(i) Every applicant or builder or owner shall submit a notice regarding his intention to commence the foundation work of the proposed multi-storied building to the Authority through authorized technical persons. The said notice shall be accompanied by the approved plan and should be in Form-V.
(ii) Soon after the receipt of the notice referred to in sub- clause (1) above, the Authority shall send a team of officers including, a civil Engineer, Architect and Town Planner, to the proposed building site and the layout for foundation of the proposed multi-storied building shall be made in presence of those officers. The team shall also submit a report to the Authority to the effect that the layout has been made as per the approved plan.
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019
Chapter 17
Multi-Storied Buildings and Group Housing Schemes/Apartments: Additional Requirements
(iii) During or soon after the construction of the foundation work of the multi-storied building, the Municipal Chairperson, Municipal President of the Authority or his representatives or independent Engineer/ Architect appointed by Authority shall inspect the construction to ensure that the setbacks, coverage, basement if any, and foundation standards are according to the approved plan.
(iv) The applicant / builder shall submit periodic progress report after casting of each floor slab in Form-VIII.
17.4 Liability of Defective Construction
(i) For defective constructions, the Authority shall sue the owners, builders, architects, and the engineers for both civil and criminal liabilities, besides taking action under these Bye-Laws.
(ii) Without prejudice to the provisions of the Act, the actions to be taken by the Authority shall include notices, cancellation of permission, stopping construction and removal of unauthorized constructions. Such actions shall be notified.
17.5Maintenance
(i) The main entrance to the premises shall not be less than 5 (five) meters in width in order to allow easy access to fire engine. The gate shall fold back against the compound wall of the premises, thus leaving the exterior access way, within the plot, free for the movement of fire service vehicles. If archway is provided over the main entrances, the height of the archway shall not be less than 5 (five) meters.
(ii) For multi-storied group housing scheme on one plot, the access way within the premises shall not be less than 7.5 (seven and half) meters in width and between individual building blocks, there shall be an open un-built space of 6 (six) meters.
(iii) The space set apart for providing access within the premises shall, in no case, be included in the calculation of requirements pertaining to parking spaces and other amenities required to be provided for the building.
(iv) Every access way shall be properly drained and lit to the satisfaction of the Authority. Manhole covers or any other fittings laid within the right of way of the access way shall be flushed with the finished surface level of it so as not to obstruct safe movement of men and vehicles.
(v) Reconstruction or addition or alteration to any multi-storied building shall not be taken in a manner which shall reduce the width of the access way to a level below the minimum prescribed limit under these Bye-Laws.
17.7ICT Landing Points
Table 17.1Number of Occupants as per type of Occupancy
Sl. No
Type of Occupancy
Number of Occupants per unit exit
Staircase
Terrace
1
2
3
4
1
Residential
25
75
2
Mixed and Other Uses
50
75
Every multi storied building complex shall have provision for Information and Communication Technology (ICT) landing point in the form of a room near the main entrance gate of dimension not less than 3m x 4m and having 3m clear height. The room shall have two fire proofs doors of 1.2m width opening outwards along with adequate ventilation in the form of windows/ ventilators. Such room shall not be counted in coverage and Floor Area Ratio (FAR) calculations.
17.8Penal Action against Builders/ Technical Personnel
(i) Notwithstanding anything contained in these Bye- Laws the Authority reserves the right to debar/ black list the builder/ technical person who has deviated from the professional conduct or has made any fraudulent statement or has misrepresented/suppressed any material facts in his application/ plan or is involved in construction of the building deviating from the approved plan/norms of these Bye-Laws.
(ii) Before taking any action under clause (1) specified above the Authority shall issue a notice specifying the reasons thereof asking for a show-cause within 15 days as to why such builder / technical person shall not be debarred / black listed. After receipt of the show cause, if any, the same shall be placed before the Authority for a decision on debarring / black listing the technical person / builder. The decision of the Authority in this regard shall be published.
(iii) An appeal against an order under sub-clause (2) above shall lie under section 30 of the Arunachal Pradesh urban and Country Act 2007.
Chapter 17
Multi-Storied Buildings and Group Housing Schemes/Apartments: Additional Requirements
17.10Completion of Construction
Every applicant/ owner shall submit a notice in Form - VI (Part-I and Part-II) regarding completion of the construction of multi-storied building, to the Authority through the registered Architect / Structural Engineer, etc who has supervised the construction. The said notice shall be accompanied with the following documents:
A. Three copies of plan of the completed building.
B. Fee, time to time fixed by the authority.
C. Record of Rights relating to ownership.
D. Evidence that all public utility services, and in particular, sewerage, drainage, water supply, and electricity have been linked to the main public utility system.
E. No Objection Certificate from Director Fire Services
17.11Issue of Occupancy Certificate
(i) The Authority on receipt of the notice of completion, along with all the required documents, shall take a decision to either issue or refuse occupancy certificate in Form-X within 30 days from the date of receipt of such notice. This fact shall be published in the public notice and website of the Authority.
(ii) If the occupancy certificate is not issued by the Authority within (60) sixty days from the receipt of notice, the owner can prefer an appeal.
(iii) Where occupancy certificate is refused by the Authority, reasons thereof shall be communicated to the applicant and the same shall be published. An appeal against such a decision will lie under section 34 (1) of the Arunachal Pradesh Urban & Country Planning Act 2007.
Chapter 17
Multi-Storied Buildings and Group Housing Schemes/Apartments: Additional Requirements
17.2Stage of Permission
Permission for construction of a multi-storied buildings & Group Housing Schemes shall be given with the approval of the Authority and in following stages namely:-
A. In the first stage permission shall be accorded conditionally to develop the infrastructure as per specification of Local Authority and Public Health Engineering Department.
B. After joint inspection, up to 75% of the proposed building height shall be allowed.
C. After completion of construction up to 75% of the proposed building as per the approved plan and plantation of 20% of the plot area the remaining 25% construction shall be allowed.
Note: The plantation shall not obstruct free movement of fire tenders around the building.
17.12Structural Safety Design and Other Services Requirements
(i) Structural Design: The structural design of foundation, masonry, timber, plain concrete, reinforced concrete, pre-stressed concrete and structural steel shall be carried out in accordance with Part-VI structural design, section-1 loads, section-2 foundation, section-3 wood, section-4 masonry, section-5 concrete and section-6 steel of National Building Code of India taking into consideration all relevant Indian Standards prescribed by Bureau of Indian Standards including the Indian Standard given in IS-Code 1893-1984, 13920-1993, 4326-1993, 13828-1993, 13827-1993 and 13935-1993 for structural safety.
(ii) Quality of Materials and Workmanship: All material and workmanship shall be of good quality conforming generally to accepted standards of Public Works Department and Indian standard specification and codes as included in Part-V Building Materials and Part-VII Construction practices and safety of National Building Code of India.
(iii) Alternative Materials, Methods of Design and Construction and Tests: The provision of the Bye-Laws are not intended to prevent the use of any material or method of design or construction not specifically prescribed by the bye-law provided any such alternative has been approved. The building materials approved by B.I.S. or any statutory body will form part of the approved building material and technology as part of the Bye-Laws.
(iv) Building Services
A. The Planning design and installation of electrical installations, air conditioning installation of lifts and escalators can be carried out in accordance with Part-VIII Building Services, section–2 electrical installation, section–3 air conditioning and heating, section-5 installation of lifts and escalators of National Building Code of India, 2005
B. The requirements of electric sub-station and the provision of electric sub-station shall also require approval from the concerned Authority.
(v) Plumbing Services
The planning, design, construction and installation of water supply, drainage and sanitation and gas supply system shall be in accordance with Part-IX, Plumbing Services, section-l water supply; section-2 drainage and sanitation and section-3 gas supply of National Building Code of India 2005.
Annexure & Appendices
Annexure & Appendices
Annexure and Appendices
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019
Annexure A
Annexure & Appendices
Annexure $pmb { A } ^ { prime prime }$
Occupancy Categorization of Buildings for Water and Other Requirement for Fire Fighting
Zone-I
Zone-II
Zone-III
GROUP "A": RESIDENTIAL
GROUP "A": RESIDENTIAL
GROUP "A": RESIDENTIAL
A1LodgingandRoomingHouses
F2 Shops and stores, etc. above500
A2One or two families private dwelling
A5 Hotels
sq.mt. floor area
A3Dormitories
F3Underground shopping centers
A4Apartment Houses
GROUP "B" EDUCATIONAL
GROUP "C" INSTITUTIONAL
GROUP "G" INDUSTRIAL
B1Schoolsupto higher secondary level
C1Hospitals and Sanitoria (More than 100 beds)
G3High hazard Industries
GROUP "C" INSTITUTIONAL
GROUP "D" ASSEMBLYBUILDINGS
GROUP"H"STORAGEBUILDINGS
C1 Hospital & Sanitoria (upto100 beds)
D1 for more than 1000 persons with permanent
C2Custodial Institutions
stage and fixed seats
C3 Penal & mental Institutions
D2 for less than 1000 persons with permanent stage and fixed seats
GROUP "D" ASSEMBLY
GROUP "E" BUSINESS
GROUP"J"HAZARDOUSBUILDING
BUILDINGS
BUILDINGS
S
D3Upto300persons without permanent
E1Offices, Banks, etc.
stage and fixed seats
E2Laboratories, Libraries, etc.
D4Above 300 persons without
E3Telephone Exchanges
permanent stage & fixed seats
GROUP "E" BUSINESS
GROUP "F" MERCANTILE
E3Computer Installations
F1 Shops, Stores, etc. upto 500
E5Broadcasting stations
m<sup>2</sup> floor area
GROUP "G" INDUSTRIAL
GROUP "G" INDUSTRIAL
G1Low hazard Industries
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019
Annexure B I
Annexure & Appendices
Chapter 17Multi-Storied Buildings and Group Housing Schemes/Apartments: Additional Requirements
17.1 Restriction on Construction of Multi-Storied Building
(Construction of multi-storied building shall not be permitted in localities, sectors “A”, “B”, “P”, and Upper Niti Vihar in Itanagar. The Authority may include any other areas for prohibition of multi storied building from time to time by notification.
The Authority may restrict construction of multistoried buildings in any other area on the basis of objective assessment of the available infrastructure and planning needs after obtaining due approval of the Government.
Before commencement of these Bye-Laws, where permission has been granted conditionally, such cases shall be dealt with under these Bye-Laws as far as possible, without any major change, or without removal of construction. However, where violation of Heritage Zone conditions has occurred, this relaxation shall not apply.
No multi-storied building shall be allowed to be constructed:
A. With approach road less than 18 m. width;
B. On plot the size less than 5000 sq. m.
C. Within 100 meters from the centre of the National High Way 415-A or on either side in the corridor between Banderdewa and Chimpu via Naharlagun and Itanagar.
D. Within 100 meters from the centre of the State Highway or major roads connecting two or more Districts on either side.
17.6Exit
(i) Every multi-storied building meant for human occupation or assembly, shall be provided with exit sufficient to permit safe escape of the occupants in case of fire or other emergencies.
(ii) An exit may be a door-way, corridor, passage way to an internal or external staircase or to a verandah or roof or terrace having access to a street.
(iii) Exits shall be so arranged as to provide continuous means of access to the exterior of a building or exterior open space leading to a street without passing through any occupied unit.
(iv) Exits shall be so located that the travel distance on the floor shall not exceed twenty meters in case of residential, educational, institutional and hazardous occupancies and thirty metres in the case of assembly, business, mercantile, industrial and storage occupancies. Wherever more than one exit is required for a floor of a building, exits shall be placed at a reasonable distance from each other as possible. All the exits shall be accessible from the entire floor area at all floor levels.
(v). There shall be at least two exits serving every floor and at least one of them shall lead to a staircase.
Chapter 17
Multi-Storied Buildings and Group Housing Schemes/Apartments: Additional Requirements
(vi) The width of every exit shall not be less than one meter and shall be provided as per the following table.
Table – 11.1 Number of Occupants as Per Type of Occupancy
Explanation:
A. Lifts and escalators shall not be considered as an exit.
B. ‘Travel distance’ means the distance from any point in the floor area to any exit measured along the path or egress except that when the floor areas are sub-divided into rooms, used singly or of rooms and served by suite corridors and passage, the travel distance may be measured from the corridor entrance of such rooms or suites to the nearest staircase or verandah having access to the street.
17.9Occupancy of the Building
In addition to the general provisions the following provisions shall be followed in case of multi storied buildings, apartments and group housing schemes;
(i) No person shall occupy or allow any other person to occupy any part of the multi-storied building for any purpose until such building or any part of it, as the case may be, is granted occupancy certificate by the Authority.
(ii) On receipt of completion certificate in Form-6 (Part-I & Part-II) the authority shall issue a provisional occupancy certificate in Form-X to enable the builder / land owner to obtain service connections.
The authorities entrusted with the job of providing services like electricity, water supply and sewerage shall not provide such services without provisional occupancy certificate by the Authority. However, temporary service connection may be provided for construction purpose.
(iii) The builder shall cause to register an Association of apartment owners, before occupancy certificate for 50% or more of the floor area is given.
(iv) The Builder shall submit a copy of the agreement it has entered into with the apartment owners’ society. This agreement shall show the terms of maintenance of public utilities.
(iii) On satisfactory compliance of above & provision of the services the final occupancy certificate shall be issued by the authority.
Annexure “B-I”
Fire Protection Requirements for Buildings in Zone-I Category
Sl. No.
Measures
Group-A: Residential A1, A2, A3, A4
Group-B: Educational
Group-C: Institutional
O
I
II
III
I
II
III
I
II
III
1
Access
P
P
P
P
P
P
P
P
P
P
2
Means of Escape
P
P
P
P
P
P
P
P
P
P
3
Compartmentation
P
P
P
P
P
P
P
P
P
P
4
Refuge Area
X
X
X
X
X
X
X
X
X
X
5
Emergency Lights
X
X
P
P
P
P
P
P
P
P
6
Exit Signs
P
P
P
P
P
P
P
P
P
P
7
PA System with Talk Back Facility
X
X
X
X
X
P
P
P
P
P
8
Moefa
X
X
X
P
X
P
P
P2
P
P
9
Extinguishers
P
P
P
P
P
P
P
P
P
P
10
Hose Reel
P3
P
P
P
P3
P
P
P
P
P
11
Yard Hydrant
X
X
X
P
X
P
P
X
P
P
12
Down Comer
X
X
X
P
X
P
X
P4
X
X
13
Wet Riser
X
X
P
X
X
X
P
X
P
P
14
Fire Detection System
X
X
X
X
X
P6
X
P2
P
P
15
Automatic Sprinkler System
S
S
S
S
S
S
FS
S
S
FS
16
Under Ground Tank
X
X
X
X
X
X
P
P2
P
P
17
Over Head Tank
P13
P
P
P
P
P
P
P
P
P
18
Fire Pumps
X
X
X
X
X
X
P
X
P
P
19
Booster Pumps
P3
P
P
P
P
P3
P
P
X
P
20
Auto D.G. Set
P3
X
P
P
P3
P
P
P
P
P
21
MCB/ELCB
P
P
P
P
P
P
P
P
P
P
22
Hose Boxes
X
X
X
P
X
P
P
P4
P
P
23
Fireman's Grounding Switch
P
P
P
P
P
P
P
P
P
P
VI. Height less than 15 m and plot area 501 sqm and above up to 1000 sqm.
Annexure B I
Annexure & Appendices
Annexure – B I (Contd.) Fire Protection Requirements for Buildings in Zone-I Category
Sl. No.
Measures
Group - D: Assembly D3 D4
Group-E: Business E3 E5
Group - G: Industrial G1
I
II
III
I
II
III
IV
V
VI
VII
VIII
1
Access
P
P
P
P
P
P
P
P
P
P
P
2
Means of Escape
P
P
P
P
P
P
P
P
P
P
P
3
Compartmentation
P
P
P
P
P
P
P
P
P
P
P
4
Refuge Area
X
X
X
X
X
X
X
X
X
X
X
5
Emergency Lights
P
P
P
P
P
P
P
P
P
P
P
6
Exit Signs
P
P
P
P
P
P
X
X
P
P
P
7
PA System with Talk Back Facility
P1
P
P
X
P
P
X
X
X
X
P
8
Moefa
P1
P
P
X
P
P
X
X
P
P
P
9
Extinguishers
P
P
P
P
P
P
P
P
P
P
P
10
Hose Reel
P2
P
P
P
P
P
X
P
P
P
P
11
Yard Hydrant
X
P
P
X
P
P
X
X
X
P
P
Legend
Guest Houses/Lodging having up to 20 rooms or 40 beds and below:
I. Height less than 15 meters.
II. Height 15 m and above up to 24 meters.
IV. Height less than 15 m and plot area less than 250 sqm.
V. Height less than 15 m. and plot area 251 sqm and above up to 500 sqm.
X Not to be provided.
