- Various measures taken to improve and strengthen the transport supply in CMA in the past include:
a) Procurement of about 305 buses under Madras Urban Development Project MUDP-I, 915 buses under MUDP-II and 1600 buses under Tamil Nadu Urban Development Project (TNUDP) through PTC and DATC (now merged into MTC) was made at a cost of about Rs.63 m, Rs.221 m and Rs.927.50 m respectively.
b) In addition, 3 bus depots and 8 terminals were constructed during MUDP-I and 10 bus depots/terminals under TNUDP.
c) The following rail projects were implemented by Southern Railway.
i) Quadrupling Chennai-Arakkonam B.G. Line (upto Pattabiram);
ii) Gauge conversion of Chennai Beach - Tambaram - Chengelpattu lines including optimisation of the line (by replacing road/rail level crossings by overpasses or underpasses) (under implementation);
iii) Development of Mass Rapid Transit System (MRTS) from Chennai Beach up to Thirumylai for a length of 8.5 km in the I Phase at a cost of Rs.2690 m commissioned in 1997; and
iv) Commissioning of II phase of MRTS from Thirumylai to Velachery (11.165 km) at cost of Rs.7690m on 19, Nov. 2007
-
Critical bottlenecks in the road network have been improved under MUDP I (Rs.15.20 cr), MUDP II (Rs.63 m) and TNUDP (Rs.839 m) through Department of Highways (DoH) and Chennai Corporation (CoC). These included forming an inner ring road for a length of 17.5 km initially and dualling its carriageway subsequently. The balance of it comprising the northern segment for a length of 12.5 km has been formed and the southern segment for a length of 6 km. is being formed. The First phase of Chennai Bypass connecting NH 45 and NH 4 for a length of 19 Km at a cost of Rs.900 m has already been completed and commissioned in November 2002. Development of Chennai Mofussil Bus Terminal (CMBT) at Koyambedu has been completed at a cost of Rs.1030 m and commissioned in Nov. 2002. Chennai City Contract Carriage Bus Terminal (CCCBT) has also been constructed and commissioned. Improvements to radial roads in and around CMA have been carried out for a total length of 250 km at a cost of 2120 m.
-
The major road and rail investments proposed for the future comprise the following:
a) Extension of MRTS Phase II from Velachery to St.Thomas Mount for a length of 5 Km at a cost of Rs.4160 m;
b) Development of II phase of Chennai Bypass from NH4 to NH5 for a distance of 13 km. at a cost of Rs.4450 m;
c) Construction of 4 No. grade-separators, 3 on IRR and 1 on NH-45 opp. airport at a cost of Rs. 2100 m;
d) Gauge Conversion of Chennai Beach-Tambaram rail line at a cost of Rs.2350 m;
e) Development of an Outer Ring Road for a distance of 62 Km at a cost of Rs.9000 m;
f) Developing the 2nd BG coaching terminal at Egmore;
g) Development of 3rd rail line from Beach to Athipattu;
h) Development of 4th rail line from Beach to Athipattu;
i) Quadrupling the rail line between Pattabiram and Thiruvallur;
j) Development of 3rd rail line from Thiruvallur to Arakkonam;
-
Drawing a cue from the document viz. Action plan for IT corridor, 2003 prepared by CMDA, GoTN have commenced implementation of a high quality 6-lane arterial road from Chennai to Mammallapuram for a length of 47 km at a cost of Rs.1217.4 m through IT Expressway Ltd., a special purpose vehicle floated through TNRDC to serve the IT and ITES industries located primarily in the southern outer-CMA.
-
Recognising the fact that the capacity of the urban road network can be appreciably increased by removing the major bottlenecks in the network particularly along such strategic roads such as IRR, it has been proposed to construct well-designed grade separators at all the critical intersections of radial roads with IRR. In the first phase NHAI on its own is developing 3 grade separators at Kathipara, Padi and Koyembedu intersections and one opposite airport on GST Road at a total cost of Rs.2100 crores. These are expected to be completed with a period of 18 to 24 months. The GoTN are proposing to develop the grade-separators at Thirumangalam and Vadapalani intersections of IRR in the second phase.
Non-transport developments
-
The Government in the Transport Department have already taken various initiatives for introducing innovative technologies for motorised vehicles. The Govt. have recently directed for induction of 5000 LPG operated autos in the City. There are also 14 no. ALDS (automatic LPG Dispensing System) in the City. Already electric operated cars manufactured by a company (Reva) are on the roads of Chennai. The strategy to improve the air quality in the metropolis will be principally governed by such conscious measures as to tilt the modal share in favour of public transport modes and the initiatives being taken both by GoI and GoTN to phase out lead in petrol and sulphur dioxide in diesel, making it mandatory on the part of vehicle manufacturers to conform to Bharat II, to introduce pollution-free fuels such as CNG/LPG for vehicle operation.
-
Several non-transport measures were also implemented over the last decade to reduce traffic congestion. These include decentralisation of the CBD, viz., shifting of the whole-sale market to koyambedu, the Iron and Steel Market to Sathangadu, construction of truck terminal at Madhavaram which have relieved the arterials and other City roads considerably from the lorry and bus traffic.
Institutional arrangement
- The traffic and transportation schemes are presently implemented by several departments and agencies. While long-term planning and coordination is carried out by CMDA, individual schemes are executed by Railways, DoH, CoC, MTC; The traffic enforcement is carried out by Chennai Traffic Police (CTP). There are a number of committees to coordinate the implementation of transport schemes in the CMA. They are:
i) High Level Coordination Committee for MRTS (Chaired by Vice-Chairman, CMDA) for coordinating implementation of MRTS Phase-I&II
ii) Chennai Road Safety Council (Chaired by Commissioner of Police) for traffic enforcement
iii) Coordination Committee (Chaired by Superintending Engineer, Chennai Corporation)
iv) Indian Transport Road Development Association (Chaired by Rane Power Steering Ltd.).
v) Besides these agencies, there are agencies, which are concerned with licencing of vehicles and policy making such as Regional Transport Office etc.
In the absence of financial and administrative powers vested with these committees, the coordination effected by these committees is limited.
- Under the UNDP-UNCHS supported Sustainable Chennai Project, through the deliberations of the action committee and working groups certain actions for substrategies such as
(i) optimising the utility of existing transport infrastructure;
(ii) enhancing the modal share of rail and bus and
(iii) improving the air quality
were discussed and implemented.