RWH in a building site includes storage or recharging into ground of rain water falling on the terrace or on any paved or unpaved surface within the building site.
- The following systems may be adopted for harvesting the rain water drawn from terrace and the paved surface.
(i) Open well of a minimum diameter of 1m and minimum depth of 6m OR open well of a minimum diameter of 0.3 m and minimum depth of 2 m at every 6 m in the Storm Water Drain, in to which rain water may be channeled, after filtration for removing silt and floating material. The well shall be provided with ventilating covers. The water from the open well may be used for non-potable domestic purposes such as washing, flushing and for watering the garden.
(ii) RWH for recharge of ground water may be done through a bore well around which a pit of one meter width may be excavated upto a depth of at least 3 m and refilled with stone aggregate and sand. The filtered rain water may be channeled to the refilled pit for recharging the borewell.
(iii) An impervious surface/underground storage tank of required capacity may be constructed in the open space and the rain water may be channeled to the storage tank. The storage tank shall always be provided with ventilating covers and shall have drawn-off taps suitably placed so that the rain water may be drawn off for domestic washing, gardening and such other purposes. The storage tanks shall be provided with an overflow.
(iv) The surplus rain water after storage may be recharged into ground through percolation pits or trenches or combination of pits and trenches. Depending on the geomorphological and topographical condition, the pits may be of the size of 1.20 m width x 1.20 m length x 2.00 m to 2.50 m depth. The trenches can be of 0.60 m width x 2.00 to 6.00 m length x 1.50 to 2.00 m depth. Terrace water shall be channeled to pits or trenches. Such pits or trenches shall be back filled with filter media comprising the following materials.
a) 40 mm stone aggregate as bottom layer up to 50% of the depth;
b) 20 mm stone aggregate as lower middle layer up to 20% of the depth;
c) Coarse sand as upper middle layer up to 20% of the depth;
d) A thin layer of fine sand as top layer;
e) Top 10% of the pits/ trenches will be empty and a splash is to be provided in this portion in such a way that roof top water falls on the splash pad.
f) Brick masonry wall is to be constructed on the exposed surface of pits/ trenches and the cement mortar plastered.
The depth of wall below ground shall be such that the wall prevents lose soil entering into pits/trenches. The projection of the wall above ground shall be atleast 15 cm.
g) Perforated concrete slabs shall be provided on the pits/trenches.
(v) If the open space surrounding the building is not paved, the top layer upto a sufficient depth shall be removed and refilled with course sand to allow percolation of rain water into ground.
(vi) For effective drainage of rain water, the roof of building shall be so constructed or framed as to permit effective drainage of the rain water therefrom by means of rain water pipes. Such pipes shall be so arranged, joined and fixed so as to ensure that the rain water is carried away from the building without causing dampness in any part of the walls or foundation of the building or those of adjacent buildings.
PART – XII ENVIRONMENTAL SUSTAINABILITY
-
The terrace shall be connected to the open well/borewell/storage tank/recharge pit/ trench by means of HDPE/PVC pipes through filter media. A valve system shall be provided to enable drain away the first washings from roof or terrace catchment, as they would contain undesirable dirt. The mouths of all pipes and openings shall be covered with mosquito (insect) proof wire net. For the efficient discharge of rain water, there shall be at least two rain water pipes of 100 mm dia. for a roof area of 100 sq. m.
-
RWH structures shall be so sited as not to endanger the stability of building or earthwork. The structures shall be designed such that no dampness is caused in any part of the walls or foundation of the building or those of an adjacent building.
-
The water so collected/ recharged shall as far as possible be used for non-drinking and non-cooking purpose.
Provided that when the rain water in exceptional circumstances will be utilised for drinking and/ or cooking purpose, it shall be ensured that proper filter arrangement and the separate outlet for by passing the first rain-water has been provided.
Provided further that it will be ensured that for such use, proper disinfectants and the water purification arrangement have been made.
63. Special Provisions; for installation of Solar Water Heating (SWH) Systems.
Solar Water Heating (SWH) Systems shall be installed in the buildings for Hospitals, Hotels, Guest Houses, Police/Army Barracks, Canteens, Laboratories and Research Institutions, Hostels of Schools and Colleges and other Institutions.
-
The SWH systems shall be mandatory in hospitals and hotels, where the hot water requirement is of continuous nature. In these buildings, the system shall be provided with auxiliary electrical back-up.
-
The use of SWH system is recommended in the following type of buildings in Govt/Semi–Govt and Institutional buildings where the hot water requirement may not be continuous/permanent:
-
Guest House
-
Police/Army barracks
-
Canteens
-
Laboratory and Research Institutions where hot water is needed
-
Hostels of Schools and Colleges and other Institutes.
- The use of SWH system may be allowed in any other building.
The installation of the electrical backup in all such water heating systems shall be optional depending on the nature of requirement of hot water.
It is suggested that SWH systems of the capacity of about 100 liters per day on thermosyphon with necessary electrical back-up be installed at residential buildings like hostels.
In order to facilitate the installation of the SWH systems, the new buildings of aforesaid types shall have the following provisions.
-
All such buildings where SWH systems are to be installed will have open sunny roof area available for installation of SWH system.
-
The roof loading adopted in the design of such building should be at least 50 kg/sq. m for the installation of SWH system.
PART – XII ENVIRONMENTAL SUSTAINABILITY
-
SWH systems can also be integrated with the building design. These can either be put on the parapet or could be integrated with the south facing, vertical wall of the building. The best inclination of the solar energy collector for regular use throughout the year is equal to the local Latitude of the place. The solar energy collector should be facing south. However, for only winter use, the optimum inclination of the solar energy collector would be Latitude+15 degrees of the south.
-
All the new buildings of aforesaid types to be constructed shall have an installed hot water line from the roof top and also insulated distribution pipelines to each of the points where hot water is required in the building.
-
The capacity of the SWH system to be installed on the building shall be decided on the basis of the average occupancy of the buildings. The norms for hospitals, hotels and other buildings are given below:
64. Waste (Grey)Water Recycling and Reuse
(1) Development/redevelopment of the plots which attract requirements/provisions of Notifications of Ministry of Environment and Forest (MoEF), Government of India, issued from time to times hall have the provision for recycling and reuse of waste water.
Provision of recycling and reuse of waste water system may also be permissible in any development other than mentioned above. The professional on record shall certify the detailed scheme for the recycle and reuse of waste water.
PART – XII ENVIRONMENTAL SUSTAINABILITY
The Waste Water Recycling System shall include the following:
i) Waste water other than from water closet, laundries, and hospitals shall be recycled.
ii) The system shall not constitute a nuisance of foul gases and/or cause public hazard due to its installation and operation.
iii) The waste water recycling system shall be designed considering the anticipated occupancy load and seasonal fluctuations in discharge.
iv) Separating of Waste Water:
(a) The waste water shall be recycled by installing recycling plant.
(b) Separate plumbing network shall be installed to collect waste water from kitchens, bath rooms, washing machines and dish washers leading to recycling plant with separate underground and overhead tanks provided for this purpose.
(c) The entire connecting network shall be painted in purple blue color.
(d) Recycled Waste Water system shall be maintained in good condition and shall comply with the requirements of Maharashtra Pollution Control Board (MPCB), if any.