S Sprinklers to be provided if basement area is 200 sqm or more.
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh BuildingByelaws 2019|
Annexure B I
Annexure & Appendices
To be provided if building is more than ground floor, first floor and total covered area exceed 1500 sqm.
To be provided in building where total covered area exceeds 1000 sqm or Building is more than ground floor except group housing.
To be provided if building is ground floor, first floor and total covered area exceeds 300m.
To be provided if building is more ground floors.
To be provided in building except educational buildings.
In case seating capacity is 1000 persons minimum or covered area above 1500 sqm or basement area 200 sqm and more (other than places or worships).
To be provided for E-4 and E-5 buildings but not required if building is fully sprinklered.
To be provided for E-4 and E-5 buildings.
25,000 lt. capacity underground water storage tank to be provided.
50,000 lt. capacity underground water storage tank to be provided.
To be provided where ever sprinklers are not installed.
Terrace tank of 5,000 lt. capacity to be provided, if sprinklers and installed. The capacity shall be accordingly increased.
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh BuildingByelaws 2019|
Annexure B II
Annexure & Appendices
Annexure ${ } ^ { prime } pmb { B } { cdot } pmb { U } ^ { prime prime }$
Fire Protection Requirements for Buildings in Zone-II Category
Sl No
Measures
Group-A: ResidentialA5 : Hotels
Group-C:C2:Hospital
Group-D: Assembly D1, D2, D5
I
II
III
IV
V
VI
V
VI
1
Access
P
P
P
P
P
P
P
P
2
Means Of Escape
P
P
P
P
P
P
P
P
3
Compartmentation
P
P
P
P
P
P
P
P
4
Refuge Area
X
X
X
X
X
X
X
X
5
Emergency Lights
P
P
P
P
P
P
P
P
6
Exit Signs
P
P
P
P
P
P
P
P
7
PA System With Talk Back Facility
X
P
P
P
P
P
P
P
8
Moefa
X
P
P
P
P
P
P
P
9
Extinguishers
P
P
P
P
P
P
P
P
10
Hose Reel
P
P
P
P
P
P
P
P
11
Yard Hydrant
X
X
P
P
X
P
X
P
12
Down Comer
X
P2
X
X
X
X
X
X
13
Wet Riser
X
X
P2
X
P4
P
P5
P
14
Fire Detection System
X
P
P
P
P3
P
P
P
15
Automatic Sprinkler System
S
S
FS
F S7
S
FS
S8
FS
16
Under Ground Tank
X
X
P
P
P3
P
P8
P
17
Over Head Tank
P
P
P
P
P
P
P
P
18
Fire Pumps
X
X
P
P
P4
P
P8
P
19
Booster Pumps
P
P
P
X
P
X
P
X
20
Auto D.G. Set
P
P
P
P
P
P
P
P
21
MCB/ELCB
P
P
P
P
P
P
P
P
22
Hose Boxes
X
P
P
P
P4
P
P
P
23
Fireman's Grounding Switch
P
P
P
P
P
P
P
P
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019
Annexure B II
Annexure & Appendices
Annexure “B-II” (Contd.)
Fire Protection Requirements for Buildings in Zone-II Category
Sl No.
Measures
Group-E: Business E1 E2 E4
Group : F Mercantile
Group-G: Industrial G2
VII
VIII
IX
X
XI
XII
XIII
XIV
XV
1
Access
P
P
P
P
P
P
P
P
P
2
Means of Escape
P
P
P
P
P
P
P
P
P
3
Compartmentation
P
P
P
P
P
P
P
P
P
4
Refuge Area
X
X
X
X
X
X
X
X
X
5
Emergency Lights
P
P
P
P
X
X
P
P
P
6
Exit Signs
P
P
P
P
X
X
P
P
P
7
PA System with Talk Back Facility
X
P
P
X
X
X
X
X
P
8
Moefa
X
P
P
X
X
X
P
P
P
9
Extinguishers
P
P
P
P
P
P
P
P
P
10
Hose Reel
P
P
P
P1
P
P
P
P
P
11
Yard Hydrant
X
P
P
X
X
X
X
P
P
12
Down Comer
P3
X
X
X
X
X
P4
X
X
13
Wet Riser
X
P
P
X
X
X
X
P6
P
14
Fire Detection System
P3
P
P
X
X
X
X
X
P
15
Automatic Sprinkler System
S
S
FS
S
S
S
S
FS
FS
16
Under Ground Tank
X
P
P
X
X
P9X
P10
P
P
17
Over Head Tank
P
P
P
P1
P
P
P
P
P
18
Fire Pumps
X
P
P
X
X
X
X
P
P
19
Booster Pumps
P
P
P
P1
P
P
P
P
P
20
Auto D.G. Set
P
P
P
X
X
P
P
P
P
21
MCB/ELCB
P
P
P
P
P
P
P
P
P
22
Hose Boxes
P3
P
P
X
X
X
P
P
P
23
Fireman's Grounding Switch
P
P
P
P
P
P
P
P
P
12
Down Comer
X
X
P
P2
X
X
X
X
X
X
X
13
Wet Riser
X
P
P
X
P
P
X
X
X
P5
P
14
Fire Detection System
P7
P
P
P2
P8
P9
X
X
X
P
P
15
Automatic Sprinkler System
S7
FS
FS
S
S
FS
S
S
S
S
FS
16
Under Ground Tank
P7
P
P
X
P
P
X
X
P10
P11
P
17
Over Head Tank
P2
P
P
P
P
P
P5
P
P
P
P
18
Fire Pumps
P11
P
P
X
P
P
X
X
X
P5
P
19
Booster Pumps
X
X
X
P
X
X
P12
P
P
P
P
20
Auto D.G. Set
P7
P
P
P
P
P
X
X
P
P
P
21
MCB/ELCB
P
P
P
P
P
P
P
P
P
P
P
22
Hose Boxes
P
P
P
P2
P
P
X
X
X
P5
P
23
Fireman's Grounding Switch
P
P
P
P
P
P
P
P
P
P
P
Legend for Appendix “B-II”
I. Height less than 15 m and area up to 300 sqm on each floor.
II. Height less than 15 m and area above 300 sqm up to 1000 sqm on each floor.
III. Height less than 15 m and area above 1000 sqm on each floor.
IV. Height 15 m and above.
V. Height less than 15m.
VI. Height 15 m and above up to 30 m.
VII. Height less 15 m
VIII. Height 15 m and above up to 24 m.
IX. Height more than 24 m
X. Height less than 15 m and plot area up to 750 sqm
XI. Height less than 15 m and plot area less than 250 sqm
XII. Height less than 15 m and plot area 251 sqm and above up to 500 sqm
XIII. Height less than 15 m and plot area 501 sqm and above up to 1000 sqm
XIV. Height less than 15 m and plot area more than 1001 sqm
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh Arunachal Pradesh Building Byelaws 2019
Annexure B II
Annexure & Appendices
XV. Height above 15 m and up to 18 m
P to be Provided.
X not to be Provided.
S Sprinklers to be provided if basement area is 200sqm or more
FS Fully Sprinklered.
To be provided if building is more than one floor.
To be provided in buildings above two floors.
To be provided if the building is more than ground floor, first floor and covered area exceeds 1500 sqm
To be provided if building is more than first floor and the covered area exceeds 300 sqm.
To be provided for more than storeyed buildings and above.
To be provided if building is ground floor, first floor and above.
Buildings to be fully sprinklered if height exceeds 15m.
157
To be provided if seating capacity exceeds 1000 persons.
25,000 lt. capacity underground tank to be provided.
50,000 lt. capacity a ground tank to be provided if riser is not provided.
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh Arunachal Pradesh Building Byelaws 2019
Annexure B III
Annexure & Appendices
Annexure “B-III”
Fire Protection Requirements for buildings in Zone-III Category
Sl.N o.
Measures
Group F mercantile(F2,F3)
Group G Industrial (G3)
Group H Storage
Group J Hazardous
H<15mA>750M2
H>15 m
UGS
I
II
III
IV
H<15mSingle Storey
H<15mMore than one Storey
H<15 m Single Storey
H<15m More than One Storey
1
Access
P
P
P
P
P
P
P
P
P
P
P
2
Means of Escape
P
P
P
P
P
P
P
P
P
P
P
3
Compartmentation
P
P
P
P
P
P
P
P
P
P
P
4
Refuge Area
X
X
X
X
X
X
X
X
X
X
X
5
Emergency Lights
P
P
P
X
P
P
P
X
P
P
P
6
Exit Signs
P
P
P
X
P
P
P
X
P
P
P
7
PA System with talk back facility
P1
P
P
X
X
X
X
X
X
P
P
8
Moefa
P1
P
P
X
X
X
P
X
X
P
P
9
Extinguishers
P
P
P
P
P
P
P
P
P
P
P
10
Hose Reel
P
P
P
P
P
P
P
P
P
P
P
11
Yard Hydrant
P
P
P
Legend for Annexure "B-III"
U.G.S.
Under Ground Shopping complex
i)
Height less 15 m shopping complex
ii)
Height less 15 m and plot area 251 sqm and above up to 500 sqm
iii)
Height less 15 m and plot area 501 sqm and above up to 1000 sqm
iv)
Height less 15 m and plot area more than 1001 sqm
P
To be provided
X
Not to be provided.
S
Sprinklers to be provided if basement area is 200 sqm or more.
FS
Fully Sprinklered.
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019
Annexure B III
Annexure & Appendices
To be provided in building of more than one floor.
To be provided if covered area exceeds 1000 sqm
To be provided in building above two floors.
To be provided in buildings if covered area is more than 200 sqm
50,000 lt. capacity underground state water storage tank to be provided.
1, 00,000 lt. capacity underground state water storage tank to be provided.
2, 00,000 lt. capacity underground state water storage tank to be provided.
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019||
Annexure C
Annexure & Appendices
Annexure “C”
Water Requirement Criterion: Unless otherwise specified in Annexure B, water requirement for fighting in different categories of occupancies shall be based on following.
Occupancy Category
Sprinkler Design
Sprinkler Design
Max. area coverage/
No. of House Streams*
Duration of Discharge (Min.)
Discharge Density (lt./min/sq.mt.)
Area (sq.mt.)
Sprinkler (sq.mt.)
Fully other Sprinkled
Fully Sprinkled
Wet Riser Sprinkled
LEVEL-I
02.5
084
21
2
4
45
45
LEVEL-II
05.0
360
12
3
6
60
90
LEVEL-III
10.0
225
09
3
6
90
90
Note: The discharge through a standard hose stream shall be taken as 567 lt./min.
Estimation of Total Water Requirements Fully Sprinklered Buildings
Occupancy Category
Sprinkler (lt.)
Riser (lt.)
Total (lt.)
Wet Riser cum Down Comer (lt.)
LEVEL-I
9,450
51,030
60,480(60,000)
1,02060(1,00,000)
LEVEL-II
1,08,000
1,02,060
2,10,060(2,00,000)
2,04,120(2,00,000)
LEVEL-III
2,02,500
1,02,060
3,04,560(3,00,000)
3,06,180(3,00,000)
3. Water Storage Tanks
The design of the water storage tanks shall be as laid down in National Building Code of India.
The capacity of underground water storage tank shall not be more than 85% of the total water requirement.
The capacity of overhead tank shall not be less than 15% of the total water requirement.
The entire water requirement can be provided in overhead tanks and pumping requirements shall be finalized in consultation with Chie Fire Officer.
Under ground water storage tank shall not be provided in the setback areas.
Storage Requirements
Occupancy Category
Under Ground Static Tank
Over Head Tank
Fully Spkd. (lt.)
Riser (lt.)
Fully Spkd. (lt.)
Riser (lt.)
LEVEL-I
50,000
85,000
10,000
15,000
LEVEL-II
1,70,000
1,70,000
30,000
30,000
LEVEL-III
2,50,000
2,50,000
50,000
50,000
4. Riser/Down comer
The size of the riser/ down comer shall be such that velocity of flow does not exceed 5m/second subject to a minimum of 100 mm. diameter.
The number of riser/down comer shall be calculated on the basis that if 30 m of delivery hose is laid, it reaches the farthest comer of the remotest compartment on the floor.
The riser/down comer shall be provided in the staircase/staircase lobby in such a manner that it does not obstruct the means of escape.
Only single headed hydrants shall be used on the riser/down comer.
Annexure C
Annexure & Appendices
The size of hose to be provided with the internal hydrants shall be 50 mm diameter and with 63 mm diameter instantaneous male/female couplings.
Diffuser branch shall only be provided in the hose boxes.
In case of partially sprinklered building tapping from the wet riser is permitted for sprinkler feed.
In case of fully sprinklered building separate rising mains and pumps shall be used for sprinkler system and wet riser.
5. Selection of Pumps
Pumping requirement shall be met by a single pump or combination of pumps.
If more than one pumps are installed to meet the pumping requirement they shall be so arranged that they come into operation one after another depending upon fall in pressure in the mains and the combined pumping capacity shall be 20% more than the actual pumping capacity needed.
Jockey pump shall be selected to give minimum 3% and maximum 5% of aggregate pumping requirement at the same pressure to that of the main pump subject to maximum discharge of 450 LPM.
Standard pumps shall only be used having discharge capacity as 1800 LPM, 2280 LPM 2850 LPM & 4550 LPM.
The pump shall be capable of giving the pressure as shown in the table below:
Occupancy Category
Pressure* At Terrace Level
Fully Spkd. (Kgf./Cm2)
Riser(Kgf./Cm2)
LEVEL-I
3.5
3.5
LEVEL-II
3.5
5.5
LEVEL-III
5.5
7.0
* Orifice plates shall be installed at the hydrants on rising mains / yard hydrants to ensure that the pressure does not exceed 7 Kgf./Cm2.
Annexure D
Annexure & Appendices
Form for Application to Erect, Re-Erect and Extension of a Building or to make Material Alteration in part of the Building
To
Chief Town Planner/Director Town Planning & ULBs
Government of Arunachal Pradesh
Mowb – II, Itanagar
Sir,
I hereby give notice on behalf of Shri that the owner intends to erect, re-erect and extend or make alteration in part of the building in Plot No. Dag No. Map sheet No./… Allotment No. /LPC No. Locality/Area/Sector . Purpose of Allotment Ward No situated at in accordance with the APBBL 2019 and I forward herewith, the following plans and specification duly signed by me and by the owner.
Location Plan (showing landmark)
Site Plan– showing the details of position and setbacks.
Building Plans, Elevations and Sections.
Service Plan
Parking and Circulation Plan.
Landscape Plan and Open Space - wherever required.
Structural Drawings
Heating Ventilation Air Conditioning (HVAC) Plan - wherever required.
General Specifications (in attached form)
Ownership Title (Allotment/LPC)
2 Nos of recent photographs of the applicants
Other Documents: -
(i) NOC from PHE Department
(ii) NOC from Power Department
(iii) NOC from Highway Department (wherever required)
(iv) NOC from Disaster Management Department (wherever required)
(v) ECBC NOC from APEDA – (wherever required)
(vi) NOC from Fire Department – (wherever required). Fire Safety Design as required in National Building Code duly approved by the Director Fire Service. Alternatively, an undertaking to the effect that Fire Safety Plans duly approved shall be submitted along with the application.
The building plan has been prepared strictly as per the approved building Byelaws and relevant IS Codes / provisions of NBC. The construction shall be carried out in accordance with the building plan and I shall be completely accountable for any lapse on my part up to within 6 months after obtaining completion certificate of the building.
Statement of Proposal and Certificate (By the Owner and Registered Architect/Engineer/Town Planner)
Classification of the Proposal of Building …… (New Erection / Re-erection /Extension/Alteration)
Classification of Building Utility… (Residential/Commercial/Institutional/Health/PSP/Industry)
Total Area of Plot (in sqm)…
Geographical Coordinates of Building Location : - Northing -
: - Easting -
5. Built-up Area Statement
Description
Proposed (area inSqm).
