Repairs to existing Building
(1) Repairs to be carried out can be categorized as detailed below:
Partial repairs- The repairs to the extent of 75% of BUA will be termed as partial repairs. The partial repairs shall be allowed with the permission of the Commissioner.
Extensive repairs- The repairs beyond 75% of BUA will be termed as extensive repairs which shall be allowed with the special permission of the Commissioner.
(2) Type of Repairs:
Category- I-The building neither affected by the road widening nor by DP Reservations.
Category-II-The buildings affected by the road widening or by reservations or by both
(3) Pre-requisites while submitting the proposal:
(i) Notice under section 342 of MMC Act and notice under section 44/69 of MR & TP Act 1966 duly signed by owner/NOC Holder.
(ii) NOC from M.B.R & R Board (if cessed building)
(iii) Structural audit report/Statutory Notice issued by MCGM/MHADA
(iv) Photographs showing condition of building as under:
a) Front roadside view from ground to top floor in one or more photographs as possible.
b) Side view elevation photographs wherever possible.
c) Dangerous portions proposed for repairs
d) Type of existing material in mode of construction
e) Roof photographs.
(v) Plan showing block plan, location plan and all the details existing on site
(vi) List of all the existing tenants/occupants signed by NOC Holder and countersigned by Architect, in case of non cessed building and list of all the existing tenants/occupants signed by Ex. Engineer M.B. R. & R Board in case of cessed building.
(vii) Owner’s consent for the proposed repairs/authority under section 499 of MMC Act where Owner’s consent for proposed repairs is not possible.
(viii)The onus of submitting authenticity of the structure for which repairs have been proposed shall entirely vest with owner/NOC holder
(4) Guidelines
(1) The buildings which are in need of Extensive Repairs shall be preferably developed or redeveloped under the provisions of these Regulations. However, if development/redevelopment is not possible due to various reasons such as size/shape of plot, disputes and other reasons, then Extensive Repair may be allowed.
(2)Except those buildings affected by setback of important roads from the point of view of their widening, in all other cases repairs will be allowed inclusive of setbacks, with registered undertaking for not claiming any compensation on account of repairs for the structure and shall
APPENDICES AND ANNEXURES
handover the portion of road setback as per prevailing policy/provision, when required by MCGM. The provision of Twin column arrangement shall be insisted at the sanctioned R.L / D.P. Road so as to detach the part of the building falling within the setback as and when required by MCGM for widening of roads.
(3) When repairs are allowed in the setback/widening of the road portion only then, Standing Committee shall be intimated as per the section 297(3) of MMC Act.
310
If a road is already widened on either side of the building which is to be taken up for repairs, such building can be taken up for repairs in conformity with (2) and (3) above, if it requires extensive repairs.
(4)Repairs may be allowed on sites under reservation, if the same is not under acquisition.
Incase of reserved sites which are under acquisition, the repairs may be allowed with special permission of the Commissioner. In both the cases, registered undertaking shall be insisted upon from the NOC holder/owner stating that no compensation will be claimed on account of repairs for the structure as and when the property is acquired, and grant of permission for repairs will not in any way affect the process of acquisition and shall not be used as a tool to impede the process of acquisition.
(5) It shall be the responsibility of the owner/NOC holder to ensure that the existing tenements/existing authorised uses are maintained.
(6) No repairs to the unauthorised structure/unauthorised part of structure shall be allowed.
(7) In case of cessed properties MHADA/MBRRB may carry out repairs of buildings after obtaining remarks from MCGM as per provisions of the MHADA Act. Remarks and observations if any as stated in these guidelines shall be complied with during the course of repairs.
Notes:
-
The repairs to the non-tallying portion which forms part of common amenities such as toilet block, washing places, common passage, and staircase can be considered at Dy. Ch. E (BP)'s level.
-
In case applicant submits documentary evidence from Government Authority to prove the existence of non-tallying portion prior to 01/04/1962 for non-residential and 17/4/1964 for residential buildings, repairs can be allowed
-
In case of partial/extensive structural repairs of buildings owned by Government/Semi Government organizations/Municipal Corporation/B.E.S.T. Undertaking/Government-Semi Government Undertakings, approval of the Head of department/Competent Authority of Concerned organization shall be sufficient. Structural Audit as per the requirement of MCGM and compliance thereof shall have to be observed by the concerned organization/Authority.
APPENDICES AND ANNEXURES