20.1 Infrastructure Estimates for 2035
20.1.1 Water Supply Cost Estimates for 2035
Water demand for urban area under SUDA authority is estimated under different heads using CPHEEO norms.
| Category | Water Demand(per day) | Demand for 2025(MLD) | Demand for 2035(MLD) |
|---|---|---|---|
| Household | 150 per capita | 1140 | 1445 |
| Health Institutions | 400/per bed | 14 | 14 |
| Government offices | 45 per capita | 1.1 | 1.1 |
| Industrial demand | 145 | 145 | |
| Railway station | 70 per capita | 28 | 35 |
| Colleges | 45 per capita | 6.1 | 8.1 |
| Schools | 45 per capita | 73.7 | 95.1 |
| Total Demand | ~1410 | ~1750 |
Source: CPHEEO manual
Total capital cost of additional water supply infrastructure during these two phases (2016-2025 and 2026-2035) are given below.
| Category | Unit Cost | 2016-2025 (Cr. INR) | 2026-2035 (Cr. INR) | Total Cost (Cr. INR) |
|---|---|---|---|---|
| Augmentation of Intake Wells | 0.1 Cr/MLD | 15 | 27.9 | 42.9 |
| Additional treatment capacity with SCADA system | 0.3 Cr/MLD | 52.8 | 209.4 | 262.2 |
| Network costs | 12 Cr/sq.km. | 2324 | 3844 | 6168 |
| Cost of water meters | 2000/ unit | 356.7 | 171 | 527.7 |
| Total | 2748.5 | 4251.9 | ~7001 |
Average inflation rate of 5% per year is considered
Source: Surat Municipal Corporation records
It would be difficult to estimate the infrastructural requirements for each and every village of the area. Therefore, the villages are divided in 5 categories according their populations for ease in estimating the requirements. Estimates for these population classes are given in the table below. The towns having estimated population higher than 20,000 have already been considered as a part of estimates made for city area.
SURAT URBAN DEVELOPMENT AUTHORITY |
Page
| Capital work | Cap. Ex. for population upto 2,000 | Cap. Ex. for population upto 5,000 | Cap. Ex. for population upto 10,000 | Cap. Ex. for population upto 15,000 | Cap. Ex. for population upto 20,000 |
|---|---|---|---|---|---|
| Unit Estimated Cost | 12,15,000 | 50,00,000 | 90,00,000 | 1,50,00,000 | 2,00,00,000 |
Source: Cost functions for predicting capital expenditure of small town water systems
| Sr. No. | Category | Total number of villages | Total Cost |
|---|---|---|---|
| 1 | Population up to 2,000 | 52 | 6,31,80,000 |
| 2 | Population up to 5,000 | 82 | 41,00,00,000 |
| 3 | Population up to 10,000 | 27 | 24,30,00,000 |
| 4 | Population up to 15,000 | 10 | 15,00,00,000 |
| 5 | Population up to 20,000 | 5 | 10,00,00,000 |
| Total | 176 | 96,61,80,000 | |
| Total Inflated Value | 1,17,19,76,340 |
Considering 5% inflation every year and 70% of investment in first 10 years
20.1.2 Sewerage Estimates for 2035
Based on the population projections and city expansion within SUDA area, the total infrastructural requirements in terms of sewerage is estimated below. This is done considering the current gaps in service delivery and future needs. The estimates are made in two phases, 2025 and 2035. Four major components of any drainage system are Sewage Treatment Plant, Sewage Pumping Stations, Underground Network including Rising Mains. To estimate the future cost requirements, cost for unit area for each of these four components is considered. The unit costs for these components are provided in table given below.
| Sr. No. | Component | Unit Cost (Cr. INR/ km²) |
|---|---|---|
| 1 | Sewage Treatment Plant | 2.84 |
| 2 | Pumping Stations | 2.78 |
| 3 | Network | 3.79 |
| 4 | Rising Mains | 1.32 |
Source: Surat Municipal Corporation records
Considering this as unit cost of development per hectare area and projecting it for two invest phases of year 2025 and 2035, following results were found. Total urbanised area in 2014 was around 197 sq.km. The total drainage network in the city during the same year was in area of 154 sq.km. This mean that 43 sq.km. of the urban area was still without drainage system. The priority would be to lay down sewerage in this area in addition to the expansion of the city area which is estimated to be around 163 sq.km. The total area to be covered with sewerage by 2025 comes out to be 206 sq.km. Phase-wise estimates for this period are given in the table below.
|211
C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C C
DEVELOPMENT PLAN 2035
2017
| Investment Year | Area to be Covered | Investment at present value (Cr. INR) | Investment at inflated value |
| 2016 | 82.4 | 884 | 884 |
| 2019 | 61.8 | 663 | 809 |
| 2022 | 61.8 | 663 | 935 |
| Total by 2025 |
20.1.3 Solid Waste Management Estimates for 2035
Municipal solid waste within Surat city is collected by Surat Municipal Corporation. Door-to-door collection of waste is done from households, commercial users. Collected waste is then taken to transfer stations, from where it is transported to the dumping site.
For more efficient solid waste management system, the 'segregation of waste at source' is essential. Collection of segregated (dry and wet) will be done for the amount projected in the table below.
| Category | 2025 | 2035 |
|---|---|---|
| Projected population within city | 76 lakhss | 96 lakhss |
| Per capita of waste generation estimated | 450 gm | 450 gm |
| Total waste generation estimated | 3420 TPD | 4325 TPD |
| Dry component of total waste generated | ~1200 TPD | ~1515 TPD |
| Wet component of total waste generated | ~2250 TPD | ~2815 TPD |
The collected waste will be processed at decentralised facilities spread all across the cities. Decentralised processing is recommended for saving fuel costs and avoiding unnecessary transportation of waste over long distances. Overall processing cost of waste is around 400 Rs. / per capita/year for large cities. The investment estimates are given in the table below.
Page
| Category | Unit cost (Present value) | 2016-2025(Cr. INR) | 2026-2035(Cr. INR) | Total by 2035 (Cr. INR) |
| Door-to-door collection of waste and transportation of waste | - | Outsourcing | Outsourcing | |
| Processing of dry+wet waste and treatment | INR 1000/ capita/ 2-3 years | 3276 | 7074 | 10,350 |
| Cost of secondary collection bins | - | - | - | - |
| Cost of engineered landfill | INR 176.5/ tonne | 43 | 91 | 134 |
| Total | 3319 | 7165 | 10,484 | |
| Average inflation rate of 5% per year is considered | ||||