9. Development permission and commencement certificate
(1) Necessity of obtaining permission: No person shall erect or re-erect a building or alter any building or carry out any development or redevelopment, on any plot of land or cause the same to be done without obtaining development permission and a commencement certificate from the Commissioner.
(2) Items of operational construction by some authorities excluded: Construction for operational purposes, including maintenance of operational structures, emergency/essential staff quarters by the following organizations, authorities or departments, whether temporary or permanent, may be exempted from the purview of these Regulations, except those relating to floor space index and fire precautions:
i. Railways;
ii. National Highways;
iii. National Waterways;
iv. Major ports;
v. Aerodromes and Airports;
vi. Posts and Telegraphs, Telephones, Television, Wireless, Broadcasting authorities and the authorities of other similar forms of communication;
vii. Regional grids, towers, gantries, switchyards, control room, Relay room for transmission, distribution, etc. of electricity;
viii. Defence Authorities;
ix. Any other essential public services as may be notified by the State Government.
x. Metrorail Administration (MRA)/Project Implementing Agency designated by the Government for the Metro Rail and Monorail/Light Rail Transit (LRT) Projects.
xi. Facilities & services of Municipal Corporation of Greater Mumbai such as Roads, Water Supply, Sewerage, Storm Water Disposal and any other essential public services as decided by the Municipal Commissioner.
All such constructions shall, however, conform to the prescribed requirement for the provision of essential services, water supply connections, drains, etc. to the satisfaction of the Commissioner.
(3) Operational constructions excluded: The following constructions for operational purposes of the organizations, authorities or departments listed above are exempted from the purview of these Regulations except those relating to floor space index and fire precautions:
(i) Repairs and renovation of existing installations of buildings used for operational purposes alone and which do not involve addition to or increase of built-up areas.
(ii) In the case of the Railways/Metro Rail and Monorail/LRT Authority:
a) repairs and renovation of existing railway tracks, including culverts, over bridges, under-passes or bridges, tunnels and side drains;
PART II DEVELOPMENT PERMISSION
b) platforms, goods sheds and offices, parcel offices, sub-stations, foot-over bridges turntables, lifting towers, gantries, signal and signal boxes or control cabins in hump yards;
c) running (loco) sheds, carriage and wagon depots, carriage washing places, overhead or ground level water tanks, pipelines and pumping station; running rooms, train examiners' offices, yard depots, permanent way inspectors' and signal inspectors' stores in railway yards and all overhead electric equipment for traction.
d) Operational Control Centre, Playback Training Room, Stabling Yards, Maintenance Workshop, Auto wash plant, Auxiliary Rail Vehicle Building, Under Floor Wheel Lathe & Blow Down Plant, Cooling Tower, Generator Area, Auxiliary Substation, Traction Substation, Transformer Area, Water Treatment Plant, Wastewater Treatment Plant, Depot, Control Centre, Sump Area, Parking Check post, Loading & Unloading Areas, Fouling Points, DG Set Rooms, Metro& Mono Stations(Underground& Elevated),Viaduct & Tunnel, Ventilation Shaft, Entry/Exit Block, Passages, Underground Passages to Station Box, Lift/ Staircases, Escalators, Air Handling Unit.
(iii) Store sheds, when ancillary to operational requirement only;
Provided that, for the construction of new railway lines or tracks the approval of the State Government shall be necessary. For construction of new buildings, goods stores, sheds or platforms, parcel offices and workshops or for purposes of major remodeling, the approval of the Commissioner shall be necessary.
Further provided that, the following constructions by the organizations, authorities or departments listed in sub-Regulation (2) herein shall not be deemed to be operational for the purpose of exemption under the said Regulations, namely: -
(i) Residential buildings, commercial buildings, office buildings and industrial buildings (other than gate lodges, essential operational staff quarters and the like), roads and drains, hospitals, clubs, institutes and schools in residential, commercial or industrial areas of the colonies of such organizations, authorities or departments.
(ii) Construction, installation or any extension of any building in the case of any service other than those mentioned in this Regulation.
(4) Exclusion from requirement of permissions: -No permission shall be required to carry out tenantable repair works to existing buildings, which have been constructed with the approval from the competent authority or are in existence since prior to 17.04.1964 in respect of residential structures and 01.04.1962 in respect of non-residential structures, as described under section 342 of MMC Act 1888.
No permission shall be required for, provision of safety grills to window/ventilator. No permission shall be required for repairs to the Existing Consumer/Distribution/Receiving Substation of the BEST/Electric Supply Company. However, no addition/alteration shall be permissible without the approval of the Commissioner.
No permission shall be required for installation of Solar Panels having base of solar panel at height 1.8m from terrace, ensuring structural stability from the Licensed Structural Engineer.
No permission shall be required for internal light weight partitions/cabins up to height of 2.2 in the Residential/commercial building/establishment subject to structural stability from the Licensed Structural Engineer. Further internal light weight partitions/cabins up to floor height will be
PART II DEVELOPMENT PERMISSION
permissible if it satisfies the criteria for light & ventilation and other requirements of these regulations certified by the Architect/Licensed Surveyor/Town Planner, fire safety requirements certified by fire safety consultant and subject to structural stability from the Licensed Structural Engineer.
(5) Validity of development permission: The development permission granted in the past shall be governed by the provision of section 48 of the MR&TP Act, 1966.
Where development has commenced as per the development permission/IOD issued prior to publication of these Regulations, the CC shall be issued or revalidated till completion of development in accordance with the plans approved, in respect of the said IOD including minor amendments thereof as per the then Regulations.