage in FAR.
r. For entrance lobby/lobby area, See 8.10(i). Entrance Lobby/Lobby Area is not permitted free from FAR and Ground Coverage in residential plotted development.
s. Male and Female common toilets served by a public corridor shall be free from FAR, but shall be counted in Ground Coverage.
t. For the additional area of passageway/ corridor constructed over and above the prescribed /permissible limit, See7.11.2.i.
u. Interior open to sky areas shall be allowed to covered with retractable roofing at the terrace level or at minimum double height to prevent climatic/weathering effects and the space below can be used as landscaped area, public space but cannot be used for any commercial purpose.
7.17.3 Only temporary site office shall be allowed during construction, which shall be removed before occupancy of building or validity of building sanction whichever is earlier.