11.3Multiple Units(for single stand-alone residential plots)
In order to promote additional housing stock, provision of multiple Housing units on a single Residential Plot is permissible. The total covered area will be within the prescribed FAR limits and the number of residential units, shall be based upon the available approach road width, will be as follows:
S. No.
Existing road width
Minimum area of plot
Number of units
Plains
Hills
1
9.0-18.0mt.
6.0-9.0mt.
500 sq. mt. (in hill area 250 sq. mt.)
6
More than 500 sq. mt. (more than 250 sq. mt. in hill area) one additional unit admissible for increase in plot area for every 125 sq. mt.
2
more than 18.0 mt.
more than 9.0 mt.
750 sq. mt. (in hill area 500 sq. mt.)
10
More than 500 sq. mt. (more than 250 sq. mt. in hill area) one additional unit admissible for increase in plot area for every 125 sq. mt.
Table 22: Provision for multiple housing units on a single residential plot
Note:
• Provision of a minimum 5% open / Green area mandatory
25% of infrastructure development cost is to be deposited as Bank Guarantee or Agreement for mortgaging of property of similar value with the Development Authority.
In such cases in addition to the fixed payable fees, Rs. 50,000 / - for each unit as “unit fees shall be necessarily deposited.
11.4Group Housing / Sub Division Layout
(i) The project of group housing / sub-division layout shall be classified on the basis of their areas as follows:
S. No.
Habitat Description
Plains
Hills
Area (Ha)
Area (Ha)
Min
Max
Min
Max
1
Sub Cluster
0.20
2.0
0.10
1.0
2
Cluster
2.01
6.0
1.01
3.0
3
Neighborhood
6.01
20.0
3.01
10.0
4
Township
20.01
40.0
10.01
20.0
5
Special Township
Above 40.0
Above 20.0
Table 23: Classification of Group Housing / Sub-division layout
Note The detail provision of Special Township shall be fixed separately
(ii) Registration ofRegistered Habitat Developer in the respective Habitat category is mandatory.
However, for layout (sub-division) projects of less than one acreand for projects (layout and group housing) Within the Development Area / Special Development Area, such registration is not mandatory. Processing fee for such projects is Rs 50,000.00and for projects of area more than one acre, the processing fee and Bank Guarantee will be as per the provisions of Group Housing.
(iii) Dwelling Unit Density: 500 Dwelling unit per hectare(For Hills and Plain)
S. No.
Plot Size
Dwelling Unit Density
1
Upto 200 sq. mt. Plot size
1 Unit
2
200 sq. mt.- 300sq. mt.
2 unit
3
300- 500sq. mt.
3 unit
4
> 500sq. mt.
as per density defined for multiple units
Table 24:Calculation of Dwelling Unit Density for Layout Plans
On the basis of the proposed population in Group Housing and Layout Schemes, facilities and services viz. health education shall be provided in the projects as mentioned in clause 7.5. Further, for the proposed population in the project, sufficient provisions shall be made w.r.twater supply, electricity, sewer etc. as per the prevailing norms and standards.
The proposed density shall be permissible based upon the availability of potable water demand projected for next ten years, for which NOC from the concerned Authority shall be obtained.
(iv) Internal Road Width (Residential Group Housing and Layout Schemes)
S. No.
Minimum Road Width (mt.)
Maximum Road Length (mt.) (if it is not in the form of loop street)
Plains
Hills
1
7.5
2
100m
2
9
3
200m
3
9
4.5
400m
4
12
6
800m
5
15
7.5
1000m
6
18
9
1000m
7
Minimum width of loop street 9.0m
Minimum width of loop street 6.0m
Minimum length 400m
a. Width of such Roads,havingPark / Open space / Inactive uses on one side will be 7.5m in plain and 4.5m (motor-able) 2.0m (pedestrian) in Hills.The maximum length of such road will be 200mt.
b. In EWS and LIG layout schemes the minimum internal roads will be 6.0 mt. in plains and 4.5 mt. (for motor-able roads) and 2.0 mt. (for pedestrian Pathways) in Hills.
(v) Other Provisions
In Group Housing and sub-division layout projects the following facilities / services will be provided in proportion of the total scheme area. In Building where vertical mix uses are permitted the proportion of Public / Semi Public and commercial use will be based on the total FAR of the project
S. No
Uses / Facilities
Plot size
2000 to 4000 sq. mt.
