General7.1
All electric and renewable energy equipment and systems shall comply with the mandatory requirements of §7.2.
Power transformers of the proper ratings and design must be selected to satisfy the minimum acceptable efficiency at 50% and full load rating. The permissible loss shall not exceed to values listed in Table 7 -1 for dry type transformers and Table 7 -2 for oil type transformers.
The BEE star rating for dry type transformer shall take precedence over this table once notified by BEE under BEE Standards and Labelling Program. For oil type transformer BEE star rated transformer (BEE Standards and Labelling Program) shall be used in all compliant buildings. Power transformers to meet compliance shall have:
(a) minimum 3 stars rating in ECBC Buildings
(b) minimum 4 stars rating in ECBC+ Buildings
(c) 5 stars rating in SuperECBC Building
| Rating kVA | Max. Losses at 50% loading W* | Max. Losses at 100% loading W* | Max. Losses at 50% loading W* | Max. Losses at 100% loading W* |
| Up to 22 kV class | 33 kV class | |||
| 100 | 940 | 2400 | 1120 | 2400 |
| 160 | 1290 | 3300 | 1420 | 3300 |
| 200 | 1500 | 3800 | 1750 | 4000 |
| 250 | 1700 | 4320 | 1970 | 4600 |
| 315 | 2000 | 5040 | 2400 | 5400 |
| 400 | 2380 | 6040 | 2900 | 6800 |
| 500 | 2800 | 7250 | 3300 | 7800 |
| 630 | 3340 | 8820 | 3950 | 9200 |
| 800 | 3880 | 10240 | 4650 | 11400 |
| 1000 | 4500 | 12000 | 5300 | 12800 |
| 1250 | 5190 | 13870 | 6250 | 14500 |
ELECTRICAL AND RENEWABLE ENERGY
ELECTRICAL AND RENEWABLE ENERGY
| 1600 | 6320 | 16800 | 7500 | 18000 |
|---|---|---|---|---|
| 2000 | 7500 | 20000 | 8880 | 21400 |
| 2500 | 9250 | 24750 | 10750 | 26500 |
*The values as per Indian Standard/BEE Standard & Labeling notification for dry type transformer corresponding to values in this table will supersede as and when the Indian standards/ BEE Standard & Labeling notification are published.
| Rating (kVA) | Impedance(%) | Max. Total Loss (W) for transformers up to 11 kV class | |||||
| ECBC Building | ECBC+ Building | SuperECBC | |||||
| 50 %Load | 100%Load | 50 %Load | 100%Load | 50 %Load | Build1in0g0%Load | ||
| 16 | 4.5 | 150 | 480 | 135 | 440 | 120 | 400 |
| 25 | 4.5 | 210 | 695 | 190 | 635 | 175 | 595 |
| 63 | 4.5 | 380 | 1250 | 340 | 1140 | 300 | 1050 |
| 100 | 4.5 | 520 | 1800 | 475 | 1650 | 435 | 1500 |
| 160 | 4.5 | 770 | 2200 | 670 | 1950 | 570 | 1700 |
| 200 | 4.5 | 890 | 2700 | 780 | 2300 | 670 | 2100 |
| 250 | 4.5 | 1050 | 3150 | 980 | 2930 | 920 | 2700 |
| 315 | 4.5 | 1100 | 3275 | 1025 | 3100 | 955 | 2750 |
| 400 | 4.5 | 1300 | 3875 | 1225 | 3450 | 1150 | 3330 |
| 500 | 4.5 | 1600 | 4750 | 1510 | 4300 | 1430 | 4100 |
| 630 | 4.5 | 2000 | 5855 | 1860 | 5300 | 1745 | 4850 |
| 1000 | 5 | 3000 | 9000 | 2790 | 7700 | 2620 | 7000 |
| 1250 | 5 | 3600 | 10750 | 3300 | 9200 | 3220 | 8400 |
| 1600 | 6.25 | 4500 | 13500 | 4200 | 11800 | 3970 | 11300 |
| 2000 | 6.25 | 5400 | 17000 | 5050 | 15000 | 4790 | 14100 |
Total loss values given in above table are applicable for thermal classes E, B and F and have component of load loss at reference temperature according to Clause 17 of IS 1180 i.e., average winding temperature rise as given in Column 2 of Table 8.2 plus 3 0 ° C . An increase of 7% on total for thermal class H is allowed.
