(1) Every person who intends to occupy such a building or part thereof shall apply for the occupancy certificate in FORM-VI which shall be accompanied by completion notices in relevant Form -VI(A) or VI(B) duly signed by the Architect and / or the supervising Engineer and along with following documents:
(i) Detail of sanctionable violations from the approved building plans, if any in the building, jointly signed by the owner, Architect and Engineer.
(ii) Complete Completion drawings or as-built drawings along with completion certificate from Architect
(iii) Photographs of front, side, rear setbacks, front and rear elevation of the building shall be submitted along with photographs of essential areas like cut outs and shafts from the roof top. An un-editable compact disc / DVD / any other electronic media containing all photographs shall also be submitted.
(iv) Completion notice from Architect for green building and ECBC compliance, wherever required
(2) After receipt of the application for an occupancy certificate for low risk buildings, Authority shall consider the same as per planning and building standard regulations without reference to any Public Agency.
(3) After receipt of the application for an occupancy certificate for any building other than low risk building, Authority shall consider and refer the same to such Public Agencies having regard to the nature of building for obtaining a No-Objection Certificate from such Public Agency such as fire safety, pollution control board .etc.
(4) Common Inspection Programme of the Building:
(i) After receipt of application for issue of occupancy certificate, the Authority shall notify a date and time for conduct of common inspection programme of the building for which occupancy certificate has been requested.
(ii) Every Public Agency, which needs to conduct field visit and inspection for giving their noobjection certificate, shall conduct the same as part of the notified common inspection
programme, the date of which shall be a date, which is three days after but not later than seven days, of receipt of the application.
(iii) Time limits
a. The Public Agencies shall normally issue No-Objection Certificates within three working days of conduct of common inspection programme
b. If any Public Agency has any objection or requires further information, then an inspection report, specifying points of objection thereof shall be submitted within three working days of conduct of inspection to the Authority with a copy to the applicant for compliance.
c. No-Objection Certificate shall be issued within three working days from the date when compliance to the objection has been made or additional information as required has been submitted by the applicant through the Authority to the satisfaction of such Public Agency.
(iv) Deemed Approval: If No-objection certificate from any public agency is not received as per the time limit fixed then it shall be deemed to have been issued by the concerned Public Agency.
(5) Condition for Grant or refusal of occupancy certificate:
(i) The occupancy certificate shall be granted by Authority for low risk buildings within ten days from the date of receipt of the application in Form ‘VII’ duly filled in, if the building has been constructed and completed as per the provisions of Planning and Building Standard Regulations of the Authority.
(ii) The occupancy certificate shall be granted by the authority for the building other than low risk building within thirty days from the date of receipt of duly filled in the application Form ‘VII’, if same, is as per the Planning and Building standards regulation of the Authority and is in accordance with the norms and standards fixed in the relevant Acts, regulations, regulations or instructions issued by any Public Agency and the applicant has complied to observations and provided information and documents as required by Public Agencies and Authority.
(iii) Authority may refuse to grant occupancy certificate at any time, if application form has not been duly filled or the same is not as per Planning and Building Standard Regulation of the Authority or any Public Agency has refused to give No-Objection Certificate.
(iv) Order for grant of Occupancy Certificate by Authority shall be in Form ‘VII’ on payment of fee which shall be decided by Authority
(6) The ‘Occupancy Certificate’ shall be issued on the basis of parameter mentioned below:
(i) Minimum 50% of total permissible ground coverage, excluding ancillary zone, shall be essential for issue of occupation certificate (except for industrial buildings) for the first time and the building shall be complete in itself in all respects, for occupancy:
(ii) Provided, in case of residential plotted, minimum 50% of the total permissible ground coverage shall be essential to be constructed to obtain occupation certificate, where one habitable room, a kitchen and a toilet forming a part of submitted building is completed.
(iii) The debris and rubbish consequent upon the construction has been cleared from the site and its surroundings.
(7) No owner / applicant shall occupy or allow any other person to occupy new building or part of a new building or any portion whatsoever, until such building or part thereof has been certified by the Competent Authority or by any officer authorized by him in this behalf as having been completed in accordance with the permission granted and an ‘Occupancy Certificate’ has been issued in Form -VII. However, Competent Authority may also seek composition charges of compoundable violations which are compoundable before issuance of Form -VII.
(8) Connection to the municipal sewer / water mains
a) Temporary connection for water, electricity or sewer, permitted for the purpose of facilitating the construction, shall not be allowed to continue in the premises without obtaining completion/occupancy certificate.
b) No connection to the Municipal water mains or to the Municipal sewer line with a building shall be made without the prior permission of the Authority and without obtaining occupancy /completion certificate.
c) In case the use is changed or unauthorized construction is made, the Authority is authorized to discontinue such services or cause discontinuance of such services.
(9) If the owner or Architect or Engineer or Consultant as the case may be, submits a wrong report while making application under this byelaws or if any additional construction or violation is reported to exist at site or has concealed any fact or misrepresented regarding completion of construction of building along with its eligibility for seeking occupation certificate or before the completion of such report, he shall be jointly and severally held responsible for such omission and complaint against the Architect for suspension of his registration and the owner shall be liable to pay for the penalty as may be decided by the competent authority after giving an opportunity of hearing. Further, if it is emerged that the information is concealed by Technical Person, necessary penal proceedings will be initiated along with debarring Technical Person from practicing in the State of Uttarakhand