2.0 Overview of procedure and general requirement
2.0.1 Procedure
(a) For residential plots up to 105 sq.m in size forming a part of approved layout/ special areas/ unauthorized regularized colony/ village abadis/ lal dora /extended lal dora resettlement colonies and slum & JJ cluster/ Rehabilitation Colonies, excluding those within LBZ, the procedure and documentation shall be as per ‘SARAL’ scheme given in Chapter 4 of these Bye Laws.
(b) The entire process from applying for sanction of building plan to issue of occupancy-cum-completion certificate shall consist of following steps:
(i) Submission of application for sanction of building plan and NOC applications in Common Application Form (CAF) along with building permit fees, drawings and documents.
(ii) Grant of sanction within stipulated period, Payment of requisite fees & charges, as applicable, and release of sanctioned building plan.
(iii) Intimation of completion of work up to plinth level.
(iv) Plinth level inspection and online issue of plinth level inspection certificate.
(v) Submission of application for issue of Occupancy-cum-Completion Certificate (OCC) and NOCs (Fire, Water etc) in Common Occupancy-cum-Completion Certificate Request Form (COCCRF) along with requisite fees, drawings and documents.
(vi) Single joint site inspection by all concerned departments.
(vii) Intimation of compounding fee and charges, if applicable, and release of OCC along with completion plan.
(c) However, the above procedure shall stand amended to the extent specified in the fast track procedures specified in Chapter 3 based on risk-based classification of buildings.
(d) Building permit not required: No notice and building permit is required for addition/alterations which do not otherwise violate any provisions regarding building requirements, structural stability, fire safety requirements and involve no change to the cubic contents or to the built up area of the building, as defined in bye laws, for the following:
i. Plastering/ cladding and patch repairs *.
ii. Re-roofing or renewal of roof including roof of intermediate floor at the same height.
iii. Flooring and re- flooring.
iv. Opening and closing windows, ventilators and doors opening within the owner’s plot. No opening towards other’s property/ public property will be permitted.
v. Rehabilitation/repair of fallen bricks, stones, pillars, beams etc.
vi. Construction or reconstruction of sunshade not more than 75 cm in width within one’s own land and not overhanging over a public street;
vii. Construction or reconstruction of parapet and also construction or re-construction of boundary walls as permissible under these bye-laws;
viii. White washing, painting etc. including erection of false ceiling in any floor at the permissible clear height provided the false ceiling in no way can be put to use as a loft/ mezzanine, etc.
ix. Reconstruction of portions of buildings damaged by storm, rains, fire, earthquake or any other natural calamity to the same extent as existed prior to the damage as per sanctioned plan, provided the use conforms to provisions of MPD.
x. Erection or re-erection of internal partitions provided the same are within the preview of these bye-laws.
xi. For erection of lifts in existing buildings in residential plotted development (low–rise). Change/installation/ rearranging/ relocating of fixture(s) or equipment/s or HVAC-MEP services, UGR,STP/ETP without hindering other’s property/public property shall be permitted.
xii. Landscaping
xiii. Public art
xiv. Bank ATM (up to a maximum area of 9.0 sqm only), Public washroom, security room /guard room are permitted in setback area, provided it does not obstruct fire vehicles movement, in plot more than 3000 sqm (other than residential plotted), as per Chapter 12.
xv. Placing a porta cabin upto 4.5 sqm within the plot line subject to free fire tender movement.
Note: The liability for any structural flaws or defects in the buildings arising out of such additions/ alterations shall rest with the owner/ architect/ engineer/ structural engineer.
* For Heritage Buildings, refer Annexure II.
2.0.2 Information required from the applicant by the sanctioning authority and other agencies to be provided in CAF and COCCRF
(a) Information required from the applicant by the sanctioning authority and for granting No Objection Certificates by the internal/ external agencies such as Delhi Fire Services, Delhi Urban Art Commission, Airports Authority of India, Delhi Pollution Control Committee, Heritage Conservation Committee, Department of Forest, Department of Labour, Delhi Jal Board, National Monuments Authority, Chief Inspector of Factories, Director General of Explosives, etc., shall be provided in CAF/COCCRF, as applicable.
(b) Any undertaking/ declaration required by the sanctioning authority or any other agency, shall be part of CAF/COCCRF, as applicable.
2.0.3 Bulk characteristics for Development: Bulk characteristics for development on any specific plot can be determined by the owner/ concerned professional(s) by referring to the Master Plan for Delhi, Zonal Development Plan, layout plan, land records such as lease deed/ conveyance deed, allotment/ auction conditions, control drawings, other applicable guidelines, etc. The sanctioning authority shall ensure that the Master Plan for Delhi, Zonal Development Plans, approved layout plans, other applicable guidelines are made available free of cost in the public domain on their websites.
2.0.4 The plans/ drawings to be submitted at various stages of the process to the sanctioning authority shall adhere to the following requirements:
(a) Key Plan: Layout/ site plans shall include a key plan drawn to a scale of not less than 1:10,000 showing boundary and location of the site with respect to neighboring landmarks including North Point.
(b) Size of Drawing Sheets: Size of drawing sheets shall be any of those specified in table 2.1 below:
| S.No | Designation | Trimmed size, mm |
|---|---|---|
| 1 | A0 | 841x1189 |
| 2 | A1 | 594x841 |
| 3 | A2 | 420x594 |
| 4 | A3 | 297x420 |
| 5 | A4 | 210x297 |
| 6 | A5 | 148x210 |
(c) All dimensions in drawings shall be indicated in metric unit.
(d) Recommended notation for colouring of plans: The site and building plans shall be coloured as specified in the table 2.2 given below. The colouring notation used for items, which are not listed in table 2.2, shall be indexed: