(1) Any person intending to erect or re-erect building shall apply on FormSC-I& SC-II along with documents stated in Clause 2.1 to the Competent Authority for the intimation of approval of building plans of Low Risk Category Buildings (as defined in Chapter-4) under self-certification by the Empanelled Architect alongwith scrutiny and other types of fee as applicable, giving fifteen day notice to the Competent Authority for approval of building plans intimating the date of start of construction. The construction can be started after fifteen days, in case any objection is not conveyed to the applicant.
(2) Certificate of conformity to regulation and structural safety for the relevant buildings (depending upon type and height) in the relevant Form SC-II.
(3) Competent Authority or any other person authorized by him reserves the right to check the building plans and construction at any stage and violations (except compoundable ones), if found shall have to be rectified by the owner / applicant. In case the owner / applicant fail to rectify violations, the Competent Authority may take necessary steps to remove the violations. Action shall also be taken against the
(4)
defaulting Architect by referring his case to the Council of Architecture of misconduct and debarring / blacklisting the Architect from doing practice in State Government Departments / Authorities. All rectifications shall be at the risk and cost of the owner and no plea of the owner shall be entertained for any default committed by the Architect engaged by him. In all such cases the procedure of self-certification shall stand aborted.
If a building is erected or re-erected or construction work is commenced in contravention to any of the building regulations, the Competent Authority or any other person authorized by him shall be competent to require the building to be altered or demolished, by a written notice delivered to the owner. Such notice shall also specify the period during which such alteration or demolition has to be completed and if the notice is not complied with, the Competent Authority or any other person authorized by him may demolish the said building at the expense of the owner.
(5) The decision of Competent Authority, in case of any dispute shall be final and binding on all concerned.
At any stage during construction, if an Architect notices that violations (except sanctionable ones) are taking place, he shall intimate to the concerned authority of such violations and stop further supervision He / She shall also intimate the owner about the violations and advise him to stop further construction Complete details along with photographs shall be submitted to the concerned authority. The Competent Authority shall immediately issue a notice to the owner on the basis of the Architect’s certificate to suspend further work and rectify violations. In such cases the owner shall be held responsible for further additions in violations. Such a situation shall automatically annul the process of self-certification and the owner may, after removal of violations, engage an Architect for preparing the revised drawings. In such cases completion shall be given only after scrutiny of revised drawings and inspection of site.
Sanctionable changes shall be allowed to be done, provided that at the completion stage all changes are incorporated by the Architect in the completion drawings to be submitted by the owner to the Competent Authority. While seeking occupancy certificate, the Architect shall give a certificate that all changes done are as per byelaws and policies of the Government from time to time.