Chapter XIIIInfrastrucutre Investments for CMA A. Chennai Metropolitan Development Plan (CMDP)
Cities play a vital role in social and economic development. Efficient and productive cities are essential for national economic growth and equally, strong urban economies are essential for generating the resources needed for public and private investments in infrastructure, social facilities, improved living conditions and poverty alleviation.
13.02 Environmental degradation holds back economic development. The urban challenge put forth before us is to improve the environmental quality and make the city livable. The level of services have to be improved by better planning, management and maintenance of the services, which could be achieved by channalising the investments in the right directions.
13.03 Every citizen has his/her own perception about city where one lives. The benefits to the citizens of CMA because of the proposed Infrastructure Investment Plan named as CMDP are:
- Improvement in the quality of life
- Higher standard of living
- Improvements in service level
- Eco-friendly environment
- Reduced pollution levels
- Less congested roads and better parking facilities
- Hassle free travel by public and private transport and
- Better employment opportunities by attracting more industries/ commercial establishments.
Benefits to The Investors
13.04 In the recent past Chennai has attracted many industries including the Information Technology Industries. Chennai has many natural advantages including availability of a Sea Port and other infrastructure attracting the large-scale industries. The strength of Chennai City is mainly the availability of good infrastructure facilities, skilled labour and availability of land for developments.
13.05 CMDA considering the need for making investments for infrastructure developments in a planned and co-ordinated manner, has proposed infrastructure investment plan called as “CMDP” in consultation with the department agencies and local bodies concerned.
13.06The major objectives of the Plan are:
i. to identify the infrastructure needs in each sector and work out the projects accordingly;
ii. to identify the quantum of finance for execution of these projects;
iii. to identify the source of finance;
iv. to prioritize the projects by working out the annual programme, medium term programmes and long term programmes;
13.07 In Chennai Metropolitan Area the development and maintenance of urban services are vested with the specialised agencies. CMWSSB, TWAD and concerned local bodies provide water supply electricity by TNEB, solid waste management by the concerned local bodies, roads by Highways and local bodies, storm water drains by local bodies and PWD. These agencies depend on Central Government, State Government and financial institutions for funding their projects. The cost of the projects to be executed in various sectors estimated to be of several crores and these projects cannot be implemented with the State Govt. budgetary support alone; additional resources have to be mobilized.
13.08 The infrastructure requirements for the Chennai City, 16 Municipal areas, 20 TP, Panchayats and 214 village Panchayats and 10 Panchayat unions which lie within Chennai Metropolitan Area have been collected from the concerned agencies and the Investment Plan for them has been prepared.
13.09 The Investment Program has been categorized into 3 categories viz. annual, medium and long-term projects. The projects that need immediate investment have been included in the annual program. The projects which have to be executed to fulfill the infrastructure requirements in the medium term have been included in the medium term programmes. Projects which require heavy investments with long gestation periods have been included in the long term programmes.
Table No.13.01 Investment Plan Rs. in Crores
Table No.13.01 Investment Plan Rs. in Crores
Table No.13.01 Investment Plan Rs. in Crores
Table No.13.01 Investment Plan Rs. in Crores
Programme/Agency
Annual Plan(2003-2004)
Medium Term Plan(2004-2007)
Long Term Plan
Traffic and Transportation
Traffic and Transportation
Traffic and Transportation
Traffic and Transportation
Urban Rail Projects
165.00
519.24
3528.00
Road/River Bridge
3.00
7.00
-
Traffic Management
11.94
3.00
-
Resurfacing of Major Roads
43.11
-
-
Strengthening of peri urban Roads
4.54
13.62
4.56
ORR
-
250.00
250.00
Widening & Strengthening of city roads
57.80
-
-
New Road formation
21.50
-
350.00
Relaying of City Roads
99.00
297.00
-
Study for Augmenting the capacity of Major Arterial Roads
0.25
3.55
-
Widening & Strengthening
-
1595.58
-
Cement Conc. - Anna Salai
-
101.32
-
Road Over/Under Bridge
-
832.71
-
Bus Terminal
-
6.00
-
Multilevel Parking
-
48.00
-
Urban Road Projects
-
-
1126.00
Urban Transit System
-
-
855.00
Truck Terminal
-
80.00
-
Sub Total
406.14
3757.02
6113.56
Housing
Housing
Housing
Housing
TNHB
5.00
570.00
-
TNSCB
27.70
330.41
325.00
Sub Total
32.70
900.41
325.00
Water Supply
Water Supply
Water Supply
Water Supply
CMWSSB
730.00
946.00
649.18
Sewerage
Sewerage
Sewerage
Sewerage
CMWSSB
295.00
607.00
897.78
CMA (Thiruvottiyur Mpty)
28.00
-
-
Sub Total
323.00
607.00
897.78
Storm Water Drain
Storm Water Drain
Storm Water Drain
Storm Water Drain
Chennai Corporation
40.00
47.00
-
PWD
44.65
3.65
-
Highways
3.68
-
-
SIDCO
0.68
-
-
CMA
13.77
-
-
DTP
8.94
10.59
-
Sub Total
111.72
61.24
-
Solid Waste Management
Solid Waste Management
Solid Waste Management
Solid Waste Management
Chennai Corporation
16.00
35.00
-
CMA
11.19
16.25
-
Sub Total
27.19
51.25
-
Electricity
TNEB
150.00
1910.81
-
Total
1780.75
8233.73
7985.52
Grand Total
18000.00
13.10 The main sources of finance identified are loans from financial institutions, budgetary support/grant from government. Public-private participation is also proposed for the housing, water supply and sewerage projects.
13.11 Based on this overall plan, annual plans are formulated in consultation with the sectoral agencies / departments, Government budgetary allocations made and implemented as Annual Plans since 2003-04. CMDA monitors the progress of implementation and report to the Government. The investment made since 2003 sectorwise under CMDP is given below.
Annual Programme 2003-04, 2004-05, 2005-06 & 2006-07 (Rs. in Crores)
Programme
Investment in 2003-04
Investment in 2004-05
Investment in 2005-06
Investment in 2006-07
Traffic & Transportation
412.16
237.28
179.48
199.28
Housing
40.77
65.17
65.27
68.91
Water Supply
581.60
309.03
99.61
92.67
Sewerage
83.16
122.88
66.23
49.58
Storm Water Drain
38.97
40.39
103.10
17.71
Solid Waste Management
-
3.695
6.06
9.94
Electricity
164.88
179.21
211.32
188.52
Others
-
-
3.36
0.44
Total
1321.54
957.66
795.58
670.23
B. Jawaharlal Nehru Urban Renewal Mission (JN-NURM)
13.12 The Government of India in 2005 has introduced the scheme called Jawaharlal Nehru Urban Renewal Mission (JN-NURM) to encourage reforms driven, fast tract planned development of identified cities with a focus on efficiency in urban infrastructure / service delivery mechanisms, community participation and accountability of urban local bodies towards citizens.
13.13 The Mission objectives are to ensure the following in the urban sector including the basic services to urban poor:
a. Integrated development of infrastructure services in cities covered under the Mission.
b. Establish linkages between asset creations and asset management for long term project sustainability.
c. Ensure adequate funds to fulfill deficiencies in the urban infrastructural services
d. Planned development of identified cities including peri urban areas, out growths and urban corridors leading to dispersed urbanisation.
e. Scale up delivery of civic amenities and provision of utilities with emphasis on universal access to urban poor.
f. Special focus on urban renewal program for the old city areas to reduce congestion.
g. Provision of basic services to urban poor including security of tenure at affordable prices, improved housing, water supply and sanitation and ensuring delivery of other already existing universal services of the Government for education, health and social security.
13.14 The Mission strategy includes preparing perspective plan called as City Development Plan (CDP), preparing projects, leveraging of funds and incorporating private sector efficiencies. The duration of the Mission is 7 years beginning from the year 2005-06. The nodal agency for the State of Tamilnadu is TUFIDCO and the concerned department at Government of Tamilnadu is Municipal Administration and Water Supply. Chennai is one of the identified cities for Government of India assistance under JN-NURM. To comply with the prerequisite of preparation of CDP, the City development plan for Chennai as called as ‘Development Plan for Chennai Metropolitan Area’ was prepared and Government of India’s approval obtained.