Permissible total loss values shall not exceed:
(a) 5% of the maximum total loss values mentioned in IS 1180 for oil type transform ers in voltage class above 11 kV but not more than 22 kV
(b) 7.5% of the maximum total loss values mentioned in above IS 1180 for oil type transformers in voltage class above 22 kV and up to and including 33 kV
All measurement of losses shall be carried out by using calibrated digital meters of class 0.5 or better accuracy and certified by the manufacturer. All transformers of capacity of 500 kVA and above would be equipped with additional metering class current transformers (CTs) and potential transformers (PTs) additional to requirements of Utilities so that periodic loss monitoring study may be carried out.
Voltage drop for feeders shall not exceed 2% at design load. Voltage drop for branch circuit shall not exceed 3% at design load.
Motors shall comply with the following:
(a) Three phase induction motors shall conform to Indian Standard (IS) 12615 and shall fulfil the following efficiency requirements:
i. ECBC Buildings shall have motors of IE 2 (high efficiency) class or a higher class
ii. ECBC+ Buildings shall have IE 3 (premium efficiency) class motors or higher class
iii. Super ECBC Buildings shall have IE 4 (super premium efficiency) class motors
(b) Motors of horsepower differing from those listed in the table shall have efficiency greater than that of the next listed kW motor.
(c) Motor horsepower ratings shall not exceed 20% of the calculated maximum load being served.
(d) Motor nameplates shall list the nominal full-load motor efficiencies and the full- load power factor.
ELECTRICAL AND RENEWABLE ENERGY
ELECTRICAL AND RENEWABLE ENERGY
BEE star rated DG sets shall be used in all compliant buildings. DG sets in buildings greater than 20,000 m2 BUA shall have:
(a) minimum 3 stars rating in ECBC Buildings
(b) minimum 4 stars rating in ECBC+ Buildings
(c) 5 stars rating in Super ECBC Buildings
Provided the building does not use DG sets for captive power generation (no more than 15% of power requirement is being met by the use of DG sets), 3 star rated DG sets may be used for ECBC + and Super ECBC Buildings
At Building mains, installed meters must be capable of monitoring energy use (kWh), Energy Demand (kW) and total Power Factor on an hourly basis. For sub -meters installed at building services, the following metering requirements must be complied with:
(a) Services exceeding 1,000 kVA shall have permanently installed electrical metering to record demand (kVA), energy (kWh), and total power factor on hourly basis. The metering shall also display current (in each phase and the neutral), voltage (between phases and between each phase and neutral), and total harmonic distortion (THD) as a percentage of total current.
(b) Services not exceeding 1,000 kVA but over 65 kVA shall have permanently installed electric metering to record demand (kW), energy (kWh), and total power factor (or kVARh) on hourly basis.
(c) Services not exceeding 65 kVA shall have p ermanently installed electrical metering to record energy (kWh) on hourly basis.
Sub Metering requirement for different services are outlined in Table 7 -3
| Building Contract Demand | ||
| 120 kVA to 250 kVA | Greater than 250 kVA | |
| HVAC system and components | Required | Required |
| Interior and Exterior Lighting | Not required | Required |
| Domestic hotwater | Notrequired | Required |
| Plugloads | Notrequired | Required |
| Renewable power source | Required | Required |
In addition to requirements stated above, for building types identified in Table 7 -4, respective services must be sub-metered.
| Mandatory requirement of sub- metering of services for specific building types | |
| Shopping Complex | Façade lighting |
| Shopping Complex | Elevator, escalators, moving walks |
| Business | Data centers |
| Hospitality | Commercial kitchens |
For tenant-based building, tenants must be provided with tap-off points to install electrical sub-meters.
All 3 phase shall maintain their power factor at the point of connection as follows:
(a) 0.97 for ECBC Building
(b) 0.98 for ECBC+ Building
(c) 0.99 for Super ECBC Building
The power cabling shall be sized so that the distribution losses do not exceed
(a) 3% of the total power usage in ECBC Buildings
(b) 2% of the total power usage in ECBC+ Buildings
(c) 1% of total power usage in Super ECBC Buildings
Record of design calculation for the losses shall be maintained. Load calculation shall be calculated up to the panel level.
In all buildings, UPS shall meet or exceed the energy efficiency requirements listed in Table 7-5. Any Standards and Labelling program by BEE shall take precedence over requirements listed in this section.
| UPS Size | Energy Efficiency Requirements at 100% Load |
|---|---|
| kVA < 20 | 90.2% |
| 20 ≤ kV! ≤ 100 | 91.9% |
| kVA > 100 | 93.8% |
ELECTRICAL AND RENEWABLE ENERGY
ELECTRICAL AND RENEWABLE ENERGY
All buildings shall have provisions for installation of renewable energy systems in the future on rooftops or the site.
| 2500 | 6.25 | 6500 | 20000 | 6150 | 18500 | 5900 | 17500 |
(a) A dedicated REGZ equivalent to at least 25 % of roof area or area required for generation of energy equivalent to 1% of total peak demand or connected load of the building, whichever is less, shall be provided in all buildings.