Permissible (Sqm)
Remarks
Max. Ground coverage
Basement
Ground Floor
First Floor
Second Floor
Third Floor
Total Floor area
Floor Area Ratio
No. of Dwelling Units
Height of the Building (in meters)
Setbacks of the Building (in meters)
Proposed (in meters)
As per approved Layout Plan
Remarks
Front
Rear
Left
Right
6. Parking Standard
Equivalent Car Space @ 1.5 ECS in plot size 100 to 300 sqm 2.5 ECS in plot size 301 to 500 sqm and 1 additional ECS in every 100 sqm
Open Parking @ 18 sqm per ECS
Ground Floor covered parking @ 28 sqm per ECS
Affidavit-cum-Undertaking
(Affidavit of Competent Professional on Rs. 100/- Non-Judicial Stamp paper of specified amount to be attested by Notary Public/Metropolitan Magistrate)
son of Architect/ Engineer/ Town Planner by profession having office at……… . Do hereby solemnly affirm and declare as under:-
That I am a Licensed Architect/Engineer/Town Planner duly registered with the Authority vide registration No. …
That I have been engaged as a Competent professional as per Appendix ‘E’ of the AP Building Bye-Laws for preparing the building plans and to supervise construction in respect of Plot No/ LPC No Locality
That I have prepared the building plans in respect of the aforesaid plot.
That I have studied the layout plan of the colony and gone through the instructions, policy decisions and other relevant documents in respect of the plot and colony.
That I have personally inspected the site. The plot under proposal forms part of the approved layout plan with respect to its location, size shape and area of the plot and proposed land use is also in conformity with the approved layout plan. The plot has been demarcated at site and the size, shape and area of plot available at site tallies with the approved layout plan.
That the ownership documents are in the shape of registered sale-deed/lease-deed in favour of the applicants and have been thoroughly examined and the ownership in favour of the applicant is in order.
That there is no construction in existence at the plot and no construction shall be started before sanction of the building plans.
That there is no encroachment on the Govt. Land/ Municipal land/Road (including RoW) /other property and road widths as shown in the layout plan are available at site.
That the proposal are in conformity with the terms and condition of lease deed which is still valid and period of construction as per lease-deed and the extension granted by the lessor is valid up to…
That the proposal have been prepared strictly in accordance with the Building Bye-laws rules regulation and practice of the department and no misinterpretation on inference of provision of Building Bye-Law has been done while preparing the plans. The construction shall be carried out strictly in accordance with the sanctioned building plans and in case any deviation is carried out, I shall inform the concerned Authority within 48 hours.
Building Permit/Sanction
File No…
Dated…
To
Subject: Sanction u/s…
Dear Sir/Madam,
With reference to your application No. ……. dated…… for the grant of sanctionto erect/re-erect/extend the building or alteration in the building to carry out development specified as per said application: -
i) Govt. Land Allotment Order /LPC No ……… ii) Plot/Dag No. …...iii) Map/Sheet No. ……….iv) Area of Plot: ….. v) Ward No:…… vi) Sector/locality
a) Purpose of Building Utility: ……….. b) Particulars of the Building: - i) FAR: ……….; ii)Ground Coverage …..; iii) Setbacks: a) Front: …m; b) Left: …..m; c) Right: …..m; d)Rear: ………m;iv)Building Height:……… v) No. of Floors:……. vi) Basement Floors: ……
I have to state that the Authority subject to the following conditions and correction done in the plans has sanctioned the same on the …
The plans are valid up to …………………day……………Months………. year ……………
The construction will be undertaken as per sanctioned plan only and no deviation from the bye-laws will be permitted without prior sanction. Any deviation done against the bye-laws is liable to be demolished and the supervising Architect engaged on the job will run the risk of being black listed.
Violation of building bye-laws will not be compounded.
It will be the duty of the owner of the plot and the Architect preparing the plans to ensure that the sanctioned plans are as per prevalent Master Plan/Zonal Plan/Building Bye-laws. If any infringement of bye-laws remains unnoticed, the concerned Authority reserves the right to amend the plans as and when infringement come to the notice and concerned Authority will stand indemnified against any claim on this account.
A notice in writing shall be sent to Authority before commencement of the constructions of the building as per byelaws. Similar notice will be sent to Authority when the building has reached up to plinth level.
The owner shall not occupy or permit to occupy the building or use or permit to use the building or any part thereof affected by any such work until occupancy certificate is issued by the concerned Authority.
Concerned Authority will stand indemnified and kept harmless from all proceedings in court and before other authorities of all expenses /claims which the concerned Authority may incur or become liable to pay as a result or in consequences of the sanction accorded by it to these building plans.
Information for Intimation of Completion of Work up to Plinth Level
To
The Chief Town Planner/Director Town Planning & ULBs
Govt. of Arunachal Pradesh
Itanagar
Sub: Information for Intimation of Completion of Work up to Plinth Level
Sir,
The construction up to plinth/column up to plinth level has been completed in Building No…………… on/in Plot No……………… Sector/Colony ……………………Ward… ……………in accordance with your permission No…………………..dated………………..under my supervision and in accordance with the sanctioned plan.
Yours faithfully,
Signature of Licensed Architect/Engineer/Town Planner/Supervisor
Name…
(In Block letters)
Address:…
.………………………………………………………
Date:…
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh||Arunachal Pradesh Building Byelaws 2019|
Appendix “A-11”
Annexure & Appendices
Appendix “A -11” (Bye laws: 2.15.3)
Inspection Report
…working as a with have carried out the inspection of Building No ..on/in Plot No Scheme No. ….Road/Street …ward.. in accordance with permission No… ...dated… .The following deviation from the sanctioned plans have been noticed which are against the provision of Master Plan / Bye-laws are of non-compoundable nature.
You may not proceed with further work till such time the deviations made are rectified and construction brought in conformity to sanction plans.
Yours Faithfully
For…
Competent Authority
Office No……
Office Stamp……………
Date…
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh||Arunachal Pradesh Building Byelaws 2019|
Appendix “A-12”
Annexure & Appendices
Appendix “A-12” (Bye laws: 2.16)
Form of Notice of Completion
(To be submitted along with prescribed fee for notice of completion and other relevant documents)
To
The
…Authority,
Technical Aspects and Options of Rain Water Harvesting in Built Forms and Open Spaces
Introduction
The storage of rain water on surface is a traditional technique and the structures used were underground tanks, ponds, check dams, weirs etc. Recharge to ground water is a new concept of rain water harvesting and the structures generally used are:-
a. Pits: Recharge pits are constructed for recharging the shallow aquifer. These are constructed 1 to 2m, wide and to 3m deep which are back filled with boulders, gravels, coarse sand.
b. Trenches: These are constructed when the permeable stream is available at shallow depth. Trench may be 0.5 to 1m. wide, 1 to 1.5m deep and 10 to 20m long depending up availability of water. These are back filled with filler materials.
c. Dug wells: Existing dug wells may be utilized as recharge structure and water should pass through filter media before putting into dug well.
d. Hand pumps: The existing hand pumps may be used for recharging the shallow/deep aquifers, if the availability of water is limited. Water should pass through filter media before diverting it into hand pumps.
e. Recharge wells: Recharge wells of 100 to 300 mm. diameter are generally constructed for recharging the deeper aquifers and water is passed through filter media to avoid choking of recharge wells.
f. Recharge Shafts: For recharging the shallow aquifer which are located below clayey surface, recharge shafts of 0.5 to 3 m. diameter and 10 to 15 m. deep are constructed and back filled with boulders, gravels & coarse sand.
g. Lateral shafts with bore wells: For recharging the upper as well as deeper aquifers lateral shafts of 1.5 to 2 m. wide & 10 to 30 m. long depending upon availability of water with one or two bore wells are constructed. The lateral shafts are back filled with boulders, gravels & coarse sand.
h. Spreading techniques: When permeable strata start from top then this technique is used. Spread the water in streams/nallah by making check dams, nallah bunds, cement plugs, gabion structures or a percolation pond may be constructed.
Procedure for Installation Rain Water Harvesting
The following provisions shall be applicable for installation of Rain Water Harvesting Structures
Annexure \"D\" (Byelaws 11.2.3)
Questionnaire for High Rise Buildings/Other Buildings Fire Service Headquarters
1.Name of the building
2.Address of the building
3.Name and address of builder/promoter
4.Name and address of owners /occupiers of individual flats
5.Plot area
(a) Title
(b)Land use (in case of residential building indicate no. of dwelling units..
6.Covered Area (at grade level)
7.Height of tile building
8.a) Overall height (from grade level up to terrace level )
b) Whether set back areas are conforming to unified building bye-laws
9.a) Number of Basement(please indicate level below grade in each case) b) If basement extends beyond the building line, please indicate the load bearing strength of the roof of basement) c) Area of the basement d) Whether any piazza is proposed? if so, details of the level of piazza and ramp etc. be indicated
10.Number of floors (including ground floor)
11.Occupancy use (please mention separately, use for basement and floors)
12.Covered area of typical floor
13.Parking areas (please give details)
14.Details of surrounding properties / features
Compass direction in relation to the building | Type of Property/feature | Height in case of building | Distance wall to wall from building | Any other information
North | | | | | |
East | | | | |
West | | | | |
South | | | | |
Approach to proposed building width of the road and connecting roads, if any............
Please give details of water supply available exclusively for the fire fighting............
Has wet riser(s) been provided? If so, please indicate the number of risers and internaldia of each ........:
4.4.7Aesthetics.
5 Awareness of Stakeholders:
5.1 Publication of Rain Water Harvesting guidelines and conduct awareness campaigns, Orientation programmes, etc. for various stakeholders (Bulk consumers, residents, etc).
5.2 To construct model demonstration project for public building, educational institutions, parks, open spaces, etc on rain water harvesting to disseminate the idea to various stakeholders.
6 Prohibition on digging of new tube wells/bore wells. Proper enforcement of such prohibition is required to be monitored at higher level and permission may only be given in exceptional circumstances.
6.1 Power of Development Authorities to use any discarded or dead tube well as recharge pit or percolation pit. The Authority may provide or cause to be used any discarded or dead tube well for use as percolation pit for any locality or for use as community Rain Water Harvesting System.
6.2 The department will prepare a list of all government buildings, which do not have rain water harvesting facilities. Such buildings will be served notices and they will be directed to implement the new structural designs at the earliest.
7 Incentives and disincentives mechanism shall be designed to facilitate the implementation of Rain Water Harvesting like rebate/fine in property tax etc.
8 Responsibility of the household -It shall be designed to facilitate the implementation of Rain Water Harvesting structure that in no case polluted or waste water is let into the recharge pit as it will lead to pollution of the ground water.
9 Penalty:
9.1 Any person found violating clause no. 8 shall be punishable as per section 35 of the Arunachal Pradesh Urban and Country Plan Act 2007.
9.2 Occupancy certificates will not be issued to the owners of the buildings unless they produce satisfactory proof of compliance of installation of rain water harvesting.
9.3 The Authority shall impose fine for the failure of the owner / builders of any building to install or to maintain Rain Water Harvesting structures depending on the residential area.
9.4 The state government may levy incremental penalty on erring property owners/builder. The rain water harvesting unit is must in houses built on sites of 100sq.m or more. The rule applies to properties built in the year 2019 or earlier. The penalty for the first three months is 25% of the water bill. From the fourth month the penalty becomes 50% of the water bill, which after six months becomes equivalent to water bill.
Form for Certificate of Architect/Engineer/Town Planner (To be submitted along with notice of completion)
To
The Chief Town Planner/Director Town Planning & ULBs Govt. of Arunachal Pradesh, Itanagar
Dear Sir,
We hereby certify that the erection, re-erection, extension or material alteration in the building No… ………..on in Plot No……. Locality/Sector/ Colony… .situated at……………...has been supervised by me and has been completed on according to the plans sanctioned, vide office communication No………………. dated
..The work has been completed to our best satisfaction, the workmanship and all the materials (type & grade) have been used strictly in accordance with general and detailed specifications. All the drainage/Sanitary/Water Supply work has been executed under our supervision and as per Building Bye-laws. No provisions of the Building Bye-laws and condition prescribed or order issued there under have been transgressed in the course of the work. The building is fit for use for which it has been erected /re-erected or altered/constructed and enlarged.
Certificate:
i) Certified that the building(s) has been constructed according to the sanctioned plan and structural design (one set of structural drawings as executed is enclosed) which incorporate the provisions of structural safety as specified in relevant prevailing NBC Part 6 and IS codes standards/Guidelines.
ii) Further certified that water harvesting as well as waste water re-cycling systems have been provided as per the sanctioned building plan.
iii) It is also certified that construction has been one under our supervision and guidelines and adheres to the drawings submitted and the records of supervision have been maintained by us.
Permission to occupy of use the building may be granted.
Any subsequent change from completion drawings will be the responsibility of the owner(s)
a) Signature of the owner with date
b)Signature of the Architect/Engineer with date
Name in Block letters
Name in Block letter, Licence No.
Address
Address
Signature of the Structural Engineer with date (for certificate 1) (as defined in NBC of India)
Form of Rejection or Compliance in Respect of Occupancy Certificate
File No Dated:…
Sh/Smt…
Subject: Occupancy Certificate in respect of Plot No…
Dear Sir / Madam,
With reference to your letter dated
With reference to your notice of completion dated
In continuation of this office letter of even No… .dated on the subject noted above, I am directed to inform you that your case bas been examined and occupancy certificate is rejected for the reasons as given below:-
Yours faithfully
Director of Town Planning & ULBs Itanagar
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh||Arunachal Pradesh Building Byelaws 2019|
Appendix “A-16”
Annexure & Appendices
Certificate of Structural Safety
Appendix “A-16” (Bye laws: 6.1.2)
To
The Director, Town Planning and ULBs Government of Arunachal Pradesh Itanagar
I am a Registered Structural Engineer (RSE). This is to certify that I have been appointed as the Structural Engineer on record to prepared the Structural Design Basis Report, detailed structural and detailed structural drawings for above mention project. I am fully conversant of my duties and responsibilities under the Regulations and assure that I shall fulfill them in all respects.
I have prepared and signed a structural design and prepared detailed structural drawings of the proposed buildings as per the latest Indian Standard Specifications, and as indicated in the Structural Basis Design Report.
Form NO. 13 Building Completion Certificate {by Construction Engineer on Record}
Reference No.
Owner’s Name: …… ... Location :
Submitted on : ..Received on : …
To
Sir,
The Director Town Planning and ULBs Government of Arunachal Pradesh Itanagar
The building/s has/have been constructed according to the sanctioned plan –
The building/s has / have been constructed as per - the detailed structural drawings and structural specifications prepared by the Structural Engineer on Record – the detailed Architectural drawings and Architectural specifications prepared by the Architect on Record. - detailed drawings and specifications of all services
All materials used in the construction have been tested as provided in specifications and a record of test reports has been kept
Signature of the Owner .... Signature of Construction Engineer on Record ....
Date: .... Date: ....
Name in block letter: .... Name in block letters: ....
Address: .... Address: ....
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh||Arunachal Pradesh Building Byelaws 2019||
Appendix “A-19”
Annexure & Appendices
Appendix “A-19” (Bye laws: 6.1.6)
Form NO. 14 Building Completion Certificate {by Structural Engineer on Record}
Reference No. …
Owner’s Name: … ... Location :
Submitted on : ..Received on :
The Director Town Planning and ULBs Government of Arunachal Pradesh Itanagar
This is to certify that detailed structural drawings of the buildings/s has / have been prepared on the basis of a detailed analysis and a detailed design carried out according to relevant previsions of the latest Indian Standard Codes, National Building Code and as indicated in the structural design basis report.
Signature of the Owner .... Signature of Structural Engineer on Record
................
Date: ............ Date:
................
Name in block letter: .... Name in block letters: ....
Address: .... Address: ....
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh||Arunachal Pradesh Building Byelaws 2019||
Appendix “A-20”
Annexure & Appendices
Appendix “A-20” (Bye laws: 6.1)
Certificate of Structural Engineer Inspection Report
(This form has to be completed by registered Structural Designer after his site inspection and verification regarding of all recommendation by the owner, which in the option of the registered structural designer are necessary for safety of the structure).
(I) Description by title and location of the property including, T.P. No., F.P. No. etc.
