(i) Every applicant or builder or owner shall submit a notice regarding his intention to commence the foundation work of the proposed multi-storied building to the Authority through authorized technical persons. The said notice shall be accompanied by the approved plan and should be in Form-V.
(ii) Soon after the receipt of the notice referred to in sub- clause (1) above, the Authority shall send a team of officers including, a civil Engineer, Architect and Town Planner, to the proposed building site and the layout for foundation of the proposed multi-storied building shall be made in presence of those officers. The team shall also submit a report to the Authority to the effect that the layout has been made as per the approved plan.
Department of Town Planning & ULBs, Govt. of Arunachal Pradesh|| Arunachal Pradesh Building Byelaws 2019
Chapter 17
Multi-Storied Buildings and Group Housing Schemes/Apartments: Additional Requirements
(iii) During or soon after the construction of the foundation work of the multi-storied building, the Municipal Chairperson, Municipal President of the Authority or his representatives or independent Engineer/ Architect appointed by Authority shall inspect the construction to ensure that the setbacks, coverage, basement if any, and foundation standards are according to the approved plan.
(iv) The applicant / builder shall submit periodic progress report after casting of each floor slab in Form-VIII.
17.4 Liability of Defective Construction
(i) For defective constructions, the Authority shall sue the owners, builders, architects, and the engineers for both civil and criminal liabilities, besides taking action under these Bye-Laws.
(ii) Without prejudice to the provisions of the Act, the actions to be taken by the Authority shall include notices, cancellation of permission, stopping construction and removal of unauthorized constructions. Such actions shall be notified.