General7.1
All electric and renewable energy equipment and systems shall comply with the mandatory requirements of §7.2.
Power transformers of the proper ratings and design must be selected to satisfy the minimum acceptable efficiency at 50% and full load rating. The permissible loss shall not exceed to values listed in Table 7 -1 for dry type transformers and Table 7 -2 for oil type transformers.
The BEE star rating for dry type transformer shall take precedence over this table once notified by BEE under BEE Standards and Labelling Program. For oil type transformer BEE star rated transformer (BEE Standards and Labelling Program) shall be used in all compliant buildings. Power transformers to meet compliance shall have:
(a) minimum 3 stars rating in ECBC Buildings
(b) minimum 4 stars rating in ECBC+ Buildings
(c) 5 stars rating in SuperECBC Building
| Rating kVA | Max. Losses at 50% loading W* | Max. Losses at 100% loading W* | Max. Losses at 50% loading W* | Max. Losses at 100% loading W* |
| Up to 22 kV class | 33 kV class | |||
| 100 | 940 | 2400 | 1120 | 2400 |
| 160 | 1290 | 3300 | 1420 | 3300 |
| 200 | 1500 | 3800 | 1750 | 4000 |
| 250 | 1700 | 4320 | 1970 | 4600 |
| 315 | 2000 | 5040 | 2400 | 5400 |
| 400 | 2380 | 6040 | 2900 | 6800 |
| 500 | 2800 | 7250 | 3300 | 7800 |
| 630 | 3340 | 8820 | 3950 | 9200 |
| 800 | 3880 | 10240 | 4650 | 11400 |
| 1000 | 4500 | 12000 | 5300 | 12800 |
| 1250 | 5190 | 13870 | 6250 | 14500 |
ELECTRICAL AND RENEWABLE ENERGY
ELECTRICAL AND RENEWABLE ENERGY
| 1600 | 6320 | 16800 | 7500 | 18000 |
|---|---|---|---|---|
| 2000 | 7500 | 20000 | 8880 | 21400 |
| 2500 | 9250 | 24750 | 10750 | 26500 |
*The values as per Indian Standard/BEE Standard & Labeling notification for dry type transformer corresponding to values in this table will supersede as and when the Indian standards/ BEE Standard & Labeling notification are published.
| Rating (kVA) | Impedance(%) | Max. Total Loss (W) for transformers up to 11 kV class | |||||
| ECBC Building | ECBC+ Building | SuperECBC | |||||
| 50 %Load | 100%Load | 50 %Load | 100%Load | 50 %Load | Build1in0g0%Load | ||
| 16 | 4.5 | 150 | 480 | 135 | 440 | 120 | 400 |
| 25 | 4.5 | 210 | 695 | 190 | 635 | 175 | 595 |
| 63 | 4.5 | 380 | 1250 | 340 | 1140 | 300 | 1050 |
| 100 | 4.5 | 520 | 1800 | 475 | 1650 | 435 | 1500 |
| 160 | 4.5 | 770 | 2200 | 670 | 1950 | 570 | 1700 |
| 200 | 4.5 | 890 | 2700 | 780 | 2300 | 670 | 2100 |
| 250 | 4.5 | 1050 | 3150 | 980 | 2930 | 920 | 2700 |
| 315 | 4.5 | 1100 | 3275 | 1025 | 3100 | 955 | 2750 |
| 400 | 4.5 | 1300 | 3875 | 1225 | 3450 | 1150 | 3330 |
| 500 | 4.5 | 1600 | 4750 | 1510 | 4300 | 1430 | 4100 |
| 630 | 4.5 | 2000 | 5855 | 1860 | 5300 | 1745 | 4850 |
| 1000 | 5 | 3000 | 9000 | 2790 | 7700 | 2620 | 7000 |
| 1250 | 5 | 3600 | 10750 | 3300 | 9200 | 3220 | 8400 |
| 1600 | 6.25 | 4500 | 13500 | 4200 | 11800 | 3970 | 11300 |
| 2000 | 6.25 | 5400 | 17000 | 5050 | 15000 | 4790 | 14100 |
Total loss values given in above table are applicable for thermal classes E, B and F and have component of load loss at reference temperature according to Clause 17 of IS 1180 i.e., average winding temperature rise as given in Column 2 of Table 8.2 plus 3 0 ° C . An increase of 7% on total for thermal class H is allowed.
Permissible total loss values shall not exceed:
(a) 5% of the maximum total loss values mentioned in IS 1180 for oil type transform ers in voltage class above 11 kV but not more than 22 kV
(b) 7.5% of the maximum total loss values mentioned in above IS 1180 for oil type transformers in voltage class above 22 kV and up to and including 33 kV
All measurement of losses shall be carried out by using calibrated digital meters of class 0.5 or better accuracy and certified by the manufacturer. All transformers of capacity of 500 kVA and above would be equipped with additional metering class current transformers (CTs) and potential transformers (PTs) additional to requirements of Utilities so that periodic loss monitoring study may be carried out.
Voltage drop for feeders shall not exceed 2% at design load. Voltage drop for branch circuit shall not exceed 3% at design load.
Motors shall comply with the following:
(a) Three phase induction motors shall conform to Indian Standard (IS) 12615 and shall fulfil the following efficiency requirements:
i. ECBC Buildings shall have motors of IE 2 (high efficiency) class or a higher class
ii. ECBC+ Buildings shall have IE 3 (premium efficiency) class motors or higher class
iii. Super ECBC Buildings shall have IE 4 (super premium efficiency) class motors
(b) Motors of horsepower differing from those listed in the table shall have efficiency greater than that of the next listed kW motor.