(II) Name of Present owner:
(III) Description of the structure:
Class I or Class II (Briefly describe the property in general and structure in particular)
(A) Function (B) Framed construction
Residential(with or without shop)
Apartment withor withoutshops
OfficeBuildings
ShoppingCenters
SchoolColleges
Hostel
Auditoria
Factory
1
2
3
Affidavit/Undertaking (For Handing Over Land Required For Road Widening)
That I/We have submitted building plans for construction of building on plot No………….. Sector/ Colony… located at… ……to the under Sanction… … of the … ….. APBBL 2019 for favour of sanction.
I/We undertake to hand over the land required for road widening as shown on site plan to concerned Authority free of cost as and when asked by …to do so.
I/We have already understood that the……………………is granting sanction on the basis of my undertaking.
If I/We fail to do so, the sanction so accorded shall be revoked and construction done as consequence thereof shall be deemed to have done unauthorisedly and shall be actionable u/s …………..of the ….Act.
Deponent
Verification
I/We verify that the contents of the above undertaking are correct to the best of my knowledge and belief and nothing material has been concealed there from.
DEPONENT
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019||
Appendix “B-I”
Annexure & Appendices
Appendix “B-1” (Bye laws: 2.9.4. iv)
Indemnity Bond for Basement
This
Indemnity
Bond
is
executed
by
Shri/Smt
S/o,
D/O,
W/O
Shri/Smt
R/O
.in favour of Director Town Planning & ULBs.
Whereas the executant has submitted to the concerned Authority the plans for, sanction of basement over Plot No………………… under the provisions of the Act and lie bye- laws made there under:-
And whereas the concerned Authority has agreed to sanction the aforesaid construction subject to the conditions that the owner shall indemnify the concerned Authority in the event of any loss or damage being cause to the adjoining building on account of the construction of the said basement either at the time of digging of its foundations or in the course of its construction or even thereafter and also against any claim of any concern thereto.
Performa to BE Submitted by Owner
Name, Status, and Address of the applicant
Name of the Architect and address with Registration number with Council of Architecture.
Details of the property/plot a) Location b) Boundaries c) Area in sq.mt. with dimensions (net plot area) d) Width of the roads
Land use a) Master Plan b) Zonal Development Plan c) Approved Layout Plan
a) Free Hold
b) Leasehold under notification for acquisition if lease hold permission of lessor for construction under the leasehold condition obtained.
c) Whether under acquisition, if so give details.
Whether the plot/land is affected under the Urban Land (Ceiling & Regulation) Act, 1976. If so, copy of the NCO from the concerned Authority be furnished.
Proposals a) Land Use
b) Coverage on each floor with proposed use of the floor space including basement.
c) FAR
d) Height
e) No. of floors.
f) Envelope controls/set backs
g) Parking norms
Encl:
Ownership title
Permission to construct under the lease
Permission under the Land Ceiling Act, 1976.
199
Site/Location Plan
Tentative proposals to explain the scheme
Signature of Architect
Signature of the owner
Name…
Name…
Reg. No…………
Address…
Address…
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019
Appendix “D”
Annexure & Appendices
Appendix “D” (Bye laws: 4.32.2)
Number and Type of Lifts Required for Different Occupancies and Space for Electrical Installations
The number and type of lifts required depending on the capacity of lift, desired speed nature of operation are as given in table below:
Table: Number and types of lifts for non-residential Multistoried Building
Sl. No.
No. of floors
Capacity of lifts in person
Speed m/s
No. of persons that can be carried by a lift
In 6 min
In 30 min.
In 50 min.
In 60 min.
Manually Operated
Automatic
Manually Operated
Automatic
Manually Operated
Automatic
Manually Operated
Automatic
1
2
3
4
5
6
7
8
9
10
11
12
1
7
6
0.6-0.75
17
-
102
-
170
-
204
-
2
7
8
0.6-0.75
22
-
132
-
220
-
-
-
3
7
10
0.6-0.75
26
-
156
-
260
-
312
-
4
7
10
1.0
30
-
180
-
300
-
360
-
5
7
13
1.0
37
-
122
-
370
-
444
-
D.2.0 Spaces for Electrical Installations
The spaces required for different electrical installations are given at 3.1 to 3.3 D.2.1 Electric Sub-station – The norms given in 3.1.1 and 3.1.2 shall be adopted for provision of space for sub-station. D.2.1.1Area Requirements for Sub-Station for buildings
Sl.No.
Total covered Area (sqm)
Transformer Capacity (KVA)
S/Stn. Size Required (sqm)
1
2500
1 X 400
70
2
4500
1 X 630
70
3
8000
2 X 630
100
4
10,000
2 X 630
130
5
15,000
4 X 630
160
6
20,000
5 X 630
175
7
25,000
6 X 630
200
8
30,000
7 X 630
220
Note
For additional 1000 sq.mt. covered area, a load of 90 KVA will come up with 150 KVA TR. Capacity at 60 % loading.
For additional of one transformer as per covered area, a space of additional 16 sq.mt. is to be provided.
In case of any deviation in space size due to unavoidable circumstance, the same may be considered with the approval of Electricity Board.
The floor of the sub-station shall have cable trenches of 0.6 mt. depth, the layout for which will be given at the time of actual construction. For this purpose, a dummy floor of 0.6 mt. depth shall be provided to facilitate cutting/digging of floor for installation of equipment’s and making subsequent changes in trenches. This floor shall be capable to withstand minimum load of 10 tones of each transformer mounted on flour wheels.
The break-up spaces required for different installations in a sub-station are given as below:
Supply company’s Switchgear room and or space of meters.
Transformer Rooms: The number and size of transformer rooms shall be ascertained from the total power requirements of the company. To determine the size of transformer and clearance around a transformer, reference may be made to good practice (I.S.1887-1967 code of practice for installation and maintenance of Transformer). A 500 KVA transformer may be provided with a minimum space of 4 mt. X 4 mt. If transformer is to be installed outdoor space shall be provided on similar considerations and adequate provision for safety enclosure is to be made. For transformer having large oil content (more than 2000 lt.) soak pits are to be provided in accordance with rule 64 of Indian Electricity Rules, 1956.
High Voltage Switch Rooms: In case of sub-station having one transformer, the owner is required to provide only one high voltage switch. In the case of single point supply for two transformers, the number of switches required is 3 and for ‘n’ transformers the number of switches is n+1. The floor area required in case of a single switch will be roughly 4 mt. X 1mt. and for every additional switch the length should be increased by 1mt.
Low Voltage Switch Rooms: The floor area requirement in respect of low voltage switchgear room cannot be determined by any formula.
Room for Stand-by-Generator: A room space not less then 6 mt. X 9 mt. may be provided for housing a standby Generator set of 50 KW.
D.2.1.1.A: Location of electric sub-station in basement of multistoried buildings:
D.2.1.2. Other Requirements for Sub-station
The sub-station will preferably be located on the ground level failing which it can be in the basement floor in no case at higher level.
The entire space will be provided at one floor in continuation.
The minimum width of the sub-station space shall not be less than 6 mt.
The areas given above in respect of the different categories of rooms hold good if they are provided with windows and independent access doors.
All the rooms should be provided with partition up to the Ceilings and shall have proper ventilation. Special care should be taken to ventilate the transformer rooms and where necessary, louvers at lower levels and exhaust fans at higher level shall be provided at suitable locations.
In order to prevent storm water entering the transformer and switch rooms through the soak pits, the floor level of the sub-station shall be at least 15 cm above the highest flood water level that may be anticipated in the locality.
D.2.2 Cable Trenches Shafts Etc.
D.2.2.1 Suitable number of vertical shafts, rising mains, distribution boxes, etc. shall also be provided as per the requirements at suitable location. Cable trenches with suitable handy covers for entry of the cables up to the substation onwards up to the street adjoining other building shall also be provided as per the requirements. These vertical shafts, rising mains, distribution boxes, cable trenches, etc. shall be so constructed as to be accessible only to authorized personnel. The rising mains and other installations in
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019
Appendix “D-2”
Annexure & Appendices
the vertical shafts, tap off boxes distribution boxes etc. required at each floor shall be provided, installed and maintained by the owner at their own cost.
Adequate enclosed space shall also be provided at each floor for installation of equipment’s for distribution on respective floors such as distribution boxes, cut-out, and meter boxes and main switches.
D.2.2.2 Location of Switch Room: In large installations other than where a sub-station is provided, a separate switch room shall be provided. This shall be located as closely possible to the electrical load center and suitable ducts shall be laid with minimum number of bends form the point of entry of the supply to the position of the main switchgear. The switch room shall also be placed in such a position that rising ducts may readily be provided there from to the upper floors of the building in one straight vertical run. In larger building, more than one rising duct and horizontal ducts may also be required for running cables from the switch room to the foot of each rising main. Such cable ducts shall be reserved for the electrical services only, which may, however, include medium and low voltage installations, such as call bell systems. Telephone installation should be suitably segregated.
D.2.2.3 Location and Requirement of Distribution Panels: The electrical gear distribution panels and other apparatus, which are required on such floor may conveniently be mounted adjacent to the rising mains, and adequate space should be provided at each floor for this purpose.
D.2.2.4 Location and Requirement of PBX/PABX Room: Information regarding provision and location of PBX/PABX room, telephone outlets and riser shall be ascertained form the relevant Authority. Adequate space should be provided for installation of Sub-Distribution Board.
1.0General
Building/Development work for which permission is sought, shall be planned, designed and supervised by registered professionals. The registered professionals for carrying out the various activities shall be:
Architect, Engineer, Structural engineer, Town planner, Landscape architect, Urban designer, Supervisor. Requirements of registration/license for these professionals by the Authority or by the body governing such profession and constituted under a statute, as applicable to practice within the local body’s jurisdiction, are given in items 1 to 7 of the following table:
(items 8-10 Plumber, Electrician and Fire Consultant may not need registration)
Sl No
Professional
Qualifications
Competence / Functions
1
Architect
Registered with valid membership of the Council of Architecture, Indiaas prescribed under Architect's Act 1972.
The registered architect shall be competent to carry out the work related to the building/development permit as given below: a.Prepare and sign all plans, sub-division/layout plans and information connected with building permit except engineering services of multistoried/ special buildings. b.Preparation of building plans, drawings and related information connected with development permit of area up to 1 hectare for metro-cities and 2 hectares for other places. c.Issuing certificate of supervision for development permit of area up to 1 hectare for metro-cities and 2 hectares for other places. (related to building layout and other architectural aspects) d.Issuing certificate of supervision and completion of all buildings pertaining to architectural aspects.
2
Engineer
Graduate in Civil Engineering from recognized Indian or Foreign University.Registeredwithvalidme mbership(Civil)oftheInstitutionofEn gineers,India.
The registered engineer shall be competent to carry out the work related to the building/development permit as given below: a.Prepare and sign all building plans, structural drawings and service plans and information connected with building permit; b.. Preparation of structural drawings, details and calculations of buildings on plot up to 500m<sup>2</sup> and up to 5 storeys or 16m in height, all service plans and related information in connected with development permit of area up to 1 hectare for metro-cities and 2 hectares for other places. c.Issuing certificate of supervision for development permit of area up to 1 hectare and 2 hectares for other places (pertaining to building layout, Building structure, civil works and service installations); d.Issuing certificate of supervision and completion of all buildings pertaining including structure and building services.
X
X
P
P
P2
P2
P
P
12
Down Comer
X
X
X
X
X
X
X
X
X
X
X
13
Wet Riser
P1
P
P
X
X
P3
P1
X
P3
X
X
14
Fire Detection System
X
P
P
X
X
P
P
X
X
P
P
15
Automatic Sprinkler System
FS
FS
FS
FS
FS
FS
FS
FS4
FS
FS
FS
16
Under Ground Tank
P
P
P
P5
P6
P7
P
P6
P
P
P
17
Over Head Tank
P
P
X
P
P
P
P
P
P
X
P
18
Fire Pumps
P
P
P
P
P
P
P
P4
P
P
P
19
Booster Pumps
X
X
X
X
X
X
X
X
X
X
X
20
Auto D.G. Set
P
P
P
P
P
P
P
P
P
P
P
21
MCB/ELCB
P
P
P
P
P
P
P
P
P
P
P
22
Hose Boxes
P1
P
P
X
P
P
P
X
P3
P
P
23
Fireman's Grounding Switch in Lifts
P
P
P
P
P
P
P
X
P
X
P
I am aware that in the event of building being constructed in violation of the sanctioned building plan approval, the Authority shall have the right to take action against me as it may deem fit including referring the matter to concerned professional and statutory councils for taking disciplinary action against me.
Signature of the Owners
Signature of Registered (Architect/
Engineer/ Town Planner)
Name of owner(s)
Address of the owner(s)
Registration No.
Empanelled No.
Address of the Architect/Engineer/
Encl: As stated above
Town Planner
Dated:
Appendix “A-1”
Annexure & Appendices
Appendix “A-1” (Bye laws 2.9.1)
Basement Total parking (sqm) @ 32 sqm per ECS
Area in sqm
Area in sqm@ 18 sqm per ECS Open Parking
Area in sqm @ 28 sqm per ECS Covered Gr. Floor
Area in sqm @ 32 sqm per Basement
Total (sqm)
1
2
3
4
5
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019||
Appendix “A-1”
Annexure & Appendices
7. Fee & Ch arges
a. Building permit fee Rs. b. Use of City Infrastructure Charges Rs. c. Additional floor space charges (provisional) Rs. d. Peripheral charges (Provisional) only for Group IV CHBS Rs e. Any other charges (please specify) Rs
Total amount (as per the details above) Rs…
Receipt No…… Dated…
We hereby certify that
The plot in question forms part of the approved layout plan and its location size and area conform to the approved layout plan and lease/sale deed/NOC of the lease Administration Branch of concerned Development Authority.
Plot is lying vacant and no construction shall be started before sanction.
The plot is free from all encumbrances (owner responsibility).
The period of construction valid up to As per the lease condition / further extension of time for construction granted by the lessor is valid up to Time construction obtained from the lease Administration Branch, Concerned Development Authority.
Size of each dwelling unit is not more than 300 sq.mt.
Signature of Owner(s)
Signature of Registered Architect
Name…
(In block letters)
Name…………
(in block letters)
Address……………
Registration No…
Address…
……………………………………
Dated:
Dated:
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh BuildingByelaws 2019|
Appendix “A-1”
Annexure & Appendices
Authority Letter
I hereby authorize Mr./Mrs.... to collect the sanction whose signature is verified below.
Specimen signature of signature of the owner(s)/Registered Architect/
Mr./Mrs...........................
Dated received.... Date .....
(Signature of authorized person / owner / Registered Architect)
Dated:.... Remark, if any....
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019||
Appendix “A-2”
Annexure & Appendices
Appendix “A-2” (Bye laws: 2.10.9)
Form for Specifications of Proposed Building Utility
The purpose (Residence, Office, Restaurant, Hotel, Dharmshala, School, Hostel Cinema, Shop, Factory Others) for which it is intended to be used…
Details of coverage on respective floor are given below:-
Sl No
Details
Existing (sqm)
Proposed (sqm)
Total
Propose of Floor (Utility)
1
Basement Floor
2
Ground Floor
3
Mezzanine Floor
4
First Floor
5
Second Floor
6
Third Floor
7
Fourth Floor
a) Approximate number of inhabitants proposed to be accommodated…
b) The number of latrines, Urinals, Kitchens, Baths to be provided…
c) The source of water to be used in the construction…
d) Distance from public sewer…
e) The materials to be used in construction Walls/Columns/Foundations/Roof/ Floors
Signature of Registered Architect/Engineer/Town Planner
Name…
Registration No…
Address………
…………………………….………………………..
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh||Arunachal Pradesh Building Byelaws 2019||
Appendix “A-3”
Annexure & Appendices
Appendix “A-3” (Bye laws: 2.10.10)
Form for Supervision
To The Chief Town Planner/Director Town Planning & ULBs Govt. of Arunachal Pradesh Itanagar Sir,
I hereby certify that erection/re-erection/extension or material alteration in the Building No…… ……on Plot No/Dag No……………… Map sheet No..…………. in Ward No.………… Locality/Sector/Colony.………
shall be carried out under my supervision and I certify that all the materials (type & Grade) and workmanship of the work shall be generally in accordance with the general specification submitted along with and the work shall be carried out according to the sanctioned plans which also included the services like drainage, sanitary, water supply, and electrical.
Signature of Registered Architect/Engineer/Town Planner
Name of Registered Architect/Engineer/Town Planner
(In block letters)
Registration No. of Architect/Engineer/Town Planner
Address of Registered Architect/Engineer/Town Planner
Empanelment Number
Dated:
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh BuildingByelaws 2019|
Appendix “A-4”
Annexure & Appendices
Appendix “A-4” (Bye laws: 2.13)
Undertaking for Payment of Other and Peripheral Charges Note: It should be on non-judicial stamp paper of specified amount attested by Notary Public / First class Magistrate.
