i) The treated waste water shall be used only for gardening, toilet flushing, landscape, irrigation, cooling towers, car washing, etc. and in no case for drinking, bathing, or washing clothes and utensils.
ii) The output water quality shall conform to the standards of non-potable water as may be prescribed by the MPCB.
iii) A clause must be included by the owner/developer in the purchase agreement with the purchaser, owner of the premises/organization or society of the occupiers or the society of purchasers stating that recycled waste water system has been provided in the development and shall have to be maintained in good condition as per the requirements of MPCB, if any.
65. Sewage Treatment Plant (STP) & Disposal
Development/redevelopment of the plots which attract requirements/provisions of relevant Notification of Ministry of Environment and Forest (MoEF), Government of India issued from time to time shall be provided with Sewage Treatment Plant (STP) and disposal system.
Provision of STP and disposal system may also be permissible in any development other than mentioned above. The professional on record shall certify the detailed scheme for the STP and disposal system.
STP shall comply with the following:
a) STP structure shall be of compact design with due approval of relevant competent Authority
b) There shall not be any foul odour around the STP area or in the ambient environment.
c) STP shall not require continuous monitoring and operation and shall work well with inconsistent inflow.
d) Treated water quality shall be of non-potable standards and can be reused for gardening, toilet flushing, landscape, irrigation, cooling towers, car washing, etc. but in no case for drinking, bathing, or washing clothes and utensils.
PART – XII ENVIRONMENTAL SUSTAINABILITY
e) Treated water shall be environmentally safe to dispose of in Land or Water.
f) A clause must be included by the owner/developer in the purchase agreement with the purchaser, owner of the premises/organization or society of the occupiers or the society of purchasers stating that, STP has been provided in the development and shall have to be maintained in good condition as per the requirement of the Maharashtra Pollution Control Board (MPCB).
66. Solid Waste Segregation
All buildings shall be provided with separate coloured bins to collect dry waste (paper, plastic, metal, glass, etc.) and wet waste (organic waste). Dedicated space shall be allocated for collecting waste before transferring waste for recycling/disposal separately.
Separate bins shall be provided for safe disposal of hazardous waste (batteries, e-waste, lamps, medical waste, etc.) as provided in hazardous waste management guidelines prescribed by the Ministry of Environment and Forest (MoEF), Government of India.
Provision for treating the wet waste in situ will have to be made and a clause must be included by the owner/developer in the purchase agreement with the purchaser, owner of the premises/organization or society of the occupiers or the society of purchasers stating that, wet waste will be treated in situ and shall have to be maintained in operational condition as per the requirement of MCGM if any.
The planning design, construction and installation of Solid Waste Management System shall be as per the National Building Code of India, Part 9 Plumbing Services, Section 1- Water Supply, Drainage and Sanitation (Including Solid Waste Management) Paragraph 6.
On the plots having total construction area 20,000 Sq.mt & above Bio-degradable Waste Treatment Plant of required capacity shall be provided and maintained.
The area under construction of Solid Waste Management System /Bio-degradable waste treatment plant shall be free of FSI.
The Completion Certificate for the Solid Waste Management System /Bio-degradable Waste Treatment Plant issued by Environmental Consultant shall be submitted before asking for Occupation Certificate/Building Completion Certificate.”
67. Tree Plantation Provisions for Enhancing/Conserving/Preserving Biodiversity
i) The development in any plot of land shall be such as to preserve, as far as practicable, the existing trees. Where trees are required to be felled, twice the number of trees shall be planted for every tree to be felled.
ii) Every plot of land shall have at least
(a)at the rate of 5 trees per 100 sq.m or part thereof of the said recreational space, to be grown within the entire plot.
(b) at the rate of 1 tree per 80 sq. m or part thereof to be grown in a plot for which a sub-division or layout is not necessary.
iii) Trees shall be planted taking care that they shall not obstruct the maneuvering of firefighting vehicles during an emergency.
iv) In between the trees planted along the boundary of plot, shrubs with grass shall be planted.
PART – XII ENVIRONMENTAL SUSTAINABILITY
68. Coastal Regulation Zone (CRZ)
Notwithstanding anything contained in these Regulations, any development within CRZ areas shall be governed by the amended Coastal Regulation Zone Notification No.S.O.19(E), dated 6th Jan, 2011 Ministry of Environment and Forest (MoEF), Government of India as amended from time to time, wherever applicable. Lands shown as Natural Area in DP and situated on the seaward side of High Tide Line, if after modification to High Tide Line, falls on the landward side of modified High Tide Line, then in such case the said land will be deemed to have been situated in the zone of adjoining land unless, said land is forest/salt pan land/occupied by mangroves/mud flats.
69. Environment Impact Assessment (EIA)
This Regulation shall be applicable to developments as specified in provisions of amended Environmental Impact Assessment Notification No.S.O.1533 dated 14.09.2006 as amended from time to time. The compliance of conditions of NOC/Remarks shall be the responsibility of the owner/developer/project proponent.
70. Energy Efficient Buildings
Owner/Developer/Project proponent at his option may opt for the certification of Indian Green Building code (IGBC)/Energy Conservation Building Conservation Code (ECBC). The provisions of appliances/fitting as per IGBC/ECBC shall be as per direction of GOI/GOM if any from time to time.
APPENDICES AND ANNEXURES
DCPR-2034