4000 sq. mt. to 2.0 Hectare
More than 2.0 Hectare
1
Public / Semi Public (Uses ancillary to Residential viz. Educational / Health / Club House / Community Hall etc.
-
Minimum 1.0%
Minimum 5.0%
2
Commercial
-
Maximum 1.5%
Maximum5%
3
Organized Green Spaces
Minimum 5%
Minimum 10%
Minimum 15%
Table 25: Facilities / Services in Group Housing and sub-division layout projects
Note:The above facilities will be based on the Population norms as defined in para 7.5
(vi) Light and Ventilation
In buildings of upto 12.0 mt. height, habitable rooms, where light and ventilation is provided through internal green spaces, the minimum area and width of such spaces will 7.5sq. mt. and 2.5sq. mt. respectively. For building of more than 12.0m height the minimum width of much spaces will be 3.0 m and the area shall be equal to 1 / 5 t h of the height of the adjacent highest wall (e.g. If the height of the highest wall is 21 mt., then the minimum area of the internal open space shall be (21*1 / 5)= 17.64 sq. mt.
S. No.
Building Height (in mt.)
Area (in sq. mt.)
Minimum Width (mt.)
1
Upto 7.0m
1.2
0.9
2
Upto 12.0m
2.8
1.3
3
Upto 18.0m
4.0
1.5
4
Upto 21.0m
5.4
1.8
5
More than 21.0m
6.0
2.0
Table 26: Size of Ventilation shaft
(vii) Guard Room of maximum 1.6sq. mt. Plinth Area (Minimum width / radius 1.2m)is permissible at the entrance subject is the condition that such construction will not be within the setback required for fire safety
11.5 Affordable Housing
As per the housing policy and the rules (annexure- )
11.6Public facilities and Services
S. No.
Main category
Sub-category
Population Standards
1
Educational Facilities
Nursery School / Crèche
1 for 2500
Primary school(upto class 5th ) (max G+I)
1 for 5000
Middle school (upto class 8th )
1 for 6000
High school / intermediate (upto class 5th to 10th or upto th12 )
1 for 7500
Integrated school (upto class 1-12th )
1 for 15000
ITI / Polytechnic
Degree college
2
Miscellaneous Educational Facilities
MBBS
Engineering
Other professional / technical institutions
Schools for handicap people
(one for city level)
University campus
3
Medical facilities
Dispensary / diagnostic center
Nursing home / maternity center / polyclinic
1 for 15000
Primary health center
1 for 20000
4
Social and cultural facilities
community building / library
1 for 15000
Other community building
Extension counter with ATM
(i) floor area for counter (ii) floor area for ATM
1 for 15000
5
Other services
Sub-post office
1 for 10000
Police station (with residence for employees)
1 for 15000
Police station (with residence for employees)
1 for 50000
Computerized Railway reservation counter
1 for 5000
Electricity services
(i) 11 KVA
1 for 15000
(ii) 33 KVA
1 for 25000
(iii) 66KVA
1 for 50000
Table 27:Public facilities and Services
11.7Eco Resorts
(i) After utilizing the maximum ground coverage, the rest of the plot area shall be necessarily kept as soft ground. Parking & other internal pathways / passage shall be developed necessarily / essentially as brick on edge or loose stone pavement.
(ii) The Maximum height of the building permissible shall be 7.5 mt. maximum upto two floors(ground and first). The roof of the first floor shall be necessarily pitched / sloping
(iii) Basement shall not be permissible
(iv) Where approach road to the site is not available as per norms and is approached by pedestrian pathway or ropeway, in such cases parking provision shall be made by the developer on the road head (on the motor-able road from where the pedestrian pathway or ropeway starts). In such cases, due to constraint of fire tender reaching the site, the developer will have to provide fire safety measures all by himself and such proposals shall be scrutinized and given NOC by fire department for their sufficiency. Such NOC shall be renewed by fire department every two years.
(v) In the premises of Eco Resort, the internal pathways shall be necessarily used as a walking trail & asper the necessity battery operated vehicle may be used.