Undertaking
I ....Son of Shri ....aged....years residents of ....Address .... owner of the above proposed Plot No./Dag No. .... Map sheet No ....do hereby undertake to pay the balance of peripheral and other charges as and when required by the concerned Authority and in this regard Authority's decision will be finally binding on me.
Executed by me as................on day of....20....
Executant
Witness:
1…………………
2…………
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh||Arunachal Pradesh Building Byelaws 2019||
Appendix “A-5”
Annexure & Appendices
Appendix “A-5”
(Bye laws: 2.9.4 viii)
That in case the owner dispenses with my services at any stage whatsoever; I shall inform the concerned Authority within 48 hours.
That the size of each dwelling unit is not more than 300 sqm.
That mandatory setbacks have been proposed and shall be maintained in accordance with the setbacks marked in the layout plan/Master Plan.
That before submission of the proposal, necessary information/clarification has been obtained from the concerned department of the concerned Authority. The plot is safe and is not affected in any scheme or the road widening. Building activities for residential use are allowed with number of storeys as per approved layout plan.
That no development/additional development/deficiency charges are payable, against this plot (in case development/additional development/deficiency charges are payable then its details be given in the separate para)
That no non-compoundable deviations shall be carried out during the course of construction.
Appendix “A-5”
Annexure & Appendices
That nothing has been concealed and no misrepresentation has been made while preparing and submitting the building plans.
That in case anything contrary to the above is found or established at any stage, the concerned Authority shall be at liberty to take any action as it may deem fit including revocation of sanction of building plans and debarring me for submission of building plans with the Authority under the scheme and also lodge a complaint with the Council of Architecture, Institute of Engineering Council or related body and ITPI, for appropriate action.
Deponent
Verification:
I the above named deponent do hereby verify at
on this… . of ……….. 20……… that contents of the above affidavit are true and correct to my knowledge. No part of it is false and nothing has been concealed there from.
Deponent
Appendix “A-6”
Annexure & Appendices
Appendix “A-6” (Bye laws: 2.14.2)
The doors and window leaves shall be fixed in such a way that they shall not, when open project on any street.
The owner will not convert the house into more dwelling units on each floor then the sanctioned.
The building shall not be constructed within minimum distance as specified in Indian Electricity Rules from voltage lines running on side of the site.
The land left open as a consequence of the enforcement of the setback rule shall form part of the public street.
The owner shall ensure that the public areas like road, parks and other public opens spaces are not used for stacking the building materials or machineries to avoid public inconvenience and nuisance.
The sanction will be void if auxiliary conditions mentioned above and other conditions whatsoever imposed are not complied.
The owner will use the premises for the use, which has been sanctioned.
The owner will not proceed with the construction without having the supervision of an Architect/Engineer as the case may be. If he\she changes his Architect\Engineer, he\she shall inform the Authority about the appointment of new Architect\Engineer within 48 hours, with a proper certificate from him.
Yours Faithfully
Encl: A set of sanctioned plan.
Appendix “A-7”
Annexure & Appendices
Appendix “A-7” (Bye laws: 2.14.2)
Form for Refusal of Building Permit
File No………… Dated: …
To
Sir/Madam.
With reference to your application No.... dated.... for the grant of sanction for the erection/re-erection/extension or alteration of building work in Plot No./Dag No. .... In Ward No. .... Locality/Sector/Colony .... I am to inform you that building permit under relevant provisions of the APBBL 2019 you application No. .... Dated .... has been refused on the following grounds.
1
2
3
4
5
Yours faithfully
Director of Town Planning & ULBs Itanagar
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019||
Appendix “A-8”
Annexure & Appendices
Appendix “A- 8” (Bye laws: 2.14.3)
Form of Revalidation
File No…… Dated…
Shri /Madam …
Subject: Revalidation of Building Plans relating to Permit No … at Plot No… Locality/Sector/Colony …. Ward No.
Dear Sir / Madam,
With reference to your application No. ……. dated…………on the subject cited above, I am directed to inform you that your building plan which were sanctioned on………….. vide file No………………..have been revalidated up to
Original sanctioned plan submitted by you is also returned herewith.
3 Please acknowledge receipt.
Yours faithfully
Director of Town Planning & ULBs Itanagar
Encl: As above.
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh||Arunachal Pradesh Building Byelaws 2019||
Appendix “A-9”
Annexure & Appendices
Appendix “A-9”
(Deleted vide amendment in Bye laws: revised clause 2.15.1 b)
Form for Notice for Commencement of Work (Contents deleted vide amendments)
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019||
Appendix “A-10”
Annexure & Appendices
Appendix “A-10” (Bye laws: 2.15.3)
Dear Sir,
I/We hereby give notice that I/We have completed the erection of building/execution of the works in Plot No No .Scheme situated at . in pursuance of the sanction granted by the Authority vide File No dated… I/We are enclosing all reports of the Authority inspection carried out during construction period.
Block
Permission to occupy or use the building may be granted.
Yours Faithfully,
Signature of owner…
Name of owner
(In Block letters)
Address of the owner
……………………………………………
Dated:
Encl : As above
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh||Arunachal Pradesh Building Byelaws 2019|
Appendix “A-13”
Annexure & Appendices
Appendix “A-13” (Bye laws: 2.16 x)
1.1 Provision of Rain Water Harvesting shall be mandatory for plot of size 100 sqm and above.
1.2 The building construction could be broadly classified as per the following:
1.2.1 Category - (A) Building on plot size less than 100 sqm.
1.2.2 Category - (B) Building up to G-2 on the plot size more than 100 sqm.
1.4 The Rain Water Harvesting arrangement is not mandatory for building with a plot size less than 100 sqm. However, the owners of buildings are advised to construct Rain Water Harvesting structure for conservation and protection of ground water. Either they adopt traditional method or any upgrade method.
1.5 All the layout open spaces / amenity spaces of housing societies and new constructions / reconstruction’s Authority may approve the Rain Water Harvesting structures of specifications different from those specified here with, subject to the minimum capacity of rain water harvesting being ensured in each case.
Annexure E
Annexure & Appendices
1.6 The owner / society of every building mentioned in the para 1.5 above shall ensure that the Rain Water Harvesting structure is maintained in good condition for storage of water for non-potable purposes or recharge of groundwater at all times.
1.7 The Authority may impose a levy for the failure of the owner of any building mentioned in the para 1.5 above to provide or to maintain Rain Water Harvesting structures and when required.
1.8 Rain Water Harvesting shall be made mandatory for every Urban Local Bodies/Planning Authority to identify, demarcate, protect and maintain the water bodies that come under their jurisdiction will prepare a list.
1.9 If Rain water Harvesting system has not been installed in the apartments/houses having area less than 100 sqm, constructed before 2019 and there is no space available for installation of the same, the issue will be heard and resolved by the concerned Development Authority and suitable order shall be passed from case to case by The CEO/ Executive officer/special offer of the Development Authority/ ULBs.
1.10 It is the responsibility of the builders of the apartments to install rain water harvesting structure, if the building is constructed on or after 2019 and the occupancy certificate has been procured from the Director of Town Planning/ Development Authority than the owner of the flats will have combined responsibility to install rain water harvesting in the building.
2. Rain Water Harvesting in a Building Site.
Includes storage or recharging into ground the rain water falling on the terrace or on any paved or unpaved surface within the building site.
2.1 The following systems may be adopted for harvesting the rain water drawn from terrace and the paved surface.
2.1.1 Open well of a minimum of 1.00 mdia and 6 m in depth into which rain water may be channeled and allowed after filtration for removing silt and floating material. The well shall be provided with ventilating covers. The water from the open well may be used for non-potable domestic purposes such as washing, flushing and for watering the garden etc.
2.1.2 Rain Water Harvesting for recharge of ground water may be done through a bore well around which a pit may be excavated up to a depth of atleast 3.0 m and refilled with stone aggregate and sand. The filtered rain water may be channeled to the refilled pit for recharging the bore well.
2.1.3 An impervious surface / underground storage tank of required capacity may be constructed in the setback or other open space and the rain water may be channeled to the storage tank. The storage tank shall suitably placed so that the rain water may be drawn off for domestic, washing gardening and such other purposes. The storage tanks shall be provided with an overflow.
2.1.4 The surplus rain water after storage may be recharged into ground through percolation pits or trenches or combination of pits and trenches. Depending on the geographical and topographical condition, the pits may be of the size of 1.20 mt. width x 1.20mt length x 2.00 mt. to 2.50 mt. depth. The tranches can be or 0.60 mt width x 2.00 to 6.00 mt. length x 1.50 to 2.00 mt. depth. The capacity/ volume and number of pits and trenched should depend upon the catchment area and quantity of peak rain fall of the area. It can vary from place to place. Terrace water shall be channelled to pits or trenches. Such pits or trenches shall be back filled with filter media comprising the following materials.
2.1.4.1 40 mm stone aggregate as bottom layer upto 25% of the depth;
2.1.4.2 20 mm stone aggregate as lower middle layer upto 25% of the depth;
2.1.4.3 Coarse sand as upper middle layer upto 40% of the depth;
2.1.4.4 A thin layer of fine sand as top layer.
2.1.5 Top 10% of the pits / trenched will be empty and a splash is to be provided in this portion in such a way that roof top water falls on the splash pad.
2.1.6 Brick masonry wall is to be constructed on the exposed surface of pits / trenches and the cement mortar plastered.
Annexure E
Annexure & Appendices
2.1.7 The depth of wall below ground shall be such that the wall prevents lose soil entering into pits / trenched. The projection of the wall above ground shall at least be 15 cms.
2.1.8 Perforated concrete slabs shall be provided on the pits / trenches. Bund should be created to minimize the run off.
2.1.9 If the open space surrounding the building is not paved, the top layer upto a sufficient depth shall be removed and refilled with coarse sand to allow percolation of rain water into ground.
2.1.10 Any other system developed, which is technically suitable and feasible under the local circumstances and conditions, which may vary from place to place.
2.2 In case the plots where the water table is high i.e 10 feet or less, it is not mandatory to follow the above provisions.
2.2.1 The terrace shall be connected to the open well / borewell / storage tank / recharge pit / trench by means of PVC pipes though filter media. A valve system shall be provided to enable the first washings from roof or terrace catchment, as they would contain undesirable dirt. The mouths of all pipes and opening shall be covered with mosquito (insect) proof wire net. For the efficient discharge of rain water, there shall be at least two rain water of 100 mm diameter for a roof area of 100 sq.m.
2.2.2 Rain water harvesting structures shall be installed as not to endanger the stability of building or earthwork. The structure shall be designed such that no dampness is caused in any part of the walls or foundation of the building or those of an adjacent building.
2.2.3 The water so collected / recharged shall as far as possible be used for non-drinking and non-cooking purpose.
2.2.4 Provided that when the rain water in exceptional circumstances will be utilized for drinking and / or cooking purpose, it shall be ensured that proper filter arrangement and the separate outlet outlet for by passing the first rain-water has been provided.
2.2.5 Provided further that it will be ensured that for such use, proper disinfectants and the water purification arrangements have been made.
3 Community Rain Water Harvesting
A common rain water harvesting structure shall be installed for a cluster of houses/buildings where there is no space for making a rain water harvesting structure. It shall be the duty of each and every owner / occupier to participate in the installation and maintenance of community rain water harvesting.
4 Rain Gardens
A rain garden is a functional landscaping technique that can beautify our property as well as help to filter and slow the flow of storm water. Rain gardens allow about 30% more rainwater to soak into the ground than traditional lawns.
4.1 Rain gardens are saucer shaped gardens that water flows into that are planted with grassed, flowers, shrubs, and sometimes small trees. They soak up water while providing wildlife habitat. The soil and basin fills with water for a short amount of time before soaking back into the surrounding soil. Plants used in these gardens are adapted to survive in short periods of flooding as well as dry soils in between storms.
4.2 They are strategically located to capture runoff hard surfaces such as a driveway, parking area, sidewalk of streets. Rain gardens fill with a few inches of water after a storm and then water filters into the surrounding soil, rather than running off to the street or storm culvert.
4.3 Rain gardens are a very good option to help lower the impact of impervious surfaces and polluted runoff because they are low-tech, inexpensive, sustainable and aesthetically pleasing.
4.4 There are multiple benefits of rain garden to the community and the local environment which include:
4.4.1 Reduced polluted storm water runoff from yards into local streams,
4.4.2 Reduced localized flooding,
4.4.3 Reduced erosion,
4.4.4 Pollution prevention,
4.4.5 Groundwater recharge,
4.4.6 Enhanced wildlife habitat,
Annexure E
Annexure & Appendices
Has any down comer been provided? If so, please give details including pump capacity............
Please indicate the present arrangement for replenishment of water for firefighting............
Is a public or other water storage facility available nearby? if so, please give the capacity and distance from your building, also please indicate if it is easily accessible............
Please give any other information regarding availability of water supply for firefighting ...............
Have internal hydrants on each floor including basement (s) and terrace.
a) No. of hydrants on each floor including basement (s) and terrace............
b) Bore and length of each floor including basement(s) ............
c) Size (bore) and type of nozzle fitted to each hose reel............
d) Is the hose reel connected directly to the riser or to the hydrant outlet? ...............
Has fire hose been provided near each hydrant? if so, Please indicate ............
Annexure D
Annexure & Appendices
a) The type hoses.
b) The size (bore) of hose
c) The length of each hose.
Have branch pipes been provided? if so, please indicate
a) The type of branch pipe.
b) Size of nozzle fitted to each branch.
25 a) If the basement is used for Car / Scooter parking or storage. Has it been sprinkled?
b) Whether any cubicles proposed in the basement? If so, the area of each cubical be indicated?
c) Whether segregation/compartmentation of the basement has been provided? If so, please give details.
Is the building equipped with automatic fire detection and alarm system? If so, please indicate
a) The type of detectors used
b) The standard to which the detectors conform
c) The code to which the installation conform
Have manual call boxes been installed in the building for raising an alarm in the event of outbreak of fire? If so, please give details.
Has public address system been installed in the building with loudspeaker on each floor with talk back facility.
Has an intercom system been provided between the various floors and the fire control room in entrance lobby?
Has a fire control room been provided in the entrance lobby of the building?
How many staircases have been provided in the building? Please indicate in each case:
a) Width of the stairway.
b) Width of treads.
c) Height of risers
d) If the treads are of the non-slip type.
What is the average occupant load per floor?
Whether fire tower has been proposed?
How many lifts have been installed in the building? Please indicate in each case:
a) The floors between which the lifts runs.
b) The type of doors fitted to the lift Car and at each landing.
c) Fire resistance raring of lift Car and landing doors, if known
d) Floor area of the lift car.
e) Loading capacity of the lift car
f) Has communication system been installed in the lift car?
g) Has a fireman's switch been installed in the lift for grounding it in the event of fire
Have any stationary fire pump (s) been installed or pressuring the wet riser? If so, please indicate.
a) The number of pumps.
b) The size of suction and delivery connection of each pump
c) The output of each pump
Has the building been protected with sprinkler system, If so, detail of sprinkler pump.
Has a standby source of power supply been provided? If it is through a generator, please indicate.
a) The capacity (output)
b) The functions that can be maintained simultaneously by the use of the Generator, such as operating lift(s); fire pumps, emergency lighting etc. system; exit signs; PA system etc.
c) Is the generator automatic in action or has to be started manually?
Has any Yard hydrant been provided from the building's fire pump?
Where more than one lifts are installed in a common enclosure have individual lifts been separated by fire resisting walls or 2 hours fire rating?
Has the lift shaft(s) lift lobby or stairwell been pressurized? If so, give details.
Annexure D
Annexure & Appendices
41. Has the lift lobbies and staircase been effectively enclosed to prevent fire/smoke entering them from outside at any floor?
42. Have all exits and direction of travel to each exit been sign-posted with illuminated signs?
43. Has a false ceiling been provided in any portion of the building? If so, please indicate location and also mention if the material used for the false ceiling is combustible or non-combustible.
