New Delhi, the 9th December, 2016
S.O. 3999(E).—Whereas, by notification of the Government of India in the erstwhile Ministry of Environment and Forests number S.O.1533 (E), dated the 14thSeptember, 2006 issued under sub-section (1) read with clause (v) of sub-section (2) of section (3) of the Environment (Protection) Act, 1986 and clause (d) of the sub-rule (3) of rule 5 of the Environment (Protection) Rules, 1986, the Central Government directed that on and from the date of its publication, the required construction of new projects or activities or the expansion or modernisation of existing projects or activities listed in the Schedule to the said notification entailing the capacity addition with change in process or technology and or product mix shall be undertaken in any part of India only after prior environmental clearance from the Central Government or as the case may be, by the State Level Environment Impact Assessment Authority, duly constituted by the Central Government under sub-section (3) of section 3 of the said Act, in accordance with the procedure specified therein;
And whereas, the said Ministry has received suggestions for ensuring Ease of Doing Responsible Business; and streamlining the permissions for buildings and construction sector which is important for providing houses and for this purpose the scheme of Housing for all by 2022 with an objective of making available affordable housing to weaker sections in urban area has ambitious target; And whereas clause (a) of sub-rule (3) of rule 5 of the Environment (Protection) Rules, 1986 provides that, whenever the Central Government considers that prohibition or restrictions of any industry or carrying on any processes or operation in any area should be imposed, it shall give notice of its intention to do so;
And whereas, a draft notification for making amendments in the Environment Impact Assessment Notification, 2006 issued in exercise of the powers conferred under sub-section (1) and clause (v) of sub-section (2) of section (3) of the Environment (Protection) Act, 1986 read with clause (d) of the sub-rule (3) of rule 5 of the Environment (Protection)Rules, 1986 was published, vide number S.O.1595 (E) dated the 29thApril 2016, inviting objections and suggestions from all the persons likely to be affected thereby, within a period of sixty days from the date of publication of said notification in the Gazette of India;
And whereas, all objections and suggestions received in response to the above mentioned draft notification have been duly considered by the Central Government;
Now, therefore, in exercise of powers conferred by sub-section (1) and clause (v) of sub-section (2) of section 3 of the Environment (Protection) Act, 1986 (29 of 1986), read with clause (d) of sub-rule (3) of rule 5 of the Environment (Protection) Rules, 1986, the Central Government hereby makes the following further amendments in the Environment Impact Assessment Notification, 2006 namely:-
In the said Notification,-
(I) afterparagraph13,thefollowingparagraphshallbeinserted,namely:-
“14.Integrationofenvironmentalconditioninbuildingbye-laws.-
(1) The integrated environmental conditions with the building permission being granted by the local authorities and the construction of buildings as per the size shall adhere to the objectives and monitorable environmental conditions as given at Appendix-XIV.
(2) The States adopting the objectives and monitorable environmental conditions referred to in sub- paragraph (1), in the building bye-laws and relevant State laws and incorporating these conditions in the approvals given for building construction making it legally enforceable shall not require a separate environmental clearance from the Ministry of Environment, Forest and Climate Change for individual buildings.
(3) The States may forward the proposed changes in their bye-laws and rules to the Ministry of Environment, Forest and Climate Change, who in turn will examine the said draft bye-laws and rules and convey the concurrence to the State Governments.
(4) When the State Governments notifies the bye-laws and rules concurred by the Ministry of Environment, Forest and Climate Change, the Central Government may issue an order stating that no separate environmental clearance is required for buildings to be constructed in the States or local authority areas.
(5) The local authorities like Development Authorities, Municipal Corporations, may certify the compliance of the environmental conditions prior to issuance of Completion Certificate, as applicable as per the requirements stipulated for such buildings based on the recommendation of the Environmental Cell constituted in the local authority.