(b) The REGZ shall be free of any obstructions within its boundaries and from shadows cast by objects adjacent to the zone.
(c) ECBC+ and Super ECBC building shall fulfil the additional requirements listed in Table 7-6 and Table 7-7 respectively.
| Building Type | Minimum Capacity to be installed in REGZ |
|---|---|
| All building types except below | Minimum 2% of total Contract Demand |
| Star Hotel > 20,000 m² AGA Resort > 12,500 m<sup>2</sup> AGA University > 20,000 m² AGA Business >20,000 m² AGA | Minimum 3% of total Contract Demand |
| Building Type | Minimum Capacity to be installed in REGZ |
|---|---|
| All building types except below | Minimum 4% of total Contract Demand |
| Star Hotel > 20,000 m² AGA Resort > 12,500 m<sup>2</sup> AGA University > 20,000 m² AGA Business >20,000 m² AGA | Minimum 6% of total Contract Demand |
Minimum rating shall be displayed on the main electrical service panel. Space shall be reserved for the installation of a double pole circuit breaker for a future renewable electric installation.
The following shall be indicated in design and construction documents:
(a) Location for inverters and metering equipment,
(b) Pathway for routing of conduit from the REGZ to the point of inter connection with the electrical service,
(c) Routing of plumbing from the REGZ to the water-heating system and,
(d) Structural design loads for roof dead and live load.
ELECTRICAL AND RENEWABLE ENERGY
Certain terms, abbreviations, and acronyms are defined in this section for the purposes of this code. These definitions are applicable to all sections of this code. Terms that are not defined shall have their ordinarily accepted meanings within the context in which they are used.
Above grade area (AGA): AGA is the cumulative floor area of all the floor levels of a building that are above the ground level. Ground level shall be as defined in building site plan. A floor level is above grade if one-third of the total external surface area of only the said floor level is above the ground level.
Accredited independent laboratory: testing laboratory not affiliated with producer or consumer of goods or products tested at the laboratory and accredited by national or international organizations for technical competence.
Addition: an extension or increase in floor area or height of a building outside of the existing building envelope.
Air conditioning and condensing units serving computer rooms: air conditioning equipment that provides cooling by maintaining space temperature and humidity within a narrow range. Major application is in data centers where dissipating heat generated by equipment takes precedence over comfort cooling for occupants.
Alteration: any change, rearrangement, replacement, or addition to a building or its systems and equipment; any modification in construction or building equipment.
Area weighted average (AWA) method: AWA method is based on the concept of weighted arithmetic mean where instead of each data point contributing equally to the final mean; each data point contributes more “weight” than others based on the size of the area the said data point is applicable to. To calculate the area weighted average mean, a summation of each data point multiplied with its respective area is divided with the total area.
Astronomical time switch: an automatic time switch that makes an adjustment for the length of the day as it varies over the year.
Authority having jurisdiction: the agency or agent responsible for enforcing this code.
Balancing, air system: adjusting airflow rates through air distribution system devices, such as fans and diffusers, by manually adjusting the position of dampers, splitters vanes, extractors, etc., or by using automatic control devices, such as constant air volume or variable air volume boxes.
Balancing, Hydronic system: adjusting water flow rates through hydronic distribution system devices, such as pumps and coils, by manually adjusting the position valves, or by using automatic control devices, such as automatic flow control valves.
Ballast: a device used in conjunction with an electric-discharge lamp to cause the lamp to start and operate under proper circuit conditions of voltage, current, waveform, electrode heat, etc.
Boiler: a self-contained low-pressure appliance for supplying steam or hot water.
Building or building complex or complex: a structure wholly or partially enclosed within exterior walls, or within exterior and party walls, and a roof, affording shelter to persons, animals, or property. Building complex means a building or group of buildings constructed in a contiguous area for business, commercial, institutional, healthcare, hospita lity purposes or assembly buildings under the single ownership of individuals or group of individuals or under the name of a co-operative group society or on lease and sold as shops or office space or space for other commercial purposes, having a connected load of 100 kW or contract demand of 120 kVA and above.
Building, base: includes building structure, building envelope, common areas, circulation areas, parking, basements, services area, plant room and its supporting areas and, open project site area.
Building, core and shell: buildings where the developer or owner will only provide the base building and its services.