44. Is the building centrally air-conditioned? if so, please indicate:
a) The material used for construction of ducts and its fittings....
b) The type of lining used for ducts, if any....
c) The type of lagging used for ducts, if any for insulating any portion of the duct; please also indicate how the lagging is secured....
d) If plenum is used for return air passage has it been protected with fire detectors? Please give details....
f) Has a separate A.H.U. been provided for each floor?
g) Whether automatic shutdown of A. H. U. is coupled with detection system/sprinkler system....
h) Is the ducting for each floor effectively isolated or is it continuous on more than one floor?
i) Are the fire dampers being provided?....
45 Where are the switchgear and transformer located? If inside the building please indicate:
a) If the switchgear and transformer (s) have been housed in separate compartments, effectively separated from each other and other portions of the building by a four-hour's fire resistive wall?
b) What precautions have been taken to prevent a possible fire in the transformer (s) from spreading?....
c) Are transformer protected by high velocity water spray system....
46 I) Where electrical cables, telephone cables wet risers / down comers pass through a floor or wall has the spaces (apertures) round the cables /pipes been effectively sealed/plugged with noncombustible, fire resistance material?....
II) Ventilation
a) Whether natural ventilation is relied upon? If so, give details of the vents for the stairwell life shafts....
b) Whether mechanical ventilation has been proposed? If so, give details of the proposed system indicating the number of air changes for the basement and other floors....
c) Whether mechanical ventilation is coupled with automatic detection system/sprinkler system? Please give details of the system....
47. Please indicate the number and type of fire extinguishers provided at various locations and the arrangement for the maintenance of the extinguishers....
48. Please indicate if all fire extinguishers bear the BIS mark....
49. Whether the refugee area has been provided? If so, the floor on which provided and the total area provided floor-wise....
50. Are the occupants of the building systematically trained in fire prevention, use of fire extinguishers and emergency procedures? If so, please give details....
51. Does an emergency organization exist in the building? If so, please give details and append a copy of the emergency (fire) orders....
52. Has a qualified officer been appointed for the building either individually or jointly with other building(s)....
53. Has the building been protected against lighting? If so, does the lighting protection conform to any code? Please indicate details provision of MCB and ELCB in the building....
54. The work has not been started on site and construction will be started only after final approval of the Authority / the position of construction at site is given below:....
Annexure D
Annexure & Appendices
Name and address of the consultant with Registration No…
Owner's Signatures
Signature of the Applicant / Architect
Name…
Name…
(In block letters)
(In block letters)
Designation……
Organization… Signature of Fire Consultant
Dated:
Name……………………
(In block letters)
Remark of the concerned Authority. The proposal has been broadly examined. The above information is correct and the proposal is permissible as far as development Authority is concerned (Additional comments, if any, may be given below or attached):
The proposal can be considered by Fire Services at conceptual stage/is forwarded to Fire Service along with 3 sets of drawings which are according to bye-laws, Master Plan, Zonal Plan, and fire fighting regulations and policy instructions of Government. The proposal involves relaxation in respect of height/set-backs/
architect has been advised to furnish the requisite material and documents given in the attached list, within one week time directly to the Fire Service.
Signature of Authority
165
Name:
Designation and office Seal:
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh| Arunachal Pradesh Building Byelaws 2019||
Annexure E
Annexure & Appendices
Annexure – “E” (Byelaws 9.4)
Appendix “A”
Annexure & Appendices
Appendix “A” (Bye laws 2.9.1 & 6.3.5)
Signature of Architect/Engineer/ Group/Engineer with date
Name in Block Letters
Name in Block letters, Licence No
Address
Address
Dated :…
Appendix “A-14”
Annexure & Appendices
Appendix “A-14” (Bye laws: 2.17.1)
Completion-cum-Occupancy Certificate
File No… Plan No… Dated:…
Shri/Miss/Smt…
With reference to your notice of completion dated I hereby certify that building as per description below certified plan at Plot No Locality Sector/Colony .situated at… whose plans were sanctioned vide No …has been inspected withreference to building bye-laws in respect to the structural safety, fire safety, hygienic and sanitary conditions and proposed rainwater harvesting systems inside and in the surroundings and is declared fit for occupation and release of regular water and electricity connections. The description of the construction work completed is given as under:
Description of Construction Work Block Wise/Building Wise.
Colony/Sector ………… . Building No. ……………
Details of Completed Work floor wise.
Yours faithfully
Director of Town Planning & ULBs Itanagar
Appendix “A-15”
Annexure & Appendices
Appendix “A-15” (Bye laws: 2.17.1)
I undertake to supply the owner and the supervise the detailed structural drawings. I shall also undertake the responsibilities if there is any structure failure even after my drawing and supervision. If my services are terminated I undertake to intimated the authority in writings.
Signature Registration No. Empanelment No.
Name: Address ……………………………………… Phone: …………………………
Appendix “A-17”
Annexure & Appendices
Appendix “A-17” (Bye laws: 6.1.7.2)
Form NO. 12 Building Completion Certificate {by Architect on Record}
Reference No. Owner’s Name: ... Location :…
Submitted on :… ..Received on : …
The Director Town Planning and ULBs Government of Arunachal Pradesh Itanagar
The building/s has /have been constructed according to the sanctioned plan.
The building/s has /have been constructed as per approved plan and design as per detailed architectural drawings and specifications prepared by Architect on Record.
Construction has been done under our supervision / guidance and adheres to the drawings submitted.
Signature of the Owner .... Signature of Architect on Record ....
Date: .... Date: ....
Name in block letter: .... Name in block letters: ....
Address: .... Address: ....
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh||Arunachal Pradesh Building Byelaws 2019||
Appendix “A-18”
Annexure & Appendices
Appendix “A-18” (Bye laws: 6.1.7.2)
4
5
6
7
8
A. Load Bearing masonry wall construction
B. Framed Structure
Construction and structural materials
Critical loadbearingelement
Brick
RCC
Stone
Timber
Steel
Roof floor
RCC
Timber
RCC
Steel
Jack-arch
Appendix “A-20”
Annexure & Appendices
v. Base plate connections with columns or pedestals
i. L di v oa ngs
(please describe some of the major cracks, their nature, extent and location, with a sketch, if necessary)
(IX) Recommendations if any
This is to certify that the above is a correct representation of fact as given to me by the owner and as determined by me after site inspection to the best of my ability and judgement.
The recommendations made by me to ensure adequate safety of the structure are complied with by the owner to entre satisfactory.
Signature of Registered Structural Engineer on Record
Date:
Name in block letter:
Registration Number:
Address: …………………………
Appendix “A-21”
Annexure & Appendices
Appendix “A-21” (Bye laws: 6.1.2)
Structural Design Basis Report
This report to accompany the application for Building Development Permission.
In case information on items 3, 10, 17,18 and 19 cannot be given at this time, it should be submitted at least one week before commencement of construction.
Part 1 General Data
S.No.
Description
Information
Notes
1
Address of the building Name of the building Plot number Subplot number TPS scheme a. Name b. Number Locality / Township District
2
Name of the owner
3
Name of builder on record
4
Name of Architect/Engineer on record
5
Name of Structural Engineer on record
6
Use of the building
7
Number of storeys above ground level (including storey to be added later, if any)
8
Number of basements below ground level
9
Type of structure Load bearing R.C.C frame R.C.C frame and shear walls Steel frame
10
Soil data Type of soil Design safe bearing capacity
IS: 1893 Cl.6.3.5.2 IS: 1904
11
Dead load (unit weight adopted) Earth Water Brick masonry Plain cement concrete Reinforced cement concrete Floor finish Other fill materials Piazza floor fill and landscape
IS:875 Part 1
12
Imposed (Live) loads Piazza floor accessible to Fire Tender Piazza floor not accessible to Fire Tender Floor loads Roof loads
IS: 875 Part 2
13
Cyclone / Wind Speed Design pressure intensity
IS: 875 Part 3
14
Seismic zone
IS: 1893 (2002)
15
Importance factor
IS: 1893 (2002) Table 6
16
Seismic zone factor (Z)
IS: 1893 Table 2
17
Response reduction factor
IS: 1893 Table 7
18
Fundamental natural period -approximate
IS: 1893 CL. 7.6
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh| Arunachal Pradesh Building Byelaws 2019||
Appendix “A-21”
Annexure & Appendices
19
Design horizontal acceleration spectrum value (Ah)
IS: 1893 CL. 6.4.2
20
Expansion / Separation joints
Enclose small scale plans of each floor on 4 4 sheets
Incase terrace garden is provided, indicate additional fill load and live load
Indicate on a small scale plan on A 4 sheet
Appendix “B”
Annexure & Appendices
Appendix “B” (Bye laws: 2.9.4 & 6.3.8)
And whereas the executant has agreed to execute an indemnity bond to the above affect and also to abide by the terms imposed by the concerned Authority to the grant of sanction for construction of the basement.
Now this deed witnesses:
That in consideration of the sanction of the plans by for construction of the basement the executant undertakes that he/she shall at all times keep harmless and free from any liability, loss or damages/ flowing from any injury or damage caused to the adjoining built-up properties or to any person as a consequence of the construction of at the time of digging of its foundations or during the course of its construction or at any time thereafter.
The owner agreed and undertakes that in the event of any claim being made by any person or persons against the concerned Authority either in respect of the sanction granted by the concerned Authority to the owner for the construction of basement or in respect of the construction or manner of construction of the basement by the owner or the consequences flowing from the said sanction the executant shall be responsible and liable and not the concerned Authority.
The executant agrees and undertake to indemnify the concerned Authority fully in respect of any amount which the concerned Authority may be required to pay to any person either by way of compensation or damages or on any other account as a result of any claim or suit or any other proceedings concerning the sanctioning of the construction of the basement of the making thereof and also in respect of the costs and expenses which the concerned Authority may incur on defending any action.
4 Without prejudice to the above undertaking the executant hereby binds itself to pay to the concerned Authority to the full extent any amount which the concerned Authority may be required to pay to any person in connection with, relating to or concerning the sanctioning of the basement or the making thereof.
5 The owner further agrees and undertakes that this bond shall remain in full force and effect till the executant faithfully observes/performs the undertaking herein before contained.
In witness whereof the executant above named has signed this bond on this ………….. day of..at
Indemnifier
Witness:
198
(Signatures)…
Address…
Name………
Full Address…
Appendix “C”
Annexure & Appendices
Appendix “C” (Bye laws: 2.12.1)
6
11
6
0.6-0.75
11
-
70
-
115
-
140
-
7
11
8
0.6-0.75
15
-
90
-
150
-
180
-
8
11
10
0.6-0.75
18
-
108
-
180
-
216
-
9
11
13
0.6-0.75
22
-
132
-
220
-
264
-
10
11
10
1.0
21
-
126
-
210
-
252
-
11
11
10
1.5
24
-
144
-
240
-
288
-
12
11
13
1.5
28
-
156
-
260
-
312
-
13
11
13
1.5
32
-
180
-
300
-
-
-
14
16
10
1.0
17
-
100
126
170
210
-
252
15
16
13
1.5
20
24
120
145
200
240
248
290
16
16
13
1.5
23
30
138
180
230
300
-
360
17
16
16
1.5
25
33
150
198
250
330
300
356
18
21
10
1.5
18
32
108
132
180
220
214
264
19
21
13
1.5
21
26
126
156
210
250
250
312
20
21
14
1.5
23
28
138
168
230
280
-
-
Note-1: a) For all non-residential buildings, the traffic cleared in 50 minutes is considered adequate and is approved by Authority. As such for calculation the number of lifts required, the rate of the clearance of traffic in column 9 and 10 and the population may be taken into consideration.
b) In addition to total number of lifts required as above, provision of one lift of the same capacity may be considered to serve as stand-by.
Note-2: The population may be worked out on the basis of useful carpet area which the person occupies (excluding area of Verandah, Lobbies, Halls, Passages, Lavatory blocks, etc.)
Note-3: The population on ground and first floor may not be taken into consideration since these floors are not generally served by lifts.
Note-4: 0.75 meter per sec. Equivalent to 150 ft. per Min. 1.00 meter per sec. Equivalent to 200 ft. per Min. 1.5 meter per sec. Equivalent to 300 ft. per Min.
Note-5: The height of buildings for lift installation i.e. the travel on the lift presumed in the above statements is as below: 7 floors 21.0 mt. 11 floors 33.0 mt. 16 floors 48.0 mt. 21 floors 64.0 mt.
Appendix “D”
Annexure & Appendices
Table: Number and types of lifts for Residential Building
Sl. No.
floors
No
Passenger unit capacity Persons
Speed in m/s
Landing Gate Type
Central System
Service Lift No.
Capacity Persons
Type of Gate
Central System
1
5 to 8
2
6
0.0 to 0.5
*
Automatic push button operation both from car and landing
-
-
-
-
2
9 to 11
2
8
0.6 to 1
*
--Do--
1
8
-
Push button car handle switch control
3
11 to 13
2
8
0.6 to 0.74
*
--Do-and without collection system
1
8
-
--do--
1
6
Power operated doors
--do--
4
13 to 19
2
8
1
-
--do--
1
8
-
--do--
2
8
1
Power operated doors
* For buildings more than 15 meters in height collapsible gates shall not be permitted. (see bye-law No. 7.9.1(f))
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019||
Appendix “D-1”
Annexure & Appendices
Appendix “D-1” (Bye laws: 4.32.2)
The dimensions and relevant information for lift installations like lift well, pit depth, machine room, clearance from top floor landing to machine room flooring is given in table below:
Table: Dimensions and required information for Lift Installation in Building
Carrying Capacity of lift (persons) Number
Load (kg)
Lift Speed
Dimension of Lift well front depth (In cm.)
(Cm)
Leading Pit Entrance (Cm)
Dimension of Machine Room
Clearance from top floor landing to machine room flooring cm
Imposed load in tones on top of lift well due to installation. It may be noted that figures do not include weight of the machine from floors and well, etc.
1
2
3
4
5
6
7
8
9
10
11
12
4
272
Up to & including 1 m/s
175
115
70
140
230
275
245
450
6.5
6
408
--do--
195
135
80
140
230
335
275
450
7.0
8
544
--do--
200
170
80
150
245
395
275
450
8.5
10
680
Up to & including 1.5 m/s
225
170
90
150
245
395
305
470
10.5
13
884
--do--
235
188
90
150
245
425
335
470
13.0
16
1088
--do--
255
205
105
150
245
520
335
480
15.0
20
1360
--do--
255
220
105
150
245
520
335
480
15.0
Note:
i) All lift well dimensions are minimum clear finished plumb requirements.
ii) iii) Where more than one lift is located in the lift well, extra width of 10 cm. Separator beam should be provided. 1 m/s = 200 ft./min.
iv) The height of landing entrance should be 210 cm. (about 7 ft.) for all lifts.
Appendix “D-2”
Annexure & Appendices
Appendix “D-2”
(Bye laws: 4.32.3)
The electric sub-station should be provided in the approved/sanctioned covered area of the buildings not below the first basement level and should be on the periphery of the building with clear independent round the clock approach having proper ramp with slope.
The ramp should be designed in such a manner that in case of fire no smoke should enter the main buildings. The exit from basement electric sub-station shall have self-closing fire/smoke check doors of 2 hours. F.R. near
Appendix “D-2”
Annexure & Appendices
entry to ramp. Additional exit shall be provided if traveled distance from the farthest corner of the ramp is more than 15mt.
The electric sub-station should be totally segregated from rest of the basement having 4 hours. F.R. wall and should have adequate internal lighting and ventilation. A perfect independent ventilation system of 30 air charges per hour linked with detection as well as automatic medium velocity water spray system for individual transformer shall be located outside the building at ground floor, fire control room shall be manned round the clock and shall also have and audio system in the basement as well as in the control room. No service such as water, sewer, air-conditioning, gas pipes or telegraphs services should pass through electric substation of the cable trench.
The rising mains should be of metal bus bars. The floor of electric sub-station should be 2 ft above the rest of basement floor and designed suitably to carry 10 tons of transformer weight on wheels also having provision of proper cable trenches 0.6 X 0.6 mt. depth. Dummy floor of 0.6 mt. depth be provided to facilitate laying of cables inside the building connecting to equipment. Fire retarding cables should be provided and cable trenches be filed with said cables. R.C.C. pipes at suitably places as required will be provided for cable entries to the sub-station spaces with suitable water proofing arrangement. A provision of 12 ft. clear height below beams should be made in the electric sub-station area along with adequate arrangement for fixing chain pulley block for a load of 15 tons. Provision of sumps shall be kept in the floor so that complete volume of transformer oil in the event of spillover could be accommodated. Sufficient arrangement to prevent spread of fire to oil pumps be made.
