57. Temporary Constructions
The Commissioner may grant permission for temporary construction of a period not exceeding six month at a time and in the aggregate, not exceeding a period of three years. Such permission may be given by him for the construction of the following, namely:
(i) Structures for protection from the rain or covering of the terraces during the monsoon only;
(ii) Pandals for fairs, ceremonies, religious functions, circus, jatra, folk dance etc;
(iii) Structures for godowns /storage of construction materials within the site;
(iv) Temporary site offices and watchmen chowkies and labourer hutments with crèche, sales office/sample or show flat within the site only during the phase of construction of the main building;
(v) Structure for exhibitions/circuses, etc.;
(vi) For factories in industrial lands, structures within the site for storage of machinery before installation;
(vii) Structures for ancillary works for quarrying operations in conforming zones;
(viii) Milk booths and telephone booths;
(ix) Transit accommodation for persons to be rehabilitated in a new construction:
(x) Structures for educational and medical facilities within the site of the proposed building during the phase of planning and constructing the said permanent buildings:
(xi) On site, Ready Mix Concrete (RMC) plant for the use at site under development/construction.
Provided that temporary construction for structures, etc. mentioned at (iii), (iv), (vi), (ix), (x)and (xi) maybe permitted to be continued temporarily by the Commissioner but in any case, not beyond completion of construction of the main structure or building, and that structure in (viii) may be continued on annual renewable basis by the Commissioner beyond a period of three years.
58. Common Antenna for Television Transmission Reception/ Telecommunication /Digital Communication/Service: -
In every Building the provision for
(1) Installation of common Television Transmission Reception/Antenna and Ducting for telecommunication lines and optical fiber cable for Digital Data communication/transmission shall be made.
(2) Ducting for laying of piped gas connection service in the surrounding of building.
59. Special Purpose NOCs
Wherever necessary, special purpose NOCs shall be required to be submitted for the development of plot/s depending upon the location & type of work as specified in these Regulations. Observance of requirements of these and all other NOCs shall be the responsibility of Owner/Developer/Project Proponent. The Commissioner may grant permissions/approvals for development based on an undertaking by the Owner/Developer/Project Proponent that he shall comply with all the requirements of special NOCs ,Laws, and Regulations that are applicable from time to time. The illustrative list of special purpose NOC’s is mentioned in Appendix III.
PART – XI MISCELLANEOUS PROVISIONS
60. Repairs to Existing Building
The structural/extensive repairs to the existing buildings, which have been constructed with the approval from the competent authority or were in existence prior to17.04.1964 in respect of residential structures and 01.04.1962 in respect of non-residential structures and which are in need of structural/extensive repairs, may be allowed without change in footprint/planning. Under the guise of repairs, addition/alterations/vertical & horizontal extension to the existing structures shall not be permissible. The structural /extensive repairs to the existing buildings may be allowed as described in Appendix IV.
60(A). Approvals of Building Permission on Fast Track based on Risk Based categorization
Notwithstanding anything contained in DCR/DCPR of the respective said Authority, the Regulations regarding approval of Building Permission by the Architect/L.S./Engineer at the stage of Commencement, Plinth checking and Completion cum Occupancy shall be as per Risk Based Classification of Building given in Table below:-
| Sr. No. | Parameters to be consider for Risk Base. | Risk Category | |
| Low Risk Category | Moderate Risk Category | ||
| 1 | Plot Area considered for Risk Based Assessment. | Buildings on a plot area upto 150 sq.m. | Buildings on a plot area between 151 sq m and upto200sq.m. |
| 2 | Permissibility In Development Plan Zone | Residential Zone, Commercial zone and Public-Semi-public Zone | Residential Zone, Commercial zone and Public-Semi-public Zone |
| 3 | Plot status | The plot should be vacant. The Plot Status, Plot criteria and permissibility in above land use zone shall be as per respective DCPR. | The plot should be vacant. The Plot Status, Plot criteria and permissibility in above land use zone shall be as per respective DCPR. |
| 4 | Type of building | Residential and other buildings as per DCPR | Residential and other buildings as per DCPR |
| 5 | Proposed Structure of Building/Storey | G.F. / P+1 RCC./Load Bearing | G.F.+1/P+2 RCC./Load Bearing |
| 6 | Front and side open spaces, Provision of Basement, Parking requirement and other requirements. | As per the provisions of Development Control Regulations. | As per the provisions of Development Control and Promotion Regulations. |
| 7 | Tree cutting/ Tree replantation. | Not permitted. | Not permitted |
| 8 | Experience Criteria for Architect /L.S./Engineer for | As per Annexture-10 of the respective DCPR regarding | As per Annexture-10 of the respective DCPR regarding |
PART – XI MISCELLANEOUS PROVISIONS
| self-certification and all approval mentioned in this regulation. | licensing and qualifications of the technical person. | licensing and qualifications of the technical person. |
|---|
Building Permission/Commencement Certificate:-
a) Submission of Proposal:- The proposal shall comprise of application u/s 44/69 of MR&TP Act, 1966, in format prescribed by Municipal Commissioner/Chief Officer/Chief Executive Officer, along with documents and undertakings required for the proposal as per regulation & required by the Municipal Commissioner/Chief Officer/Chief Executive Officer from time to time. All the required documents shall be certified and signed by the Architect /L.S./Engineer confirming with the original documents. The documents required shall be as per the DCPR of the said Authority.
b) Commencement Certificate (CC) :-After receipt of the application, the Demand Note regarding payment of Scrutiny Fee, Development Charges and other Charges based on the proposed Plans/Drawing submitted shall be given by the concern Engineer of the authority within 10 days. The owner / Architect /L.S./Engineer shall deposit the Charges as demanded. Upon deposit of such Charges with the Planning Authority, the concerned Architect/ License Surveyor (L.S.)/Engineer are empowered to grant provisional approval in the form of self-certification certifying that the plan / entire building proposal is strictly in conformity with the DCPR. This self-certification shall be treated as Commencement for the construction work.
The owner/concern Architect/License Surveyor (L.S.)/Engineer shall submit the said self-certified plan to the Authority within 10 days. Upon such submission, The Junior most Officer/Junior Engineer at ward level, authorized by Municipal Commissioner/Municipal Chief Officer shall countersign the plans without any scrutiny and issue Commencement Certificate Under Section-45 of Maharashtra Regional and Town Planning Act, 1966 within 10 days from the receipt of such plan. The Scrutiny at Authority level need not be necessary. Concern Architect/L.S./Engineer is empowered/Authorized to issue the copies of such approved plans &Certificates with his signature.
PART – XI MISCELLANEOUS PROVISIONS
c) Plinth Checking for Moderate Risk building proposal: -The concern Architect /L.S./Engineer shall apply for certificate of plinth checking in prescribed application for Moderate Risk building proposal only. The inspection shall be done by the concern Junior Engineers. The inspection report shall be prepared and uploaded within 48 hours. The Plinth checking certificate shall be grant within the period of 7 days from the receipt of the application, if found as per the sanctioned plan.
d)Building completion certificate :-On completion of work, the concern Architect/L.S./Engineer shall issue the Building completion certificate and Occupation certificate, as required as per the provision of DCPR to the completed building/structure and submit two set of completion plan along with the required certificate and all site inspection report to the authority. The concerned Engineer authorized by Municipal Commissioner / CEO MHADA/ SRA shall countersign the said Completion Plan along with Occupancy Certificate within 10 days without any scrutiny and site inspection.