(vi) The proposal of sewerage disposal shall necessarily be inspectedby Jal Nigam
(vii) In the open areas minimum of 125 trees per hectare shall be planted necessarily
(viii) 60% of the employment shall be given necessarily to the local people of the State& an affidavitin this regard shall be taken from the applicant. In case of violation of the said rule procedure or steps shall be taken to cancel the approval of map.
(ix) Other provisions, guidelines issued by MOEF for eco-tourism in and around protected areas on date 2ndJune,2011 mentioned below shall be necessarily complied:
a. As part of the State-level Ecotourism Strategy, the Stategovernment should levy a “Local Conservation Cess” as a percentage of turn-over, on all privately-run tourist facilities within 5km of the boundary of aProtected Area. The rate of cess should be determined by the State Government, and the monies thus collected should be earmarked to fund Protected Area management, conservation and local livelihood development, and not go as revenue to the State Exchequer
b. Tourist infrastructure must conform to environment-friendly, low-impact architecture; renewable including solar energy, waste recycling, rainwater harvesting, natural cross-ventilation, no use of asbestos, controlled sewage disposal, and merging with the surrounding landscape, Theabove provision shall be monitored by project sanctioning authority
11.8Service Apartments
Service apartments shall be self-contained apartments which shall have food facility (kitchen / pantry) within them & shall be used as a livable spaceor residence for a duration of short term. Other requirement:
a. Maximum of 20% of the permissible F.A.R of the hotel / offices, institutional or their campuses may be used for service apartments
b. Within the commercial land use category, minimum of 1000 sq. mt. plot area may be utilized for the service apartments as a standalone project. In the commercial use category prescribed Ground Coverage, F.A.R &Setback shall be permissible In such projects, Maximum of 20% of the total F.A.R may be used for office, conference facility, guest room and service shops
11.9 Industrial Units
As per the norms stipulated in Part-C of these Byelaws.
11.10Multiplex
(i) In a multiplex, the cinema hall, commercial activities and other recreation facilities may be providedin a single complex
(ii) In a multiplex, minimum two cinema auditoria is compulsory
(iii) The maximum seating capacity of a single cinema hall shall be 350 seats
(iv) The minimum seating capacity of a single cinema hall shall be 250 seats in plain and150 seats.in hill areas.
(v) Minimum area and width of plot- For multiplex the proposed site / plot area shall be minimum 2500 sq. mt.and width of plot shall be minimum 32.0 mt. in plain areas. In hill area the plot area shall be minimum 1500 sq. mt. and width of plot shall be minimum 24.0 mt.
(vi) Approach Road- For construction of the multiplex, apart from the existing road, provision of minimum 7.5m wide access lane shall be necessary on any other side of the plotafter the fixed setback has been provided. In addition to the front setback, provision of 7.5 mt. service lane is to be provided towards the main road for efficient circulation space of the vehicles.
(vii) In the multiplex plot, minimum 25% of prescribed setback area shall be necessarily used for plantation
(viii) The planning, designing and fire prevention provisions shall be ensured according to the relevant provisions of Uttar Pradesh Cinematography Regulations, 1951 and National Building Code and IS 4878. Other necessary services and facilities in the multiplex shall be drinking water, sanitary facilities, canteen etc. General provision may be made according to the prescribed standards.
(ix) In case the multiplex project is proposed outside the controlled area, due to land upgradation / conversion, a fee shall be payable, according to the GO, which shall be deposited in the prescribed Government head office.
(x) For other activities / facilities to be provided in addition to the cinema hall within the multiplex, a permission andno objection certificate shall be necessary as per the act / regulations / regulations of the Center or State. Only after the provision of the permission and no objection certificate shall the sanction of layout be considered.
(xi) To ensure the time bound construction of the multiplex, at the time of sanctioning of layout, the applicant shall be liable to pay the concerned agency a bank guarantee of 20% of the calculated price of existing residential sector rate. In case of non-availability of rates with the authority, the bank guarantee shall be liable of total area of the proposedplot according to theexisting general residential circle rate as prescribed by the district magistrate. In the case of mixed-use project, the bank guarantee shall be payable on total covered area of the multiplex.
(viii) Essential Provision for EWS Houses
a. It is mandatory to provide for EWS dwelling units in group housing / layout projects. Such units will be of a Maximum of 4 storeys (Ground and three additional floors) to be constructed as separate building blocks
b. It will be mandatory to construct 15%of the total Housing stock proposed in the project for EWS Housing. The procedure for approval of such units and their price will be determined
by the government from time to time. The required EWS units will either be constructed in the project area or as a separate project within a maximum radius of 5 kms. from the basic project site. The suitability of such sites will be determined by the sanctioning authority.