Transformers room and sub-station room shall be provided with steel shutters of 8’ X 8’ with suitable grills. Sufficient arrangement for pumping the water out, in case of flooding should be made to minimize loss to switchgear and transformer.
In view of experience of installation of exhaust chimneys in the multi-storeyed buildings at undesirable locations, proper provision in the form of vertical exhaust leading to above terrace level should be made for the substation.
Electric sub-station space should be made available free of cost by promoters and should be free of seepage/leakage of water. There should be no combustible material kept in side or in the vicinity. Periodic inspection of electric sub-station shall be mandatory and violation of any bye-law will be dealt, sternly with penalty and immediate disconnection.
D.2.3. General
D.2.3.1 The maintenance of the built up space for electric sub-station, distribution equipment, vertical shafts and enclosure at each floor shall be done by the owner.
The standby arrangement for electricity supply up to and including the sub-station equipment and distribution pillars at the sub-station shall be provided compulsorily.
Appendix “E”
Annexure & Appendices
Appendix “E”
(Bye laws: 2.12.5 & 6.3.6)
Qualification and Competence of Technical Personnel for Preparations of Schemes for Building Permit and Supervision
3
Structural Engineer
Post Graduate in Structural Engineering from recognized Indian or Foreign University, or Corporate Member(Civil) of Institution of Engineers (India), minimum3-year experience in NO S wTtiErtuh -c dtuTerhsaeigl 3 en-yninegagirn a eexnepdreirn fiiegenlcdper wa shcoatrliklc b.ee relaxed to 2 years in the case of post-graduate degree ofrecognized Indian or foreign university in the branch of structural engineering. In case of doctorate in structural engineering, the experience required would be one year.
The registered structural engineer shall be competent to prepare the structural design, calculations and details for all buildings and undertake their supervision. In case of buildings having special structural features, as decided by the Authority, they shall be designed only by Structural engineers.
Appendix “E”
Annexure & Appendices
Sl No
Professional
Qualifications
Competence / Functions
4
Town Planner
Graduate or Post-graduate degree in Town and Country Planning with valid Associate Membership of the Instituteof Town Planners, India.
The registered Town Planner shall be competent to carry out the work related to the development permit as given below: a) Preparation of plans for land sub-division/ layout and related information connected with development permit for all areas more than 1hectare. b) Issuing of certificate of supervision for Development of land of all areas. NOTE - However, for land layouts for development permit above 5 hectare in area, landscape architect shall also be associated, and for land development infrastructural services for roads, water supplies, sewerage/drainage, electrification, etc, the registered engineers for utility services shall be associated.
5
Landscape Architect
Bachelor or Master's degree in landscape architecture or equivalent from recognized Indian or foreign university.
The registered landscape architect shall be competent to carry out the work related to landscape design for building/development permit for land areas 5 hectares and above. In case of metro-cities, this limit of land area shall be 2 hectares and above. NOTE - For smaller areas below the limits indicated above, association of landscape architect may also be considered from the point of view of desired landscape development.
6
Urban Designer
Master's degree in Urban Design or equivalent from recognized Indian or foreign university.
The registered urban designer shall be competent to carry out the work related to urban design for city areas more than 5 hectares and campus area more than 2hectares. He/ She shall also be competent to carry out the work of urban renewal for all blighted/congested areas. NOTE - For smaller areas below the limits indicated above, association of urban designer may be considered from the point of view of desired urban design.
7
Supervisor
Diploma in Civil Engineering/ Architectural Assistantship from recognized institute with 2yrs working experienceorCivilDraftsmanshipfromI.T.Iwith5yrsexperienceunder a qualified Architect /Civil Engineer for building construction and supervision.
The registered supervisor shall be competent to carryout the work related to the building permit as given below: a. All plans and related information connected with building permit for residential buildings on plot upto 100m2 and up to two storeys or 7.5 m in height; and b. Issuing certificate of supervision for buildings asper A.
8
Plumber
Licensed by the concerned Authority through examination of Candidates-Certificate of training from ITI/Polytechnic recognized by any authority with min. 2yrs experience of execution of sanitary and plumbing works under any govt. Dept./ Local body or a qualified Architect/ Engineer. Knowledge of working drawings and dimensioned sketches.
A plumber shall be competent to do the following jobs: a. Execution / supervision of sanitary works up to 500sqmt plot size and 4 storeyed buildings.
9
Electrician
As prescribed by the concerned
electricity company
10
Fire Consultant
As prescribed by Director Fire Services, Town/City Fire Service.
Appendix “E-1”
Annexure & Appendices
Appendix “E-1” (Bye laws: 1.1 - 37)
Empanelment of Competent professional
Definition: In these rules, unless the context otherwise requires:
a) “Act” – the Act of the concerned Authority
b) “Empanelled Architect” – A person empanelled by the Authority as per rules under these bye-laws as authorized person to sanction building plans forming part of an approved lay-out plan and for other buildings as authorized in section 13.4 of the Bye-laws.
c) “Person Authorized” – means a qualified and duly registered Architect having a degree in Architecture or equivalent qualification and registered with the Council of Architects, India with minimum 5 years of experience.
d) “Sanctioned Building Plan” means a building plan of a building/premises to be constructed on a plot and approved by the Competent Authority/ Architect in accordance with the provisions of Master Plan/Zonal development plan and Building Bye-laws.
e) “Fee” means a fee to be charged by the Authority/Architect for sanction of building plans. (Design and consultations fees agreed between the architect and his/her client is independent of this ‘Fee’)
For the empanelment, the qualified Architect/Engineer shall submit list of projects handled with proof and credentials along with recommendations from Council of Architecture, India.
Authority should obtain security deposit/professional indemnity bond and professional liability insurance from empanelled Architects as decided in value from time-to-time.
The empanelment of an Architect shall be for a period of two years and can be extended from time to time subject to review by the Authority at the end of every two years.
The Architect shall be empowered to sanction building plans of residential buildings up to 15 mt. height and for plot size up to 500sqmt, forming part of approved layout plan. And for other buildings the criteria of empanelment shall be as per section 13.5 of the Bye-laws.
In respect of sanction of building plans of Government buildings, the plans shall be sanctioned by the Chief Architect/ Senior Architect of the concerned Department of the Government, provided it conform to Master Plan/Zonal Development Plan, approved layout plan and Building Bye-laws.
The Architect shall charge building application fee, other charges as prescribed under Building Bye-laws and other charges as prescribed form time to time. He will be permitted to retain 50% of the building application fee towards his service charges and balance amount along with other charges shall be deposited with the Authority along with two sets of building plans and other required documents. If the Authority wants to raise any objection, the same shall be communicated to the architect within 10 days of filing the application with the Authority. The architect while sanctioning the building plans shall take due cognizance of the objections raised by the Authority.
Before sanction of building plans, the Architect shall ensure and satisfied himself that various permissions as required by the law from different Authorities have been obtained.
The Empanelled Architect shall also ensure at the time of sanction of building plans as well as during the inspections at construction stage and also at the time of giving completion certificate that there is no violation of Master Plan/Zonal Development Plan, Approved Layout Plan and Building Bye-laws and other related rules and regulations in force.
In case it is found that there had been a violation of Master Plan/Zonal Development Plan, approved layout plan and Building Bye-laws and other related rules and regulations in force at the time of sanction of building plans/ construction stage / issue of completion certificate, action for penalizing the Architect shall be taken including removal from the panel and referring the matter to the Council of Architecture, India for appropriate action.
The Empanelled Architect shall be required to file a quarterly return of building plans received for sanction, fee received, etc. to the Concerned Authorities. His work shall be monitored to check the backlog and performance.
Appendix “E-1”
Annexure & Appendices
Before issue of a completion certificate a joint inspection is to be carried out by the officer authorized by the Authority in this behalf and the empanelled Architect. Within 10 days of the joint inspection, the Architect shall be informed about the non-compoundable deviations to be removed and composition fee to be charged for minor deviations under the rules.
The Architect shall issue the completion certificate after having satisfied himself that non-compoundable deviations have been removed from the building and necessary compounding/regularization fee has been deposited with the concerned Authority.
Appendix “F”
Annexure & Appendices
Appendix: “F” (Bye laws: 7.12.1)
Penal Action for violation of provisions of Development Code of Master Plan, Zonal Regulation and Building Bye-laws.
(A) Non-Compoundable Items
Any deviations except those set in para “AA” hereunder, from the maximum, minimum prescribed limits regarding:
Coverage,
F.A.R.
Setbacks,
Open spaces,
Total height of the building
No. of floors,
No. of DUs & density
Parking norms,
Light and Ventilation provisions,
Use
All other provisions of these bye-laws except item given in para ‘B’ below shall not be compounded/regularized and shall have to rectified by altering/ demolition at the risk and cost of owner. Besides this any other action as per terms and conditions of lease and provisions of Act shall proceed.
(A.A) Compounding Excess Coverage/FAR
i) Deviations in the coverage/FAR to the extent of 5% of the permissible coverage/FAR or 13.5 sq.mt. whichever is less in building(s) use premises, other than building(s) use premises where 100% ground coverage and fixed height is allowed as per Architectural control forming part of comprehensive schemes like District Centre, Community Centres, Cluster Court Housing etc. may be compounded after levying penalty at the following Rates:
Rates of excess coverage/floor area:
Up to 5% of excess coverage/FAR a onetime compounding fee equivalent to the land rated in the concerned locality applicable at the time of the application for compounding.
ii) For excess coverage / FAR for above 5%
Any excess coverage above 5% or 13.5 sq.mt whichever is applicable would be liable to demolish to that extent.
iii) Compounding at set back Infringements
The infringements of the setbacks maximum to the extent of 30 cm (1 ft.) may be compounded by way of levying compounding fee at the following rates:
Infringements
Residential Buildings
Non-Residential Buildings
Upto 15 cm (6 inch)
Rs. 2000 per sqm of area infringing the setback
Rs. 5000 per sqm of area infringing the set back
Above 15 cm (6 inch)
Rs. 5000 per sqm of area infringing the setback
Rs. 8000 per sqm of area of the infringing the setback
(B.B) Compoundable Items
If a building or part thereof has been constructed unauthorized, i.e. without obtaining the requisite building permit from the concerned Authority as required under the building bye-laws, the same shall be compounded at the following rates provided the building or part thereof so constructed otherwise conforms to the provisions contained in the Building Bye-laws and Master/Zonal Plan regulations. For this party shall have to submit the request for building permit in the prescribed procedure.
Rates:
a) Rs. 300 per sqm of the covered area constructed unauthorized in residential building.
Appendix “F”
Annexure & Appendices
b) Rs. 500 per sqm of the covered area constructed unauthorized: -
Rented Apartment, Group Housing & Guest Houses.
Industrial Buildings:
Storage buildings (underground or above ground)
c) Rs. 350 per sqm of the covered area constructed unauthorized in the building categorized below:
All Govt. Public and Semi-Public and Utility Buildings.
Religious, Institutional and Educational Buildings.
d) Rs. 1000 per sqm of covered area constructed unauthorized.
Cinema and Theatre Building.
Petrol Pumps (Filing / Service Station)
Hazardous Buildings.
Commercial / Business Buildings
The buildings not covered specifically under the above categories shall be compounded as decided by the Authority, considering merits of each individual case.
Items which are exempted from the calculations of the coverage and FAR e.g. cupboards, canopy, basement, and mezzanine, loft, watchman cabins, etc. but constructed unauthorized without obtaining prior permission from the Authority, but within the permissible limits shall also be compounded/ regularized at the rate prescribed above.
Deviations of the building bye-laws other than specified in (A) (Non-compoundable). Deviation up to the maximum extent of 10% from the maximum/minimum prescribed limit (as prescribed by the building bye-laws) shall be compounded at the following rates:
a) In case of deviations of areas of various components of the building, the rate of penalty will be @ Rs. 300/- per 1% deviation.
b) For deviations in terms of height the penalty shall be @ Rs. 300/- per 1% of deviation for every 10 sqm or part thereof of the affected area.
c) Deviations from the prescribed limit of width, length, penalty shall be @ Rs. 300/- per 1% of the deviation for every 10 sqm or part thereof of the affected area.
Notes:
Notwithstanding the provisions above, no penalty shall be levied for the first 3% of deviation but in case the deviation limit exceed 3% penalty shall be levied at above rates for the total deviation up to 10%.
The penalties of the above rates as given in (ii) (a), (b), and (c) shall be charged for each deviation and for every component of the building separately.
a) In case of increase in size of canopy in front open space form the prescribed limits of bye-laws the same shall be charged @ Rs. 100/- per sqm.
b) End walls up to 0.9 m in width in a terrace type construction constructed purely as an architectural feature Rs. 50/- each.
c) Enclosing of front balcony with jail wall which is being used as a part of stair case Rs. 500/- sq.mt.
d) (i) An open Urinal Wall up to 1.7 mt. height --------- No Penalty.
(ii) Water storage Tank over open urinal with walls up to 1.70 mt. in height ------- No Penalty, if sanctioned. If not sanctioned, Rs. 500/- each.
e) All roof projections beyond permissible limit of bye-laws as specified shall be counted towards FAR calculations if otherwise the same do not infringe up to any other bye-laws.
f) Plinth steps in setback portion -------------- Rs. 100 each.
g) Extra slab in mumty constructed without sanction shall be compounded at the rate given in (B) (compoundable item) provided it does not infringe upon the provision of any other bye-laws.
211
h) Partition wall provided without sanction at any floor if the same are not infringing upon the provision of any other bye-laws --------- Rs. 50 per sq.mt. of the surface area of the wall (i.e. length X height)
i) Projections/sunshade/(not more than 0.45 mt. in width on public streets/roads over window opening above first floor shall be objected. However, at Ground Floor these shall be not permitted.
The Authority if satisfied that there are other deviations of general nature, which are not described above, may fix rates for compounding such deviations. However, there shall be no further relaxation in FAR and coverage over that permitted above.
Revision of all fees and charges under consideration for compounding and regularization shall be revisited by the Authority from time-to-time based on the Schedule of rates.
Appendix “G”
Annexure & Appendices
Appendix “G”
(Bye laws: 7.9 & 8.12)
Guidelines for Mitigation of Effects of Electro Magnetic Radiation in Built Spaces
Introduction
Electromagnetic radiations are energy waves having time varying electric and magnetic fields at right angles to each other and are predominantly used for wireless communication.
Waves of Electromagnetic Radiation
Although, Electromagnetic Fields (EMF) occur in nature and thus have always been present on earth (Sun is the biggest source of natural EMR), nevertheless their occurrence has become more pronounced due to rapid advances of wireless technology in the communication sector.
The twentieth century witnessed, steady rise of environmental exposure to man-made sources of EMF due to increasing electricity demand, ever-advancing wireless technologies and changes in work practices and socia behavior. The unprecedented growth in communication industry in recent years has also caused an exponential rise in electromagnetic radiations in the envelopes surrounding all living habitats.
Human beings are thus exposed to a complex mix of electric and magnetic fields at many different frequencies, at home and at work. EMF (Electro Magnetic fields) can be broadly divided into-
Low-frequency electromagnetic fields- the common sources of which include power lines, household electrical appliances, and
High frequency electromagnetic fields: the main sources of which are radar, radio and television broadcasting, mobile telephones and their base stations, induction heaters and anti-theft devices etc.
Given below is the chart of Electromagnetic spectrum which highlights various ranges of frequencies and the equipments which work in these ranges of frequencies: -
Therefore, there is an urgent need to adopt precautions for living beings from any effects of electromagnetic radiations at our work places as well as at our living spaces.
Annexure “F”
Annexure & Appendices
Electromagnetic Radiations: Effects of Exposure
The effects of electromagnetic radiation upon living cells, including those on humans, depend upon the frequency as well as the penetrating power of the radiation.
Initially, it was believed that low frequency fields were too weak to cause heating to a significant level and thus do not have any biological effect. There have been a number of epidemiological studies for a relationship between cell phone use and consequent health threats that have been largely inconclusive. Thus, it can be concluded that their effect is not very prominent although significant. However, there are sufficient evidences to suggest the existence of complex biological effects of weaker non-thermal electromagnetic fields, and modulated RF and microwave fields. World Health Organization has classified radiofrequency electromagnetic radiation as a possible group 2b carcinogen (possible weaker threats).
In case of low-frequency radiations (radio waves to visible light) therefore, depending upon the power of the radiation heating effects are caused due to absorption of radiation by the living cells. These thermal effects increase with the frequency of radiation as penetration of radiation into the organism increases (for example microwaves penetrate more than infrared rays).