Building, existing: a building or portion thereof that was previously occupied or approved for occupancy by the authority having jurisdiction.
Building envelope: the exterior plus the semi-exterior portions of a building. For the purposes of determining building envelope requirements, the classifications are defined as follows:
(a) Building envelope, exterior: the elements of a building that separate conditioned spaces from the exterior
(b) Building envelope, semi-exterior: the elements of a building that separate conditioned space from unconditioned space or that enclose semi-heated spaces through which thermal energy may be transferred to or from the exterior, or to or from unconditioned spaces, or to or from conditioned spaces
Building grounds lighting: lighting provided through a building’s electrical service for parking lot, site, roadway, pedestrian pathway, loading dock, and security applications.
Building material: any element of the building envelope through which heat flows and that heat is included in the component U-factor calculations other than air films and insulation.
Built up area (BUA): sum of the covered areas of all floors of a building, other than the roof, and areas covered by external walls and parapet on these floors.
24-hour Business Building: Business building operated and occupied for more than 12 hours on each weekday. Intensity of occupancy may vary.
Cardinal direction: cardinal directions or cardinal points are the four main directional points of a compass: north, south, east, and west.
Centralised control: single hardware/ software for observing and controlling operations of a group of equipment and devices with similar or different functions.
Circuit breaker: a safety device that automatically stops flow of current in electrical circuits. It protects the circuit from current surge.
Class of construction: classification that determines the construction materials for the building envelope, roof, wall, floor, slab -on-grade floor, opaque door, vertical fenestration, skylight.
Coefficient of Performance (COP) – cooling: the ratio of the rate of heat removal to the rate of energy input, in consistent units, for a compl ete refrigerating system or some specific portion of that system under designated operating conditions.
Coefficient of Performance (COP) – heating: the ratio of the rate of heat delivered to the rate of energy input, in consistent units, for a complete hea t pump system, including the compressor and, if applicable, auxiliary heat, under designated operating conditions.
Common area: areas within a building that are available for use by all tenants in a building (i.e. lobbies, corridors, restrooms, etc.).
Commercial building: a building or a part of building or building complex which are used or intended to be used for commercial purposes and classified as per the time of the day the building is operational and sub classified, as per the functional requirements of its design, construction, and use as per following details:
(a) Group I – 24 hours building covering Type A Hospitality, Type B Health Care and Type C Assembly, Type D Business and,
(b) Group II – Regular building covering Type D Business, Type E Educational and Type F Shopping Complexes.
Compliance documents: the forms specified in ECBC Rules and Regulations to record and check compliance with these rules. These include but are not limited to EPI Ratio Compliance Report, Building Envelope Compliance Form, Mechanical Systems Compliance Form and Permit Checklist, Lighting System Compliance Form and Permit Checklist and certificates from Certified Energy Auditor for existing or proposed buildings.
Connected load: the sum of the rated wattage of all equipment, appliances and devices to be installed in the building or part of building or building complexes, in terms of kilowatt (kW) that will be allocated to all applicants for electric power consumption in respect of the proposed building or building complexes on their completion.
Contract demand: the maximum demand in kilo Volt Ampere (kVA) (within a consumer’s sanctioned load) agreed to be supplied by the electricity provider or utility in the agreement executed between the user and the utility or electricity provider.
Construction documents: drawings or documents, containing information pertaining to building construction processes and approvals, building materials and equipment specification, architectural details etc. required by the authority having jurisdiction.
Controls or control device: manually operated or automatic device or software to regulate the operation of building equipment.
Cool roof: roof with top layer of material that has high solar reflectance and high thermal emittance properties. Cool roof surfaces are characterized by light colors so that heat can be rejected back to the environment.
Cumulative design EPI: energy performance index for a building having two or more different functional uses and calculated based on the area weighted average (AWA) method.
Daylight area: the daylight illuminated floor area under horizontal fenestration (skylight) or adjacent to vertical fenestration (window), described as follows:
(a) Horizontal Fenestration: the area under a skylight, monitor, or saw -tooth configuration with an effective aperture greater than 0.001(0.1%). The daylight area is calculated as the horizontal dimension in each direction equa l to the top aperture
dimension in that direction plus either the floor-to-ceiling height (H) for skylights, or 1.5 H for monitors, or H or 2H for the saw -tooth configuration, or the distance to the nearest 1 meter or higher opaque partition, or one-half the distance to an adjacent skylight or vertical glazing, whichever is least, as shown in the plan and section figures.

