Major findings in the Study on Environmental Impact Assessment of the drainage and redevelopment proposal for Pallikaranai Area (consultants: KBN Engineering and Applied Sciences, Inc., Florida and Mukesh & Associates, Salem):
-
No significant adverse impacts will be caused by the preferred drainage scheme.
-
The preferred drainage scheme will allow for limited development in the study area. Severe flooding including flooding from the 50 and 100-year storm events, which now precludes development, will be reduced to acceptable levels to allow for development. Further reduction in the effects of flooding can be achieved by raising plinth levels of buildings onsite to approximately 2.0 m. above Survey of India datum (m-ASoI) and the incorporation of onsite stromwater retention and detention ponds.
-
The proposed PDA will have a significant positive benefit to the people and economy of the region. Given proper site planning, no significant adverse effects will occur from development of the PDA.
-
Development of the PDA in the study area is most desirable because of:
a) Protection from flooding,
b) Compatibility with existing land uses,
c) Proximity to existing transportation infrastructure,
d) Available labour force and
e) Negligible environment impacts.
-
The most compatible land uses for the PDA are a combination of medium, light and service industries. The development of heavy industry in the PDA is not recommended given the generally good environmental quality in the area; the requirements for stringent pollution control, monitoring and enforcement, and its incompatibility with existing land use.
-
The three most important future impacts to the preferred drainage scheme and PDA development once the preferred drainage scheme is implemented are:
a) Uncontrolled flow of offsite contaminated water to the site.
b) Effects of offsite development affecting onsite water elevations and
c) Uncontrolled induced development in the PDA which may result in relocation issues for future development.
- Relocation to the proposed reservoir is recommended for several reasons including
a) Potential water quality impacts from existing and proposed offsite development
b) Conflicts with proposed TNHB residential development
c) The existence of better alternative locations, i.e. use of tanks adjacent to the study area.
-
Relocation of the proposed MMRD road to the PDA is recommended because of the potential water quality impacts it will cause north of the East-West Flood Protection Bund. It can be located in the PDA where it can better serve the traffic needs of future development within the PDA as well as meet the Area’s traffic needs.
-
A relocation of the proposed TNHB development in the northern part of the study area needs to be considered since it is planned to occur in areas identified for portions of the drainage infrastructure. This proposed development could be incorporated in the PDA.
-
There are major offsite developments including the Perungudi landfill and the Pallikkaranai sewage treatment plant which significantly affect onsite water quality including water flowing to the Oggiam Maduvu. Future expansion of these and other development needs to be evaluated in light of impacts to the preferred drainage scheme and the PDA.
-
A basin-wide storm water management plan is necessary to assure the proposed drainage scheme will operate effectively as future development occurs adjacent to the study area and PDA.
-
Restoration and enhancement of the Velacheri Marsh should be undertaken to assure protection of surface water quality entering the study area.