Individual construction proposals should not generally require separate clearances from various authorities each time. Such clearances should be integrated into the DCR of the Master/Development Plan of the concerned city. The areas unaffected by any of the restrictions should be clearly marked out and mapped, preferably on a GIS platform. Area zones of differential control regulations (within the city) by any of these agencies may also be mapped accordingly. This will result in a composite map of the city with various control regulations as per the various agencies clearly marked on the map. Thus, the sites which are located outside these restricted/regulated areas would not require availing clearance from the respective authorities, thereby reducing the clearance process significantly.
Following are the clearances which should be integrated into the city Master Plan-
Chapter 13
Streamlining of Building Plan Approvals
| Sl. No | Name of Agency | Type of Clearance | Area of Influence | |
| 1 | National Monuments Authority through Competent Authority | Ancient Monument Approval | As prescribed in the AMASAR (Amendment and Validation) Act, 2010 for protection of monuments | |
| 2 | Ministry of Environment | Environment Clearance (EC) | As prescribed in the statutory provisions for EIA and clearance based on the size of the project in accordance with Environment Protection Act,1986 | |
| 3 | Central Ground Water Authority | Bore well Registration Certificate | As per Guidelines/criteria for evaluation of proposals/ requests for ground water abstraction, 2012 | |
| 5 | Ministry of Civil Aviation | AAI Height NoC | Critical and non-critical area as identified by AAI | |
| 6 | Ministry of Defense | Defense Clearance | Areas in and around Defense Establishments as identified by MoD. | |
| 7 | NOC (if near sea/coastal areas) | Areas under the CRZ regulations. | ||
| 8 | NHAI/PWD | Road access | Buffer zones as prescribed by NHAI along National Highways. | |
| 9 | Ministry of Railways | Area clearance | Buffer zones as prescribed by Railways along the Rail tracks/depots/yards etc. | |
Efforts are on at the Government of India level to coordinate with all the central ministries and their organizations so that they streamline their own internal processes to issue no objection etc. where ever required by law. The efforts are mainly focused on delegating the powers at appropriate levels, establishing an online application process for time bound delivery, creating public awareness about their requirements, reviewing the restrictions and reducing them, sharing the data and norms with local authorities to be incorporated in DCR etc.
Recognizing the concern for streamlining the procedures for clearances to be obtained from various departments in least possible number of procedures and number of days, the following model is given which suggests that the entire process of Pre and Post-Construction approvals should be completed within one month:
| S.l No. | Type of approval | Approving Authority | Stage of project | Normal Duration (Days) | Reduced Duration (Days) | Activity Sequence |
|---|---|---|---|---|---|---|
| A | Intimation of Disapproval (IoD) | Development Authority/ Municipality | Pre-construction | 30 | 5 | Start Activity |
| B | Site & Building Layout approval | Development Authority/Municipality | Pre-construction | 30 | 5 | Following A |
| C | NOC (if near sea/coastal areas) | Coastal Zone Management Authority | Pre-construction | 30-60 | 10 | Following B |
| D | Road access | Highway/APPWD | Pre-construction | 30 | 10 | Following B |
| E | Ancient Monument approval | Archaeological Survey of India (ASI) | Pre-construction | 30 | 10 | Following B |
| F | Environment Clearance | Deptt. of Env. & Forest or Ministry | Pre-construction | 180 | Only for large project | Following B |
| G | Bore well Registration Certificate | Central Ground Water Authority | Pre-construction | 15 | 5 | Following B |
| H | Fire Fighting Scheme Approval | Fire Department | Pre-construction | 30 | 15 | Following B |
| I | AAI Height NoC | Civil Aviation Department | Pre-construction | 30-60 | 10 | Following B |
| J | Defense Clearance | Ministry of Defense | Pre-construction | 180 | 10 | Following B |
| K | Building Permit Issue (All NOCs) | Development Authority/ Municipality | Pre-construction | 30 | 1 | Max of after C-J |
| Sub Total | 26 (Max) |
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh Arunachal Pradesh Building Byelaws 2019|
Chapter 13
Streamlining of Building Plan Approvals
| S.l No. | Type of approval | Approving Authority | Stage of project | Normal Duration (Days) | Reduced Duration (Days) | Activity Sequence |
| L | Electric Substation NoC (substation /transformers in the building) | Electricity Distribution Authority | Preconstruction as well as during construction | 15 | 5 | After K |
| M | Damp Proof Certificate(On Site) | Development Authority or Municipality | During construction | 7 | 3 | After K |
| N | Pollution Clearance | State Pollution Control Board | During Construction | 30-60 | 5 | After L |
| Ø | Construction Complete | Construction Time depends on the project Scale and Size | ||||
| O | Building completion Certificate | Development Authority/Municipality | Post construction | 30-60 | 5 | After Ø |
| P | Service Plan Clearance and Service Connections | Service Departments/ Parastatals | Post construction | 30 | 10 | After O |
| Q | Occupancy Certificate | Development Authority/ Municipality | Post construction | 15 | 2 | After P |
Explanatory Notes:
-
The above Table and Chart indicates that the processes after the applicant applies for building approval with clear land title and possession of land. Hence, clearances related to CLU and Land Title has not been considered.
-
The table illustrates the duration of clearances obtained in Normal course and suggests the reduced duration of 26 days (Pre-Construction) if the Approving Authority adopts online sanctions.
-
Clearances indicated at S Nos. C-J are concurrent with applications at the pre-construction stages, wherein their process of approval can be taken up simultaneously.
-
Clearances indicated at S Nos. L-N are concurrent with applications during-construction stage, wherein their process of approval can be taken up simultaneously.
-
S No. P has to be linked with S No. O, once applicant receives the Completion Certificate, service plan clearances and connections would be deemed to be sanctioned.
13.3 Clearances at the Local Authorities
The Town Planning & Urban Local Bodies shall ensure clearances in minimum possible time. Clearances indicated at Sl. No. A,B,H,K,L,M,N,O,P, and Q have to be obtained at the local level and all efforts have to be made to sanction the building plan using online application procedures.