9.1 The RWH system
The harvesting of rainwater simply involves the collection of water from surfaces on which rain falls, and subsequently storing this water for use. The rainwater collected can be stored for direct use or can be recharged into the underground aquifers. In scientific terms water harvesting (broadly) refers to collection and storage of rainwater from the rooftops. This also restricts evaporation and seepage into building foundations. All buildings having a plot size of 100 sqm while submitting thebuilding plans for sanction shall mandatorily include the complete proposal of rainwater harvesting.
A rainwater harvesting system consists of:
i. Roof catchment
ii. Gutters
iii. Down pipes
iv. Rain water/ Storm water drains
v. Filter Chamber
vi. Storage Tanks/ Pits/ Sumps.
vii. Ground Water recharge structures like pit, trench, tube well or combination of above
Rainwater Harvesting is a way to capture the rain runoff, store that water above ground or charge the underground aquifers and use it later. This happens naturally in open rural areas. But in congested, overpaved metropolitan cities, there is a need to devise methods to capture the rain water. The rainwater that is incident on the surface/ roof top is guided to bore wells or pits or new/old/ abandoned wells through small diameter pipes to recharge the underground water which can be used later whenever required.
Rainwater can be harvested to the extent of 55,000 liters per 100sq. meters area per year from rooftops.
9.2 Objectives
9.2.1 The objective of the Rain Water Harvesting System is to ensure the (best) possible beneficial use of ground water endowment on the entire urban area of Arunachal Pradesh.
9.2.2 To ensure that the maximum utilization of rainfall as possible through water harvesting, either by recharging it into the ground water aquifers or storing it for direct use.
9.3 The expected outcome
9.3.1 Recharge ground water,
9.3.2 Preserve and enhance surface water bodies in urban areas,
9.3.3 Provide back-up supplies during dry spell, draughts or periods of main supply break down.
9.3.4 Mitigate urban floods,
9.3.5 Improve ground water,
9.3.6 Provide environmental and ecological benefits to the urban area including fostering bio diversity.
9.3.7 Augment soil moisture for urban greenery.
9.3.8 Use rain water for urban agriculture and vegetable production.
9.4 Rainwater harvesting techniques:
There are two main techniques of rain water harvestings.
99
a. Storage of rainwater on surface for future use.
b. Recharge to ground water.
Chapter 9
Rain Water Harvesting
The technical aspects and options of Rainwater harvesting from which the city authorities can assess and choose to adopt are placed at Annexure-“E” to the bye-laws.
9.5 Harvesting provisions in various Building categories:
All buildings in a city contribute to the rainwater runoff during the monsoon and hence such runoff can be harvested for water reuse/recharge.
The indicative provisions of rainwater harvesting in various buildings types are:
| Category/Use | Area of Plot (sq.m.) | Provisions to be made | Other conditions |
| Residential Plotted | Houses | ||
| New Proposals | 100 &above | Construction of Rain Water Harvesting Structure. | Shall have emphasis on both storage &reuse. |
| Group Housing | |||
| New Proposals | All plot sizes | i. Construction of Rain Water Harvesting Structure. ii. Concrete paving to be avoided and permeable materials are to be used for all open parking spaces. | Should indicate the system of Strom Water Drainage, Rain Water Harvesting Structure and Recharging Well |
| Public and semi-public buildings | |||
| All Proposals | All plot sizes | i. Shall have Rain Water Harvesting Structure and storage ii. Shall have Recharge pits | Shall have emphasis on both storage and reuse. |
| Commercial / Mixed use | |||
| All Proposals | All plot sizes | i. Construction of Rain Water Harvesting Structure. ii. Soft landscape provisions and open spaces with Percolation pits. iii. Common treatment plant to be made part of the integrated development, funded by sale of commercial space. | Should indicate the system of Strom Water Drainage, Rain Water Harvesting Structure and Recharging Well Shall have emphasis on both storage and reuse. |
| Industrial | |||
| All proposals | All plot sizes | i. Construction of Rain Water Harvesting Structure. ii. Soft landscape provisions and open spaces with percolation pits. iii. Use of abandoned bore wells for recharging of ground water. iv. Common treatment plant to be made part of the integrated development funded by sale of commercial space. | Should indicate the system of Strom Water Drainage, Rain Water Harvesting Structure and Recharging Well. Provision should be made not to inject Contaminated water into recharge structures in industrial areas and care is to be taken to keep such structures away from sewer lines, septic tanks, soak pits, landfill and other sources of contamination. |
9.7 Ground Water Recharge
Recharging of ground water should be made mandatory not only for residential buildings but for all types of buildings, including Group Housing Societies having a plot area 500 sqm and above.
The Ground Water Recharge should also be mandatory for open spaces like parks, parking, plazas and playgrounds. The harvesting and recharge structures could be constructed by the Authority with the involvement of community based organizations like Resident Welfare Associations.
9.8 Enforcement and Monitoring
a. The Authority shall constitute a Rainwater Harvesting Cell which will be responsible for enforcement and monitoring of the provisions of Rainwater Harvesting. The cell shall employ qualified persons who are well versed with the interpretation of Building Bye Laws and responsible for enforcement as well as monitoring the functioning of the Rainwater Harvesting System.
b. The Authority shall include inspection of Rainwater Harvesting Structures before issuing Completion Certificates or NOCs for service connections to the property.
c. Set an example in the city by ensuring that Rainwater is harvested in the properties /assets owned by them including public buildings, markets, community centers, parking spaces, roads and parks etc.
d. The Authority shall also establish a mechanism to monitor 100% of RWH provisions in all the buildings above 1000 sq.m. with annual physical verification, while buildings less than 1000 sq.m. can be monitored on the basis of 10% random survey by competent authority.
e. With regard to open public spaces viz., Parks, playgrounds etc. the implementation of provision rainwater harvesting may be done with the help of Residents Welfare Associations, Community Building Organization and Non-Governmental Organizations.
f. The Authority shall ensure earmarking budgetary provision for the creation and maintenance of rainwater harvesting structures in public spaces owned and maintained by them, like parking spaces, parks, plazas etc.
g. The practice of incentives and penalties to promote rain water harvesting shall be formulated by the local authority based on best practices. Authority shall design its own incentive and penalty systems, considering the water level and scarcity.