However in case of smaller housing project (of plot area less than 5000 sq. mt.) the above provision is not mandatory. As an alternative and in lieu of constructing EWS housing stock the Developer of such project will have the choice of depositing the “Shelter Fund” with the sanctioning authorities. The fund will subsequently be used for land pooling, land development and building construction and related works for EWS housing stock. The Shelter fund amount to be calculated as per Government directions from time to time.
c. The ground coverage of EWS housing units will be included in the calculation of total ground coverage and FAR of the project.
d. Parking for EWS units will be calculated on the basis of ECS per 4 EWS units.
e. Parking in the form of open parking is mandatory.
f. Completion certificate from Empanelled structural Engineer of such units certifying that such buildings are designed and constructed in accordance with the provision of Part IV (structural design)of NBC
(ix) Document to be submitted along with building plan of group housing / layout projects
a. ITR of firm / company / trust and memorandum of trickle of firm / company, registered habitat developer’s registration and regulations / regulations regarding related of formation functioning resident welfare of association
b. Group housing projects and residential layout where building construction is proposed as per typical building plan certificate from empanelled structural engineer / authorized technical institute / universities certifying that such building comply with the provision of part iv (structural design) of NBC
c. Drawing and necessary document in the required formats related to services via electricity, water supply, sewage disposal and the like to be duly signed by the architect and the drawing should comply with BIS wide
d. NOC from fire safety officer / fire department on the relevant maps / drawing related to fire safety provision
e. Registered affidavit of applicant / developer station that occupancy of that will be permitted after obtaining completion from the functioning authority
f. Original sale deed along with latest chatauni ofthe land (project area) prior to secluding of the project 25% of the w.r.t. of development of proposed infrastructure as bank guarantee in favor of sanctioning authority an agreement or hypothecation part properly equivalent is the above amount in favor of the sanctioning authority
c. All tourism facilities located within 5 km of a Protected Area must be reviewed regularly by the Local Advisory Committee vis-a-vis environmental clearance,area of coverage, ownership, type of construction, number of employees, etc. for suggesting mitigation / retrofitting measures if needed
d. All tourism facilities located within five kms.ofa Protected Area must adhere to noise pollution regulations under “The Noise Pollution (Regulation and Control) Regulations“. 2000, and “The Noise Pollution Control Regulation and Control) (Amendment)Regulations.” 2010 issued by the Ministry of Environment and Forests.
e. All tourist facilities old and new must aim to generate at least 50% of their total energy and fuel requirements from alternate energy sources that may include wind, solar and biogas.
f. There shall be a complete ban on burning ordisposing non-biodegradable waste within theProtected Area or in surrounding eco-sensitive zone or buffer area.
g. The use of wood as fuel shall be prohibited except for campfires for which wood must be procured from State Forest Department / Forest Development Corporation depots.
h. In order to allow free passage to wildlife, development should be sensitive to the conservation of flora and fauna, and the corridor value of the area.
Chapter 11Other Provisions (provisions Specifically Related to Different Buildings / Projects / Areas)
11.1 Core Built Up Area
(i) Built up Zones / core built-up areas are normally defined in the Master Plans. In areas where such zones are not defined in the Master Plans or where Master Plans are not in force, core built up area / Zones in Development Area will be defined by the concerned Department Authorities and by Town and Country Planning Department outside the Development Area of the state.
(ii) Residential and Commercial activities or such activities which are permissible as per zoning regulations will be permitted and following activities will not be permitted.
a. Motel and resorts, multiplex and malls, multistory commercial complex (more than two floor).
b. Offices (except offices of maximum 200 sq. mt. floor area)
c. College, ITI / Poly technique, miscellaneous Technical Colleges, university complex.
d. Hospital, higher / specialized medical facilities.
e. Auditorium, Town Hall, vocational and technical institutions, cinema / theatre, coal Depot, filling and service station.
f. Industrial Units (except such Household units of maximum 30 sq. mt. area) less than 5 Kw capacity employing a maximum of 5 workers.
