Basement means a construction having a minimum 50 percent part of its height below the lowest ground level of the site. Depending upon the special topography of the site, it may be determined by the authority as per the definition in N.B.C-2016. The basement shall be used for parking, storage and utility
(1) Permissibility of Basement shall be as:
| One Basement | More than One Basement | |
| Hills | Single basement allowed in plots having minimum 18.0 mt. frontage as well as width AND minimum plot area 2000sq. mt. | not permitted |
| Plains | Upto plot size 750 sq. mt., 20% of the plot may be used for single basement meant for storage purpose and shall be accessible internally from building above | maximum three basements permitted in plots having 24 mt. frontage as well as width AND minimum plot area 4000sq. mt. |
| For plot size more than 750 sq. mt. single basement may be used for parking purposes |
Table 10: Permissibility of Basement
(2) The basement may be put to following uses:
a. Parking
b. Storage of household or other goods of ordinarily non-combustible material;
c. Strong rooms, bank cellars, etc.;
d. Air-conditioning equipment and other machines used for services and utilities of the building.
e. Only in case of High Rise Buildings, up to 10% of basement may be utilized for utilities and non-habitation purpose like A/C Plant room, Generator room, Sewerage Treatment
Plant (STP), Electrical installations, Laundry, etc. This is allowed only after fulfilling the required parking spaces.
Car wash, security room, ticketing booth, loading / unloading activities, lift / escalator lobbies.
(3) The use of basement shall be specified in the building plans at the time of submission.
(4) The maximum expanse (ground coverage) of basement shall be 50% of the total plot area and shall be within the limits after leaving the required setback.
(5) Plots bearing dead setbacks as per norms shall be eligible to construct single basement provided minimum setbacks as stipulated below are provisioned instead of dead setback for the basement as well as for the superstructure. In other plots where setbacks are defined, the below tabulated or the defined setbacks, (whichever is more) shall be applicable.
| S. No. | Height of the Building | Front Setback | Setback to be left on other sides |
|---|---|---|---|
| 1 | upto 9.0 mt. | 3.6 mt | 2.0 mt. |
| 2 | upto 12.0 mt. | 4.5 mt | 3.0 mt. |
| 3 | upto 15.0 mt. | 4.5 mt | 4.0 mt. |
| 4 | more than 15.0 mt. | 4.5 mt | 6.0 mt. |
Table 11:Setbacks to be left based on height of the building for construction of basement
(6) The basement shall be admissible below the landscaped open areas with this restriction that the ceiling slab of basement shall not be more than ground floor (flushed with ground level and property landscaped as open / green space) and recharge borewells are provided adequately for ground water recharging. In case of podium construction, the green areas may be proposed over the podium with a condition that recharge borewells are provided adequately for ground water recharging.
(7) Provision of open ramp for access to the basement in setback area shall be permitted after leaving the requisite space for fire tender movement around the building [ie. 3.60 mt. and 6.0 mt respectively from low rise and high rise construction].
(8) The maximum travel distance from any point in basement shall be according the National Building Code.
(9) For basement, the Empanelled structural engineer shall furnish structural plans alongwith an affidavit regarding the suitability of the basement w.r.t bearing capacity of the soil, liquefaction and water table and the effect of excavation of basement on stability of neighboring buildings.
(10) The basement shall have the following provisions:
Light and ventilation of basement
a. An open area of a minimum width of 1.8 mt. shall be provided across the full length and / or width of the basement storey. This area shall be within the limits of the site and shall be paved with impervious material above a concrete bed. It shall be completely unobstructed except that in this area steps may be allowed for access to it, if considered necessary.
b. Basement storeys shall be lighted and ventilated by means of windows of the minimum area within 1 / 10th to 1 / 25th of the total floor area, at least half of which must open subject to the condition that the deficit of light and ventilation shall be made up by providing artificial lighting and mechanical ventilation as per provision of National Building Code of India.
c. In the second basement and basement below the lower ground floor where it is to be used for parking / services, the provisions contained in National Building Code and Fire Safety Byelaws as applicable shall be followed.
d. Any deficiency may be met by providing adequate mechanical ventilation in the form of blowers, exhaust fans, air-conditioning systems, etc.
(ii) Damp proofing of Basement
The walls of the basement storey shall be properly damp proofed and if in contact with the soil, they must be effectively secured against dampness from the soil with the approved vertical and horizontal damp proof course.
(iii) Height of the Basement
a. The minimum clear height of the basement shall be 2.4 mt. and maximum clear height of the basement shall be up to 4.75 mt.from floor to the underside of the roof slab or ceiling subject to structural stability to be certified by the Structural Engineer.
b. The minimum height of the roof of basement shall be 0.9 mt. and maximum 1.20mt. above the average surrounding ground level for plots upto 1000 sq. mt.
c. For plots above 1000 sq. mt., the roof of basement shall be either flushed with ground or the maximum height shall be 1.20 mt. above the average surrounding ground level.
(iv) Drainage of Basement
a. Open area adjoining a basement storey, if any, shall be effectively drained to the satisfaction of the Competent Authority.
b. The responsibility of draining a basement storey and for protecting it from rain shall be that of the owner.
c. The access to the basement shall be separate from the main and alternative staircase providing access and exit from higher floors.
d. Where the staircase is continuous in the case of buildings served by more than one staircase, the same shall be of enclosed type serving as a fire separation from the basement floor and higher floors.
e. The “Exit” requirements in basements shall comply with the provisions ofPart 4 ‘Fire and Life Safety’ of National Building Code of India.