(6) The State Governments where bye-laws or rules are not framed may continue to follow the existing procedure of appraisal for individual projects and grant of Environmental Clearance for buildings and constructions as per the provisions laid down in this notification.
(7) For the purpose of certification regarding incorporation of environmental conditions in buildings, the Ministry of Environment, Forest and Climate Change may empanel through competent agencies, the Qualified Building Environment Auditors (QBEAs) to assess and certify the building projects, as per the requirements of this notification and the procedure for accreditation of Qualified Building Auditors and their role as given at Appendix-XV.
(8) In order to implement the integration of environmental condition in building bye-laws, the State Governments or Local Authorities may constitute the Environment Cell (herein after called as Cell), for compliance and monitoring and to ensure environmental planning within their jurisdiction.
(9) The Cell shall monitor the implementation of the bye-laws and rules framed for Integration of environmental conditions for construction of building and the Cell may also allow the third part auditing process for oversight, if any.
(10) The Cell shall function under the administrative control of the Local Authorities.
(11) The composition and functions of the Cell are given at Appendix-XVI.
(12) The Local Authorities while integrating the environmental concerns in the building bye-laws, as per their size of the project, shall follow the procedure, as given below:
BUILDINGS CATEGORY ‘1’ (5,000 to < 20,000 Square meters)
A Self declaration Form to comply with the environmental conditions (Appendix XIV) along with Form 1A and certification by the Qualified Building Environment Auditor to be submitted online by the project proponent besides application for building permission to the local authority along with the specified fee in separate accounts. Thereafter, the local authority may issue the building permission incorporating the environmental conditions in it and allow the project to start based on the self declaration and certification along with the application. After completion of the construction of the building, the project proponent may update Form 1A online based on audit done by the Qualified Building Environment Auditor and shall furnish the revised compliance undertaking to the local authority. Any non-compliance issues in buildings less than 20,000 square meters shall be dealt at the level of local body and the State through existing mechanism.
OTHER BUILDINGS CATEGORIES (≥ 20,000 Square meters)
The project proponent may submit online application in Form 1 A alongwith specified fee for environmental appraisal and additional fee for building permission. The fee for environmental appraisal will be deposited in a separate account. The Environment Cell will process the application and present it in the meeting of the Committee headed by the authority competent to give building permission in that local authority. The Committee will appraise the project and stipulate the environmental conditions to be integrated in the building permission. After recommendations of the Committee, the building permission and environmental clearance will be issued in an integrated format by the local authority.
The project proponent shall submit Performance Data and Certificate of Continued Compliance of the project for the environmental conditions parameters applicable after completion of construction from Qualified Building Environment Auditors every five years to the Environment Cell with special focus on the following parameters:-
(a) Energy Use (including all energy sources).
(b) Energy generated on site from onsite Renewable energy sources.
(c) Water use and waste water generated, treated and reused on site.
(d) Waste Segregated and Treated on site.
(e) Tree plantation and maintenance.
After completion of the project, the Cell shall randomly check the projects compliance status including the five years audit report. The State Governments may enact the suitable law for imposing penalties for non-compliances of the environmental conditions and parameters. The Cell shall recommend financial penalty, as applicable under relevant State laws for non-compliance of conditions or parameters to the local authority. On the basis of the recommendation of the Cell, the local authority may impose the penalty under relevant State laws. The cases of false declaration or certification shall be reported to the accreditation body and to the local body for blacklisting of Qualified Building Environment Auditors and financial penalty on the owner and Qualified Building Environment Auditors.
No Consent to Establish and Operate under the Water (Prevention and Control of Pollution) Act, 1974 and the Air (Prevention and Control of Pollution) Act, 1981 will be required from the State Pollution Control Boards for residential buildings up to 1,50,000 square meters.”;
(II) In the Schedule, for item 8 and the entries relating thereto, the following item and entries shall be substituted, namely:-
| (1) | (2) | (3) | (4) | (5) |
| "8 | Building / Construction projects / Area Development projects and Townships | |||