At higher frequencies (visible and beyond) however, the individual photons of the radiation carry enough energy individually and thus directly or indirectly can damage biological molecules. All frequencies of UV radiation have therefore been classified as Group 1 carcinogens by the World Health Organization. In this context it is a significant fact that Ultraviolet radiation from sun exposure is the primary cause of skin cancer. Thus, at such frequencies electromagnetic radiations cause much more damage to biological systems than simple heating. This is most obvious for the "extreme" Ultraviolet, X-ray and Gamma radiations, which are referred to as ionizing radiations due to the ability of photons of this radiation to produce ions and free radicals in materials which include living tissues as well. Since such radiation can produce severe damage to life at powers that produce very little heating, it is considered much more dangerous than the rest of the electromagnetic spectrum.
Health risks from Electromagnetic radiations can be numerous depending upon the power and frequency of radiations.
From the perspective of prevention of any health effects of Electro Magnetic Radiations there is a need of suitable precautions, since it is not possible to keep away from them owing to the advent of wireless communication technology which is based upon electromagnetic waves of higher frequencies besides many other applications like microwave, remote controlled toys, cordless phones, TV remotes etc.
Guidelines for Buildings and Built forms mitigating effects of EMR
While planning a building or a residential complex/ township, it is most desirable to list all probable equipment’s/ appliance emitting Electromagnetic Radiations in order of ascending/descending intensities. These should also be categorized as per indoor and outdoor emissions. Their placement in the built space and surroundings can then be decided based on certain premises.
The most fundamental principal in this regard is that the effect of Electromagnetic Radiation decreases with increase in distance from radiation emitting source. It is thus advisable-
To keep a safe distance from working electric and electronic equipments.
|Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019|
Annexure “F”
Annexure & Appendices
o Minimize the use of all equipments working on wireless technology like cordless phones, Wi-Fi, Bluetooth and the cell phones.
o Disconnect electric and electronic equipments from the power supply when not in use, especially in areas of prolonged occupancy.
Further, the list of equipments/appliances generally used in and around working/living space is placed below for appreciation of EMR radiations: -
RF Sources i.e. the transmitting towers such as AM/FM radio towers, TV towers, cell phone towers transmitting EMR continuously.
Cell phone which is ON but not in use also radiates and Wi Fi (Wireless Internet)
Cordless phone
Wi-max
Other wireless devices
CFL (Compact Florescent Light) bulbs
Neighboring EMR sources that are located next to shared walls.
Computers and laptops
Air conditioning systems
Refrigerators
Electrical heating systems/ Microwave Ovens
Power generators and voltage converters
Stereo and home entertainment systems
Fans
This list is only indicative and not exhaustive and there can be additions to it.
From the view point of effective communication, providing of mobile towers in a township/ office complex is an essential requirement and thus should be carefully planned.
The mobile tower generates and transmits high frequency radiations; so more care is needed for their placement. It should be ensured that the building identified to mount the tower should be the tallest in the vicinity and should not have adjoining buildings on which proposed or existing habitable floors are within close range.
or
Mobile Tower should be mounted on the highest sanctioned building in an area.
In regular practice that many cellular operators mount their antenna on a single tower along with other operators which increase the effects of EMR manifolds and should thus be avoided as far as possible. Else height of the tower should be increased.
Besides, Substation Equipments like Transformer, DG set etc. are also to be provided for fulfilling the bulk power requirement of the building and should be suitably placed for electrical safety as well as for mitigating effects of EMR. However, as these are low frequency devices, their placement is too decided more from electrical safety point of view than EMR.
In addition, various light sources inside the living/working spaces, UPS, servers, various other equipments running on Wi-Fi may also emit EMR. Hence their placement inside the building also needs careful consideration. Thus, in a built environment of considerable human occupancy, following broad guidelines should be adopted for placement of utility equipments/ appliances serving the building as a whole:
Equipments external to the building: Mobile Towers
|Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019|
Annexure “F”
Annexure & Appendices
Location of communication towers is governed by radio frequency system adopted and as far as possible cellular operator should try to avoid residential areas. However, where it is not possible to avoid these, they should request for permission from the appropriate authority for installation on roof top of the tallest existing buildings.
(i) First preference should however, be given to the location of tower in the commercial areas or other public areas.
(ii) Where it is not possible to avoid the location of this tower in residential, area possibility should be explored to locate them in green belt s within residential sectors or open spaces/community buildings in the sectors.
Where it is not possible to find such suitable space mentioned at Sr. No. (ii) above, tower should be permitted on the roof top of residential buildings subject to the condition that a structural safety certificate from a certified Structural Engineer has been obtained.
Such tower s should no t be permitted on occupied buildings, however if inevitable, a Steel/Metal frame of 6 M height over the roof level of the last habitable floor of the building should be provided to accommodate the tower and its associate d units.
Indoor Equipments/Appliances:
Electrical Switchboards: Unless otherwise amended by Barrier-free access regulations to such fixtures, they should be mounted as per existing stipulations laid down in CPWD General Specifications for Electrical Works-Part I Internal 2013.
Wireless Routers : Within the housing unit, the vertical mounting height of the router should be not less than 4 feet and should be kept in the Drawing / Dining zone and not within the zones of longer period of occupancy e.g. Bedrooms.
In non – residential units i.e. office spaces these routers should be kept as much away as possible and should be switched off when not in use.
Server Room: Occupied Work-stations should be at least 5 meters away from the server room or associated equipments. If people are sitting in the same room, they must wear protective gear and should not have prolonged exposure.
Computer: Should be placed in the most isolated place in a dwelling unit, while in an office space, it should not be less than 2.5 feet away from the person using it.
UPS: Should also be placed in the most isolated place in a dwelling unit, while in an office space it should not be less than 2.5 feet away from the person using it.
|Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019|
Annexure “F”
Annexure & Appendices
Mobile Phone: It usually remains with the user all the time. The only time it is kept away is when it is being charged. Thus mobile should be charged from a remotely located power point. It is thus preferable to provide a charging station in almost every working/living space at a location, as far as permissible from living space considerations.
Light sources: Usually, sun as a source of natural light is the biggest source of electromagnetic radiations. However, the atmosphere surrounding us provides a natural shield from electromagnetic radiations. In this context, the light sources used inside a living/working space should be given careful consideration from the point of view of Electromagnetic Radiations. Many luminaries available presently, like Fluorescent tubes, compact fluorescent lamps, LED lights etc. are used in working / living spaces. So their use should not only be determined from the point of view of energy conservation but also from the point of view of Electromagnetic Radiations. For this purpose recommendations of the manufacturers should serve as proper guidelines.
Table below summarizes appropriate placement of equipments /appliances in the built environment:
To Provide Facilitates in the Public Building excluding Domestic Buildings for Differently-abled Persons
1. Definitions
Ambulant Disabled People: Disabled who are able to walk but who may depend on prostheses (Artificial Limbs) orthoses (Calipers), Sticks, crutches or walking aids.
Non-Ambulant Disabled People: Disabled people with impairments that confine them to wheelchair.
Wheel Chair: Chair used by disabled people for mobility.
Size of small wheel chair: 750 x 1050 mm
ii) Size of large wheel chair: 800 x 1500 mm
2. Scope
These bye-laws are applicable to public buildings and exclude domestic buildings.
Building which shall provide access to ambulant disable and Non-Ambulant disabled are listed below. Distinction is made for buildings to be designed for the use of large wheel chairs and small wheel chair.
3. Building to be designed for Ambulant Disabled People
Higher Secondary School, Conference Hall, Dance Halls, Youth Centres, Youth Clubs, Sport Centres, Sport Pavilions, Boat Club Houses, Ice Rinks, Bowling Centres, Swimming Pools, Police Stations, Law Courts, Courts Houses, Sport Stadiums, Theaters, Concert Halls, Cinemas, Auditorias, Small Offices (the maximum plinth area 1400 sq.mt) Snack Bars, Cafes and banqueting rooms (for capacity above 50 dinners).
i) In sport stadiums provisions shall be made for non-ambulant spectators (small wheel chair)
ii) @ 1:1000 up to 10,000 spectators and @ 1:2000 for spectators above 10,000.
iii) In Theaters, Concert Halls, Cinemas and Auditoria provisions shall be made for non-ambulant spectators
(Small Wheel Chairs) @ 1/250 up to 1000 spectators and 1/500 for spectators above 1000.
4. Building to be designed for Non-Ambulant Disabled People
Schools for physically handicapped, cremation, buildings as mentioned in 3, Botanical Gardens, Religious Buildings, Old People Clubs, Village Halls, Day Centers, Junior Training Centres, Post Offices, Banks, Dispensaries, Railway Stations, Shops, Super Markets, and Departmental Stores.
Notes:Large wheel chair criteria shall be applicable on ground floors of the following building, post offices,
banks, dispensaries, railway station, shops, supermarkets, and departmental stores.
5. Building to be designed for Non-Ambulant People (using small wheel chairs)
Public lavatories in Tourist Sports, Clubs Motels, Professional and Scientific Institution, Museum, Art Galleries, Public Libraries, Laborites, Universities, Collage for further Education, Teachers Training Colleges, Technical College, Exhibition Halls Dentist Surgeries, Administrative Department of the Hospitals, Service Stations, Car Parking, Buildings Airports Terminals, Bus Terminals, Factories Employing Handicapped for Sedentary Works, Large Offices, (with plinth area abode 1400 sq.mt.), Tax Offices, Passport Offices, Pension Offices, and Labour Offices, Cafes, Banqueting Rooms and Snack Bars (For capacity above 100 dinners).
6. Buildings Requirements:
All Building requirements for building projects proposed under this category shall be conforming to Annex D, Part 3 of NBC 2005.
Appendix “H”
Annexure & Appendices
Appendix “H” (Bye laws: 7.10)
Regulations for Resettlement and Slum In-stitu Upgradation
1. Density
The net density shall be up to 250 tenements per hectare.
Minimum Plot Size
The Minimum Plot Size shall be 25 sq.mt. However, it can be 18 sq.mt. with 100% coverage provided 7 sq.mt. per tenement is clubbed for cluster space.
External walls
115 mm thick external brick wall with or without plaster shall be permitted.
Staircase
Single flight staircase without landing between the two floors shall be permitted.
Pathways
The width of path ways shall be as follows:
2 meters width for pathways up to 30 m in length.
2 meters width for pathways up to 50 m in length
Flushing System:
In water closets flushing system shall not be essential and toilets without this provision may be permitted.
Water closets pan size:
213
The water closets seat shall be of minimum 46 m (18 inches) in length.
Septic tank and leaching pit (soak pit)
A septic tank shall be provided with capacity 141.6 m liters (five cubic feet) per capita, where the municipal services are likely to be available within four or five years or so, pour flush water seal latrines (NEERI type) shall be permitted, where the municipal sewage system is not available and the water table in the area is not high.
∥Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019||
Appendix “I”
Annexure & Appendices
Appendix “I” (Bye laws: 13.5, Table 13.4)
Categories of Materials of storage for Warehouses as per combustion risk A. Non-combustible materials:
Articles (which are Non- Combustible, Non -Flammable, Non -Corrosive, Non -toxic, Non-poisonous, Non-Explosive) such as Cement, brick, mortar, hardware items, metals in solid bar/metal goods (excluding those having melting point below 1000o C)
B. Combustible Materials in following 4 sub categories
Category
Material Specifications
Stacking Height
Medium (in m)
High (in m)
Category I
Articles such as Carpets, Non synthetic/synthetic yarn and fabrics. Mechanical and electrical goods (dominantly metal parts), Glassware and crockery, fiberboards, groceries, metal goods, Papers other than those listed under categories Moderate and High, Powdered and canned foods, Plastic/glass bottles containing non- flammable liquids, etc.
Explanations:
(i) The deflector of the sprinkler fitted in the ceiling shall be at more than 1.5 m from the goods stored below. However, in case of jute storage, no jute stock shall reach within 2 m of the deflectors of the sprinkler heads. (ii) In case of storage in racks or shelves, if the height of storage is more than what is specified, intermediate sprinklers shall be provided for each shelf/rack in addition to the ceiling sprinklers and overall design density and AMAO shall be maintained as per Table 5 of IS: 15105. (iii) The aisle width between the storage stacks shall not be less than 2.5 m and the maximum area of each storage stack shall not be more than 15.0 m<sup>2</sup>. If these parameters are exceeded, the design density applicable shall be loaded by 2.5 L/min/m<sup>2</sup>. (iv) In case of mixed storage (both moderate and high hazard storage) in buildings, the parameters will be governed by the most hazardous occupancy
Goods stored not higher than what is stated above for the appropriate category or not higher than the eaves height of the roofs or within1 m of a flat ceiling whichever is the lowest shall be regarded as moderate hazard storage. If the above conditions are not met, the risk shall be regarded as high hazard storage
Notes:
Any new use which increase the number of occupants to a figure comparable with other classes of occupancy shall change the classification of the building to that of the new use (for example, Warehouse used \ for office purposes).
Ware house buildings shall not include any article which is highly combustible or explosive materials or products which are liable to bum with extreme rapidity and or which may produce poisonous fumes or explosions for storage, handling and which involve highly corrosive, toxic or noxious alkalis, acids or other liquids or chemicals producing flame, fumes and explosive, poisonous, irritant or corrosive gases; and for the storage, handling of any material producing explosive mixtures of dust which result in the division of matter in to fine particles subject to spontaneous ignition as such buildings fall in Hazardous Building Category.
Annexure “F”
Annexure & Appendices
Annexure-F
Structural stability of the said building should be calculated with the overall loading of such metal/steel frames mounted atop and ‘Structural stability certificate’ should be submitted by a registered structural engineer with the application for permission of building (pre-de sign) or installation (post-design)
Transformers: In addition to the fenced ionized area around a transformer, neighborhood level congregation activity areas should not be planned/permitted within 3M of the fence.
Diesel Generators: The location of the Generator within the Plot premises should not be adjacent to any habitable / community / recreational activity within a radius of 3M.
Sr. No
Equipment
Minimum safe distance
1
Mobile Towers
6 m height over the roof level of the last habitable floor of the building.
2
Transformers
3 m
3
Electrical Switchboards
No Change
4
Wireless Routers
4 feet (1.2 m)
5
Server Room
5m
6
UPS
2.5 feet (0.75 m)
7
Diesel Generators
Radius of 3 m
8
Mobile Phone
2 feet (0.6 m)
9
Computer
2.5 feet (0.75 m)
10
Laptop
2.5 feet (0.75 m)
11
UPS
2.5 feet (0.75 m)
12
Wireless Router modem
4 feet (1.2 m)
13
Server room
5 m away from workstations
Note:Intensity of Electromagnetic Radiations decreases with increase in distance from the radiation source. So as to minimize exposure maximum possible distance should be kept.
|Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019|
4
6.5
Category II
Articles such as Batteries, Baled cotton/synthetic fibers, Books, Baled cork, Baled waste paper, Cartons containing alcohols (in cans/bottles), Cartons of canned lacquers which dry by solvent evaporation, Chipboard, Cardboard rolls (horizontally Stored), Cereals/Grains/Foodstuff/ Flour/Sugar in sacks, Cellulose/ Cellulose pulp, Electrical goods other than those stated in Category low, Flammable liquids in non- combustible containers, Leather goods, Palletized liquor stocks, Plastics (non-foamed, other than cellulose nitrate), Rolled pulp and paper and asphalted paper (Horizontal storage), Veneer sheets, Wooden patterns, Metal/wooden furniture with plastic seats, etc
3
5.5
Category III
Articles such as Bitumen/Wax coated paper, Candles, Carbon black, Card board rolls (vertically stored), Charcoal, Coal> cellulose nitrate, Foamed plastic and foam rubber products, Flammable liquids in combustible containers, Linoleum products, Matches, Plastics other than those stated in Category Moderate, Rolled pulp and paper and asphalted paper (vertical storage), Rubber goods including tyres and tubes, Sawn timber, Ventilated wood stacks, Waxed and asphalt coated papers and containers in cartons, Wood wool, wooden pallets and flats (idle), Ail materials having wrappings or pre-formed containers of foamed plastics, etc.
2
4.5
Category IV
Offcuts and random pieces of foamed plastic or rubber rolls of sheets of foamed plastic or foamed rubber, Foam mattress, Expanded polystyrene packaging, Foam upholstery, etc