5.1 The main functions of design team (see 4.1) constituted for the planning, designing and development, are as under:
a) Formalization of design brief in consultation with the owner.
b) Site investigation/survey.
c) Preparation of alternative concept designs.
d) Selection of a concept in consultation with and with the consent of owner.
e) Sizing the system.
f) Development of design, covering :
-
Integration of architecture, structure and services,
-
Synthesis of requirements of each discipline, and
-
Interaction with each other and with the owner.
g) Preparation of preliminary designs and drawings and obtaining owner’s approval.
h) Preparation of preliminary cost estimates for approval of owner.
j) Preparation of work-breakdown structure and programme for pre-construction activities.
k) Assisting client to obtain approvals of the Authority.
m) Preparation of detailed specification and
construction working drawings with integration of engineering inputs of all concerned disciplines.
n) Preparation of detailed design of each discipline for various services.
p) Peer review/proof checking of the drawings/ designs in case of important projects, depending upon their complexity and sensitivity.
q) Preparation of detailed cost estimate.
r) Obtaining final approval of client.
s) Preparation of bill of quantities, specifications and tender documents.
5.2 The following considerations, as may be applicable to the project, may be considered during planning, notwithstanding other relevant aspects specifically prescribed in concerned parts/sections of this Code; these considerations in general are with the objective of addressing to the important issues like environmental protection, energy conservation, cultural issues, creating barrier free built-environment, safety aspects, etc, all of these leading towards sustainable development, and have to be applied with due regard to the specific requirements of size and type of project:
a) Geoclimatic, geological and topographical features.
b) Varied sociological pattern of living in the country.
c) Effective land use to cater to the needs of the society in a most convenient manner.
d) Modular planning and standardization to take care of future planning giving due consideration to the specified planning controls.
e) Emphasis on daylight utilization, natural ventilation, shielding, and window area and its disposition; daylighting to be supplemented with an integrated design of artificial lighting.
f) Optimum utilization of renewable energy sources duly integrated in the overall energy system design; with consideration of active and passive aspects in building design including thermal performance of building envelope.
g) Rain water harvesting, and use of appropriate building materials considering aspects like energy consumption in production, transportation and utilization, recyclability, etc for promoting sustainable development.
h) Requisite mandatory provisions for handicapped persons.
j) Acoustical controls for buildings and the surroundings.
k) Promotion of artwork in buildings, specially buildings of importance.
m) Due cognizance of recommendations of the Archeological Survey of India with regard to national monuments and construction in archeologically important sites.
n) Due cognizance of relevant provisions of applicable coastal zone regulation act.
p) Conservation of heritage structures and areas.
q) Environmental and social impact analysis.
r) Design of services with emphasis on aspects of energy efficiency, environment friendliness and maintainability.
s) Integrated waste management.
t) Voice and data communication, automation of building services, and intelligent building; use of security and surveillance system in important and sensitive buildings, such as, access control for the people as well as for vehicle.
u) Interlinking of fire alarm system, fire protection system, security system, ventilation, electrical systems, etc.
v) Analysis of emergency power, standby power requirement and captive power systems.
w) Cost optimization through techniques like value engineering.
y) Adoption of innovative technologies giving due consideration to constructability and quality aspects.
z) Instrumentation of buildings and monitoring and use of information so generated to effect improvements in planning and design of future building projects.