(c) Motor horsepower ratings shall not exceed 20% of the calculated maximum load being served.
(d) Motor nameplates shall list the nominal full-load motor efficiencies and the full- load power factor.
ELECTRICAL AND RENEWABLE ENERGY
ELECTRICAL AND RENEWABLE ENERGY
BEE star rated DG sets shall be used in all compliant buildings. DG sets in buildings greater than 20,000 m2 BUA shall have:
(a) minimum 3 stars rating in ECBC Buildings
(b) minimum 4 stars rating in ECBC+ Buildings
(c) 5 stars rating in Super ECBC Buildings
Provided the building does not use DG sets for captive power generation (no more than 15% of power requirement is being met by the use of DG sets), 3 star rated DG sets may be used for ECBC + and Super ECBC Buildings
In all buildings, UPS shall meet or exceed the energy efficiency requirements listed in Table 7-5. Any Standards and Labelling program by BEE shall take precedence over requirements listed in this section.
| UPS Size | Energy Efficiency Requirements at 100% Load |
|---|---|
| kVA < 20 | 90.2% |
| 20 ≤ kV! ≤ 100 | 91.9% |
| kVA > 100 | 93.8% |
ELECTRICAL AND RENEWABLE ENERGY
ELECTRICAL AND RENEWABLE ENERGY
All buildings shall have provisions for installation of renewable energy systems in the future on rooftops or the site.
At Building mains, installed meters must be capable of monitoring energy use (kWh), Energy Demand (kW) and total Power Factor on an hourly basis. For sub -meters installed at building services, the following metering requirements must be complied with:
(a) Services exceeding 1,000 kVA shall have permanently installed electrical metering to record demand (kVA), energy (kWh), and total power factor on hourly basis. The metering shall also display current (in each phase and the neutral), voltage (between phases and between each phase and neutral), and total harmonic distortion (THD) as a percentage of total current.
(b) Services not exceeding 1,000 kVA but over 65 kVA shall have permanently installed electric metering to record demand (kW), energy (kWh), and total power factor (or kVARh) on hourly basis.
(c) Services not exceeding 65 kVA shall have p ermanently installed electrical metering to record energy (kWh) on hourly basis.
Sub Metering requirement for different services are outlined in Table 7 -3
| Building Contract Demand | ||
| 120 kVA to 250 kVA | Greater than 250 kVA | |
| HVAC system and components | Required | Required |
| Interior and Exterior Lighting | Not required | Required |
| Domestic hotwater | Notrequired | Required |
| Plugloads | Notrequired | Required |
| Renewable power source | Required | Required |
In addition to requirements stated above, for building types identified in Table 7 -4, respective services must be sub-metered.
| Mandatory requirement of sub- metering of services for specific building types | |
| Shopping Complex | Façade lighting |
| Shopping Complex | Elevator, escalators, moving walks |
| Business | Data centers |
| Hospitality | Commercial kitchens |
For tenant-based building, tenants must be provided with tap-off points to install electrical sub-meters.
All 3 phase shall maintain their power factor at the point of connection as follows:
(a) 0.97 for ECBC Building
(b) 0.98 for ECBC+ Building
(c) 0.99 for Super ECBC Building
The power cabling shall be sized so that the distribution losses do not exceed
(a) 3% of the total power usage in ECBC Buildings
(b) 2% of the total power usage in ECBC+ Buildings
(c) 1% of total power usage in Super ECBC Buildings
Record of design calculation for the losses shall be maintained. Load calculation shall be calculated up to the panel level.
| 2500 | 6.25 | 6500 | 20000 | 6150 | 18500 | 5900 | 17500 |
(a) A dedicated REGZ equivalent to at least 25 % of roof area or area required for generation of energy equivalent to 1% of total peak demand or connected load of the building, whichever is less, shall be provided in all buildings.
(b) The REGZ shall be free of any obstructions within its boundaries and from shadows cast by objects adjacent to the zone.
(c) ECBC+ and Super ECBC building shall fulfil the additional requirements listed in Table 7-6 and Table 7-7 respectively.
| Building Type | Minimum Capacity to be installed in REGZ |
|---|---|
| All building types except below | Minimum 2% of total Contract Demand |
| Star Hotel > 20,000 m² AGA Resort > 12,500 m<sup>2</sup> AGA University > 20,000 m² AGA Business >20,000 m² AGA | Minimum 3% of total Contract Demand |
| Building Type | Minimum Capacity to be installed in REGZ |
|---|---|
| All building types except below | Minimum 4% of total Contract Demand |
| Star Hotel > 20,000 m² AGA Resort > 12,500 m<sup>2</sup> AGA University > 20,000 m² AGA Business >20,000 m² AGA | Minimum 6% of total Contract Demand |
Minimum rating shall be displayed on the main electrical service panel. Space shall be reserved for the installation of a double pole circuit breaker for a future renewable electric installation.
The following shall be indicated in design and construction documents:
(a) Location for inverters and metering equipment,
(b) Pathway for routing of conduit from the REGZ to the point of inter connection with the electrical service,
(c) Routing of plumbing from the REGZ to the water-heating system and,
(d) Structural design loads for roof dead and live load.
ELECTRICAL AND RENEWABLE ENERGY
Certain terms, abbreviations, and acronyms are defined in this section for the purposes of this code. These definitions are applicable to all sections of this code. Terms that are not defined shall have their ordinarily accepted meanings within the context in which they are used.