(b) Vertical Fenestration: the floor area adjacent to side apertures (vertical fenestration in walls) with an effective aperture greater than 0.06 (6%). The daylight area extends into the space perpendicular to the side aperture a distance equal to daylight extension factor (DEF) multiplied by the head height of the side aperture or till higher opaque partition, whichever is less. In the direction parallel to the window, the daylight area extends a horizontal dimension equal to the width of the window plus either 1 meter on each side of the aperture, or the distance to an opaque partition, or one-half the distance to an adjacent skylight or window, whichever is least.

Daylight Extension Factor (DEF): factor to manually calculate the daylight area on floor plates. It is to be multiplied by the head height of windows. It is dependent on orientation and glazing VLT, shading devices adjacent to it and building location.
Daytime Business Building: Business building operated typically only during daytime on weekdays up to 12 hours each day.
Deadband: the range of values within which a sensed variable can vary without initiating a change in the controlled process.
Demand: maximum rate of electricity (kW) consumption recorded for a building or facility during a selected time frame.
Demand control ventilation (DCV): a ventilation system capability that provides automatic reduction of outdoor air intake below design rates when the actual occupancy of spaces served by the system is less than design occupancy.
Design capacity: output capacity of a mechanical or electrical system or equipment at design conditions.
Design conditions: specified indoor environmental conditions, such as temperature, humidity and light intensity, required to be produced and maintained by a system and under which the system must operate.
Demand factor: is the ratio of the sum of the maximum demand of a system (or part of a system) to the total connected load on the system (or part of the system) under consideration. Demand factor is always less than one.
Distribution system: network or system comprising controlling devices or equipment and distribution channels (cables, coils, ducts, pipes etc.) for delivery of electrical power or, cooled or heated water or air in buildings.
Door: all operable opening areas, that are not more than one half glass, in the building envelope, including swinging and roll-up doors, fire doors, and access hatches.
Door area: total area of the door measured using the rough opening and including the door slab and the frame.
Economizer, air: a duct and damper arrangement with automatic controls that allow a cooling system to supply outdoor air to reduce or eliminate the need for mechanical cooling during mild or cold weather.
Economizer, water: a system by which the supply air of a cooling system is cooled indirectly with water that is itself cooled by heat or mass transfer to the environment without the use of mechanical cooling.
ECBC Building: a building that complies with the mandatory requirements of §4 to §7 and also complies either with the prescriptive requirements stated under the ECBC Building categories of §4 to §7, or, with the whole building performance compliance method of §9.
ECBC+ Building: a building that complies with the mandatory requirements of §4 to §7 and also complies either with the prescriptive requirements stated under the ECBC+ Building categories of §4 to §7, or, with the whole building performance compliance method of §9. This is a voluntary level of compliance with ECBC.
Effective aperture: Visible Light Transmittance x window -to-wall Ratio.
(E A = V L T × W W R)

Efficacy: the lumens produced by a lamp plus ballast system divided by the total watts of input power (including the ballast), expressed in lumens per watt.
Efficiency: performance at a specified rating condition.
Efficiency, thermal: ratio of work output to heat input.
Efficiency, combustion: efficiency with which fuel is burned during the combustion process in equipment.
Emittance: the ratio of the radiant heat flux emitted by a specimen to that emitted by a blackbody at the same temperature and under the same conditions.
Energy: power derived from renewable or non-renewable resources to provide heating, cooling and light to a building or operate any building equipment and appliances. It has various forms such as thermal (heat), mechanical (work), electrical, and chemical that may be transformed from one into another. Customary unit of measurement is watts (W).
Energy Conservation Building Code (ECBC): The Energy Conservation Building Code as updated from time to time by the Bureau and displayed on its website (www.beeindia.gov.in).
Energy Efficiency Ratio (EER): the ratio of net cooling capacity in watt to total rate of electric input in watts under design operating conditions.
Energy recovery system: equipment to recover energy from building or space exhaust air and use it to treat (pre-heat or pre-cool) outdoor air taken inside the building or space by ventilation systems.
Envelope Performance Factor (EPF): value for the building envelope performance compliance option calculated using the procedures specified in 4.3.5 and 4.3.5.1.1. For the purposes of determining building envelope requirements the classifications are defined as follows:
a) Standard Building EPF: envelope performance factor calculated for the Standard Building using prescriptive requirements for walls, vertical fenestrations and roofs
b) Proposed Building EPF: the building envelope performance factor for the Proposed Building using proposed values for walls, vertical fenestrations and roofs
Energy Performance Index (EPI): of a building means its annual energy consumption in kilowatt-hours per square meter of the area of the building which shall be calculated in the existing or proposed building as per the formula below,