13.15 Strengths-weakness-opportunities and threats in respect of Chennai are given below:
Strengths
Opportunities
Strong Commercial and Industrial Base
High telecom penetration
Skilled and educated man power
Growth oriented reforms
High standard educational and health institutions
Public Private Participation
Good urban land market and availability of developable lands.
Uninterrupted and quality power supply
Weaknesses
Threats
Traffic congestion
Automobile pollution
Inadequate infrastructure
Overcrowding in certain pockets
Water shortage
Decrease in manufacturing industry
Institutional Arrangements in Development Planning
13.16 The rapid urban population growth and consequent pressure on the developments in major urban centres have led the Government of Tamil Nadu to set up specialised agencies to tackle the urban development issues in various sectors such as housing, water supply and sewerage etc. The principal ones are CMWSSB, TNSCB, and TNHB. The Chennai Metropolitan Development Authority was set up in 1973 with the main objective of being in charge of long term planning and co-coordinating the various urban development activities in the Metropolis.
13.17 The agencies involved in the infrastructure planning and development in CMA are presented below. The details of agencies and its responsibilities are presented in the table no.13.02 below.
Table No.13.02 The Details of Agencies and its Responsibilities
Table No.13.02 The Details of Agencies and its Responsibilities
Table No.13.02 The Details of Agencies and its Responsibilities
Table No.13.02 The Details of Agencies and its Responsibilities
Sl.No.
Agency
Responsibility
Jurisdiction
Local Government
Local Government
1
Chennai Corporation-
Provision of roads, construction of ROBs, RUBs, pedestrian subways etc., streetlights, solid waste collection and management, micro-drainage, parks and play grounds in their area of jurisdiction
Within the local body area
2
Municipalities-
Provision of roads, construction of pedestrian subways etc., streetlights, solid waste collection and management, micro-drainage, parks and play grounds in their area of jurisdiction
Within the local body area
3
Town Panchayats
Provision of roads, construction of pedestrian subways etc., streetlights, solid waste collection and management, micro-drainage, parks and play grounds in their area of jurisdiction
Within the local body area
4
Village Panchayats
Provision of roads, construction of pedestrian subways etc., streetlights, solid waste collection and management, micro-drainage, parks and play grounds in their area of jurisdiction
Within the local body area
Parastatal Agency
Parastatal Agency
5
TNHB
Neighbourhood development including provision of plots and ready built houses, Sites and Services schemes.
Tamil Nadu State but focus is more on CMA
6
MTC
Bus transport
CMA
7
Traffic Police (Greater Chennai)
Traffic management schemes
Greater Chennai
8
TNEB
Electricity generation and supply
Tamil Nadu State
9
PWD
Implementation & maintenance of macro drainage system
Tamil Nadu State
10
CMDA
Urban planning, co -ordination of project implementation
CMA
11
CMWSSB
Water supply & sewerage facilities for CMA
CMA*
12
TNSCB
Provision of housing, infrastructure and livelihood programs in slum areas
Tamil nadu State but focus is more on CMA
13
Highways Department
Major roads within Chennai City, all bus route roads and major district roads, construction of ROBs, RUBs, pedestrian subways etc.
Tamil nadu State
* Though CMWSSB has jurisdiction over the CMA as per their Act, their area of operation are limited presently to Chennai City Corporation area and a few adjoining areas such as Mogappair, I.T.Corridor etc. However they have proposed to expand their area of operation covering the entire CMA.
13.18 Though the geographical areas of jurisdiction of these agencies overlap, their operational jurisdictions and functions are well defined. For example in the Chennai City Municipal Corporation Area, CMWSSB is solely in charge of water supply and sewerage; in respect of National Highways and roads except for the major roads handed over to State Highways for maintenance, others are maintained by the Chennai Municipal Corporation. In respect macro drains such as rivers and canals the PWD is responsible of maintenance; the micro drains are provided and maintained by the City Corporation of Chennai and other local bodies within CMA.
13.19 Capital investment plan for the various sector proposed under JN-NURM are given below.