17.1 Electric Vehicle Charging Infrastructure (EVCI)
Based on the occupancy pattern and the total parking provisions in the premises of the various building types, charging infrastructures shall be provided only for EVs, which is currently assumed to be 20% of all 'vehicle holding capacity'/'parking capacity' at the premise.
Additionally, the building premise will have to have an additional power load, equivalent to the power required for all charging points (in a PCS) to be operated simultaneously, with a safety factor of 1.25 (refer Explanatory Note- Annexure E-1 as given in paragraph 17.2 of this chapter)
17.1.1 Residential Buildings (plotted house)
17.1.1.1 Charging Infrastructure requirements for individual house/self-use:
| Building Type | Plotted House |
|---|---|
| Ownership of station | Private (Owner) |
| Connection and Metering | Domestic meter |
| Type of Charger | Slow charger as per owner's specific requirements |
| Modes of Charger | AC (Single charging gun) |
| Norms of Provisions | Min.1 SC and additional provisions as per the owner individual |
Note: -
The charging infrastructure installed by a homeowner shall be construed as a Private Cl meant for self-use (non-commercial basis) as per the note at clause no 4 of the explanatory notes at Annexure E-1 given in paragraph 17.2 of this chapter.
17.1.2 All other buildings (including Group Housing)
Any PCS installed at Public/Private areas or building premises of any category that caters to commercial mode of charging of EVs shall be deemed as a Public Charging Station and shall have to install the minimum requirements of chargers as specified in the Guidelines dated 14.12.2018 of Ministry of Power (refer Annexure E-2 for MoP Guidelines). However, in order to provide sufficient charging points for the EV share in all vehicles (refer clause 3 of the Explanatory Note-Annexure E-1 given in paragraph 17.2 of this chapter), ratio of types of chargers is recommended in the table below-
17.1.2.1 Charging Infrastructure requirements for PCS (commercial use):
| Building Type | Any building type | |||
| Ownership of Station | Service provider | |||
| Connection and Metering | Commercial Metering and Payment | |||
| Type of Charger | as per min requirements specified in MoP Guidelines (refer Annexure E-2 given in paragraph 17.8 of this chapter) | |||
| Additional Chargers | PCS service providers shall install additional number of kiosk/chargers beyond the minimum specified requirements to meet the ratio of charging points as prescribed below (by the type of vehicles). | |||
| Norms of Provisions for charging points | 4Ws 1 SC-each 3 EVs 1 FC-each 10 EVs | 3Ws 1 SC - each 2 EVs | 2Ws 1 SC - each 2 EVs | PV (Buses) 1 FC- each 10 EVS |
Note:
(i) Charging bays shall be planned currently at 20% capacity of all vehicles including 2Ws and PVs(cars)
(ii) Open metering and on-spot payment options to be available for all users.
(iii) Provision of FCB, CS and BS shall not be mandatory and will be at the discretion of the service provider.
Abbreviations used:
2Ws Two wheelers
3Ws Three wheelers
4Ws Four wheelers/PV (cars)
PVs Passenger Vehicles
EV Electric Vehicle
SC Slow Charger/Slow Charging (AC)
FC Fast Charger/Fast Charging (DC and a few AC ones)
PCS Public Charging Stations
FCBCS Fluid Cooled Battery Charging Station
BS Battery Swap
17.1.2.2 Space Norms for Electric Vehicle Charging Infrastructure:
| Sl. No. | Category | Population served per unit | Land area requirement | Other controls | |
| Type of Facility | Area Required | ||||
| A. | Public Charging Stations | Every 25 Kms, both sides along the highways/ roads | PCS with charger ratio (min. requirements of PCS, as per MoP) 1 FC for every 10 EVs 1 SC for every 3 EVs | Additional area as per total parking capacity at the Restaurants/Eateries | Equipped with CCE and LCC, as may be required for fast charging. |
| B. | Fast Charging facility/FCB CS (for long Distance & Heavy Duty EVs) | Every 100 Kms. both sides along the highways/ roads | At least 2 chargers 1 CCC type 1 CHAdeMO type (min. 100KW each) | Min. 15m x 7m | May be coupled with the PCS at item A above, with CCE and LCC. |
| C. | Battery Swapping Station | Optional provisions as per MoP Guidelines | Standalone | Min. 5.5m x 2.75m | May be coupled with PCS at item A or FCB CS at item B above. |
| Provided along with FBC charging Stations | |||||
Source: Urban & Regional Development Plans Formulation and Implementation Guidelines (URDPFl-2014)