(iii) Norm for Development and Redevelopment / Reconstructions
a. Minimum Net Plot Area 30 sq. mt. (Residential)&10 sq. mt. (Commercial) Minimum Width 2.0 m (Commercial Plot) Width of Residential Plot as per definition of Housings (EWS,LIG.LMIG) and Plot GIVEN in definitions. In the towns of religious importance the minimum net plot area of guest house shall be 250 sq. mt. in hills and 400 sq. mt. in plains.
b. Front Boundary:
In case where the road is not a Master Plan road the front boundary of the plot will be determined from the center line of the road abutting the plot. The determination of such boundary will be as follows:
S. No.
Existing Road Width
Distance to be left from the centre of the existing road for determination of front boundary
Maximum Height of the buildings
1
Up to 3.0m
1.5m
6.5m
2
3.1 to 4.5 m
2.25m
6.5m
3
4.6 to 7.5m
3.75m
9.0m
4
7.6 to 9.0m
4.5m
9.0m
5
9.1 to12.0m
6.0m
12.0m
6
12.1 to 18.0m
9.0m
12.0m
Table 19: Determination of Front Boundary
In towns of religious importance, the approach road provisions for guest house shall be as follows:
Region
Min approach road existing width
Road widening to be left fully from the plot
Hills
4.5 mt.
Min 1.5 mt.
Plains
7.50 mt.
1.5mt.
Parking if not available within the plot, the same shall be provided within 500mt. from the site at public parking place and the same shall be ensured by the sanctioning authority.
Table 20: Approach road provisions for guest house
c. Norm for Reconstruction of Building in plots upto 200sq. mt.
S. No.
Building Norm
Norm as per Plot size
Upto 100 sq. mt.
(>100-200 sq. mt.)
1
Ground coverage
75%
70%
2
FAR
As per Permissible ground coverage and permissible maximum height
3
Minimum front setback*
1.20
1.80
4
Basement
not allowed
not allowed
Table 21: Norm for Reconstruction of Building in plots upto 200 sq. mt.
Note: *Existing setback will prevail in cases where the existing setback are greater than the above mentioned setbacks.
(iv) For Plots upto 200 sq. mt. Plot Area and abutting on a minimum of 9.0 m width road maximum 20% of the permissible Ground coverage can be used as basement in Commercial / Mixed Buildings. Such basement will be used only for storage.
The approach to such Basement will be in the form of internal staircase / ramp.
(v) For Corner Plot of upto 100 sq. mt. Area the provision of road side setback on sides and rear will not be mandatory. Such plots having an area of 101 sq. mt. to 200 sq. mt., a minimum of 1.0
mt. road side setback is required. In case where the existing setback is greater than the required setback the provision existing of setback will prevail.
(vi) For plots greater than 200 sq. mt. Area provision of ground coverage, FAR, minimum front setback and basement will be as per the respective provisions of the byelaws. Basement will not be permissible in Residential / mixed use Building and in Building abutting on roads less than 9.0 m width.
(vii) Sub division of Plots will be as per sub division bylaws and with a minimum Area of such sub divided plots shall be 40 sq. mt.
(viii) For non-residential use building on roads less than 9.0 mt. or plot size less than 200 sq. mt. public parking shall be developed by the sanctioning authority. For this purpose parking fee shall be charged at the time of sanctioning plan which shall be computed based upon the circle rate of the required parking area in the project. This fee shall be deposited in an ESCROW account for parking fund and shall be used exclusively for developing public parking spaces in or near core areas.
(ix) A maximum of 40% width of front setback (front setbacks to be determined after having the required Right of way of public roads) can be used for sunshade, projection, Balcony etc.
(x) Plinth Level: minimum 0.45 mts. from ground level.
(xi) Horizontal and vertical expansion will be permitted subject to the structural safety of such building. The expansion will be permitted in cases where the required right of way and setback condition are adhered to. Such expansion will be permitted within the FAR limits.
11.2 Single Residential
(i) Normally, in open / undeveloped areas, individual single residential units will bepermitted only if the sub divided plot is part of a larger approved layout plot.
(ii) However, in special circumstances, after due permission from the sanctioning authority, such stand-alone plots situated within the urban local body limits, which have not been sub divided from a larger open area and where the width of the road is less than the required width, permission for construction can be granted after leaving required land for right of way to ensure minimum road width and required setback.